Carolina Power & Light Co. v. United States

82 Fed. Cl. 23, 2008 U.S. Claims LEXIS 134
CourtUnited States Court of Federal Claims
DecidedMay 19, 2008
DocketNo. 04-37C
StatusPublished
Cited by28 cases

This text of 82 Fed. Cl. 23 (Carolina Power & Light Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carolina Power & Light Co. v. United States, 82 Fed. Cl. 23, 2008 U.S. Claims LEXIS 134 (uscfc 2008).

Opinion

OPINION AND ORDER

WHEELER, Judge.1

Plaintiffs Carolina Power & Light Company (“CP & L”) and Florida Power Corporation (“FPC”) claim damages of $91,029,704 from Defendant caused by the failure of the Department of Energy (“DOE”) to collect and dispose of spent nuclear fuel beginning January 31, 1998 under the terms of DOE’s Standard Contract. CP & L and FPC are wholly-owned subsidiaries of Progress Energy, Inc., a public utility in the southeast United States. Plaintiffs’ damages consist of costs incurred in mitigation of DOE’s partial breach of the Standard Contract. This Court has jurisdiction over Plaintiffs’ claim pursuant to the Tucker Act, 28 U.S.C. § 1491(a). See PSEG Nuclear, LLC v. United States, 465 F.3d 1343 (Fed.Cir.2006). Defendant’s liability for partial breach of contract has been established. See Maine Yankee Atomic Power Co. v. United States, 225 F.3d 1336, 1337-40 (Fed.Cir.2000) (“Maine Yankee”); N. States Power Co. v. United States, 224 F.3d 1361, 1367 (Fed.Cir.2000). Thus, only damages are at issue.

CP & L and FPC (collectively “Progress Energy” or “Plaintiffs”) operate five nuclear reactors at four power plants in North Carolina, South Carolina, and Florida. The power plants are known as Harris, Brunswick, Robinson, and Crystal River. Plaintiffs’ damages claims fall into five categories: (1) $208,120 to complete a study for a dry storage facility known as an Independent Spent Fuel Storage Installation (“ISFSI”) at the Brunswick plant; (2) $32,734,951 to activate two additional spent fuel storage pools at the Harris plant; (3) $16,975,182 to ship spent fuel from the Robinson and Brunswick plants to the Harris plant; (4) $36,436,059 to construct and load the Robinson plant ISFSI; and (5) $4,675,392 to design, construct, and replace spent fuel racks at the Crystal River Plant.

The United States Court of Appeals for the Federal Circuit has held that nuclear utilities may recover proven incurred costs as mitigation damages for DOE’s partial breach, but may not recover forecasted future costs. Indiana Michigan Power Co. v. United States, 422 F.3d 1369, 1375-77 (Fed.Cir.2005) (“Indiana Michigan”). Consequently, Plaintiffs have limited their claims in this case to costs incurred through December 31, 2005. In accord with the Restatement (Second) of Judgments § 26 (1982), Plaintiffs retain the right to bring later actions on claims for damages incurred thereafter. See Indiana Michigan, 422 F.3d at 1378.

Defendant opposes Plaintiffs’ claims in part, but acknowledges that Plaintiffs at a minimum are entitled to recover $44,339,037. Defendant accepts responsibility for an additional $16,962,904, increasing the total to $61,301,941, if the Court agrees with Plaintiffs’ view of DOE’s obligations under the Standard Contract. Defendant’s objections to Plaintiffs’ damages generally are that: (1) Plaintiffs have not properly credited DOE for costs they would have incurred absent the breach; (2) Plaintiffs have not shown that certain costs increased incrementally as a result of the breach; and (3) certain costs were not caused by the breach, or are otherwise unsupported or unallowable. Defendant agrees that Plaintiffs’ claimed costs were foreseeable at the time of contracting, and that the incurred costs were reasonable.

The Court conducted a nine-day trial in Washington, D.C. during November 5-16, 2007. The witnesses in order of appearance were: Lou Martin, former manager of nuclear fuel at Progress Energy; Steve Edwards, supervisor of Progress Energy’s Spent Fuel Management Unit; Robert Kunita, former CP & L senior engineer; Alva Wayne Wor-thington, Progress Energy’s lead engineer of the Spent Fuel Management Unit; Michael Culver, a Progress Energy reactor engineer; Dean Tibbitts, a Progress Energy engineer; [27]*27Tom Lehmann, former FPC nuclear chemistry manager; Ted Williams, superintendent of major projects at Progress Energy; Tom Pollog, a DOE engineer in the Office of Waste Management within DOE’s Office of Civilian Radioactive Waste Management (“OCRWM”); Robert Morgan, DOE’s former director of OCRWM; David Zabransky, a nuclear utility specialist in the OCRWM’s Office of Waste Management; Mike Calvello, manager of Nuclear Generation Business Services at Progress Energy; Defendant’s experts, Gregory Maret and Larry Johnson; and Michael Lawrence, DOE’s former director of the OCRWM.

The Court also accepted the parties’ designations of previous deposition and trial testimony from eight witnesses who were unable to testify at trial: Lake H. Barrett, DOE’s former deputy director of the OCRWM; Alan Brownstein, DOE’s former director of the OCRWM Regulatory Coordination Division; Christopher Kouts, DOE’s former director of the OCRWM Office of Waste Management; Loring E. Mills, former executive with the Edison Electric Institute (“EEI”); Ronald Milner, former chief operating officer of the OCRWM; Robert M. Rosselli, former director of DOE’s Resource Management Division; Nancy H. Slater, former team leader in the OCRWM Regulatory Coordination Division; and Victor W. Trebules, former director of the Office of Project Control at OCRWM. The parties filed post-trial briefs on January 22, 2008, and reply briefs on February 19, 2008. The Court heard closing arguments on April 4, 2008.

For the reasons explained below, the Court finds that Plaintiffs are entitled to recover $82,845,926 in mitigation damages through December 31, 2005. The Court agrees in large part with Plaintiffs’ interpretation of DOE’s Standard Contract. In furtherance of the purposes of the Nuclear Waste Policy Act of 1982, 42 U.S.C. §§ 10101-10270 (1982), the intent of the Standard Contract was for DOE to begin collecting and disposing of spent nuclear fuel beginning January 31, 1998, and to do so in sufficient quantities so that nuclear utilities would not need to provide any additional storage facilities at individual reactor locations. DOE contemplated the establishment of two central repositories, and an interim storage facility if needed, where the spent fuel would be stored. One of these repositories was to be located at Yucca Mountain, Nevada. As events unfolded, the central repositories were not established, and DOE did not collect or dispose of any spent fuel beginning January 31, 1998. To date, DOE has yet to collect and dispose of any spent fuel, even as nuclear plant owners have been paying billions of dollars in fees to DOE under the Standard Contract. Plaintiffs alone have paid DOE $661 million in fees through December 31, 2005.

The Court has disallowed four elements of Plaintiffs’ damages claim. For two such items, the Crystal River re-rack project ($4,675,392) and the Harris component cooling water system upgrade ($1,166,640), the Court concludes that Plaintiffs would have incurred these expenses for other reasons absent DOE’s partial breach. For various manual journal entries challenged by Defendant ($345,701), Plaintiffs have not met their burden of showing what these expenses were for, or whether they were caused by DOE’s breach. Plaintiffs’ claim for Allowance for Funds Used During Construction (“AFUDC”) ($1,996,045) is in reality a claim for interest against the Government, and is unallowable by law. See 28 U.S.C. § 2516(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bishay v. United States
Federal Claims, 2019
Entergy Gulf States, Inc. v. United States
125 Fed. Cl. 678 (Federal Claims, 2016)
System Fuels, Inc. v. United States
125 Fed. Cl. 331 (Federal Claims, 2016)
Dairyland Power Cooperative v. United States
123 Fed. Cl. 220 (Federal Claims, 2015)
Alabama Power Company v. United States
119 Fed. Cl. 615 (Federal Claims, 2014)
Carolina Power & Light Co. v. United States
115 Fed. Cl. 57 (Federal Claims, 2014)
Yankee Atomic Electric Company v. United States
113 Fed. Cl. 323 (Federal Claims, 2013)
Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)
BPLW Architects & Engineers, Inc. v. United States
106 Fed. Cl. 521 (Federal Claims, 2012)
Power Authority v. United States
99 Fed. Cl. 661 (Federal Claims, 2011)
Entergy Nuclear Fitzpatrick, LLC v. United States
101 Fed. Cl. 305 (Federal Claims, 2011)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)
Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Arizona Public Service Co. v. United States
93 Fed. Cl. 384 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
Boston Edison Co. v. United States
93 Fed. Cl. 105 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
82 Fed. Cl. 23, 2008 U.S. Claims LEXIS 134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carolina-power-light-co-v-united-states-uscfc-2008.