Duke Energy Progress, LLC v. United States

CourtUnited States Court of Federal Claims
DecidedJanuary 7, 2019
Docket18-891
StatusPublished

This text of Duke Energy Progress, LLC v. United States (Duke Energy Progress, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duke Energy Progress, LLC v. United States, (uscfc 2019).

Opinion

In the United States Court of Federal Claims No. 18-891C

(Filed: January 7, 2019)

************************************* * DUKE ENERGY PROGRESS, INC. and * DUKE ENERGY FLORIDA, INC., * * Spent Nuclear Fuel; Nuclear Waste Plaintiffs, * Policy Act of 1982; CFC Rule 12; Motion * to Dismiss; Breach of Contract; v. * Collateral Estoppel; Foreseeability of * Damages. THE UNITED STATES, * * Defendant. * * *************************************

Brad Fagg, with whom were Paul M. Bessette and Jane T. Accomando, Morgan, Lewis & Bockius LLP, Washington, D.C., for Plaintiffs.

Jimmy S. McBirney, Trial Attorney, with whom were Joseph P. Hunt, Assistant Attorney General, Robert E. Kirschman, Jr., Director, Lisa L. Donahue, Assistant Director, Christopher L. Harlow, Kristen B. McGrory, and Melissa L. Baker, Trial Attorneys, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, D.C., and Jane K. Taylor, U.S. Department of Energy, Office of the General Counsel, Washington, D.C., for Defendant.

OPINION AND ORDER

WHEELER, Judge.

Plaintiffs Duke Energy Progress, LLC and Duke Energy Florida, LLC (collectively, “Duke”) seek damages for activities taken to mitigate the impact of the Department of Energy’s breach of contract relating to the acceptance and removal of spent nuclear fuel (“SNF”).1 Duke Energy Florida, LLC owns the Crystal River Unit 3 nuclear plant. Crystal River generated SNF as a byproduct of the reactor’s operation until October 2009 when

1 This is the fourth round of Duke cases before this Court arising out of DOE’s breach of the same contract. Duke shut the facility down for a scheduled maintenance and refueling outage. Duke prolonged the shutdown beyond this scheduled period after discovering a delamination, or concrete separation, at the facility. In February 2013, Duke retired the Crystal River facility. Duke alleges in its complaint that it incurred shutdown-related expenses that it would have avoided had the Government not breached the contract.

Currently before the Court is Defendant’s partial motion to dismiss Plaintiffs’ complaint. The Government asserts that the doctrine of collateral estoppel precludes Duke from re-litigating certain issues of fact and law conclusively determined during an earlier case relating to this contract. Defendant argues that Plaintiffs’ claim is incompatible with these already-established issues so that they cannot assert a claim for relief. For the reasons explained below, the Court DENIES Defendant’s partial motion to dismiss because Plaintiffs’ complaint does not present issues of law and fact identical to those litigated in the prior related proceeding.

Background

A. The Nuclear Waste Policy Act and Breach of the Standard Contract

Congress enacted the Nuclear Waste Policy Act of 1982, as amended, 42 U.S.C. §§ 10101 et seq. to address nuclear power plants’ disposal of SNF. Generally, the Act specifies that SNF generators and owners are responsible for interim SNF storage costs until DOE accepts the material. See § 10131(a)(5). Pursuant to the Act, DOE executed a Standard Contract for Disposal of Spent Nuclear Fuel (“Standard Contract”) with four of Duke’s plants, including the Crystal River facility. Under the Act and the Standard Contract, Duke agreed to pay into the Nuclear Waste Fund in exchange for DOE’s performance of spent fuel disposal services. DOE was required to begin accepting SNF no later than January 31, 1998 and continue acceptance and disposal until no further SNF remained at Duke’s facilities. To date, DOE has neither accepted nor disposed of SNF from any of Duke’s sites. Duke has sought damages for activities taken to mitigate the impacts of DOE’s breach of contract in successive rounds.2 B. The Delamination Event at Crystal River

During the third round of these related cases, Duke attempted to recover costs incurred at Crystal River. Duke began a scheduled outage at Crystal River in 2009 to begin a renovation designed to increase the plant’s power production capacity. Duke decided to self-manage the project, although this kind of undertaking typically is overseen by a professional consulting firm. During construction, Duke encountered a delamination in

2 See Indiana Michigan Power Co. v. United States, 422 F.3d 1369, 1378 (Fed. Cir. 2005) (holding that utilities are required to file successive actions for damages related to DOE’s breach of the Standard Contract within six years of incurring such damages). 2 Crystal River’s containment building. At this same time, Duke was building an Independent Spent Fuel Storage Installation (“ISFSI”) pad at Crystal River. Duke decided to suspend work on the ISFSI project following the delamination at Crystal River. Since the ISFSI was not completed, Duke stored its waste and fuel elsewhere at additional expense.

In the prior round, this Court considered the above facts and their impact on Duke’s ability to recover certain costs, and determined that:

Duke’s decision to self-manage the steam generator replacement project and the eventual delamination were not foreseeable results of [DOE’s] breach. Based on prior, similar projects, if Duke had retained a professional firm to assist in the engineering aspects of the project, it is likely that delamination problems would not have happened. Edwards, Tr. 199-201. . . . If the delamination had not occurred, work on the Crystal River storage installation would not have been interrupted, negating the continued need for dry storage. Edwards, Tr. 206, 209. Suspending the dry storage project resulted in the storage and contract termination costs that Duke claims. As this suspension was a result of the delamination and DOE had no involvement in the events leading to the delamination, these expenses are solely attributable to Duke.

Duke Energy Progress, Inc. et al v. United States, 135 Fed. Cl. 279, 289 (2017). Duke’s unforeseeable mismanagement of the project therefore broke the causal chain between DOE’s breach and Duke’s dry storage and contract termination expenses sought in round three. Accordingly, this Court denied Duke recovery for these costs.

C. The Present Dispute

Duke permanently retired Crystal River in February 2013. However, the last of the SNF was not removed from the Crystal River pool storage facility to the ISFSI until January 2018. As a result, Duke incurred post-shutdown costs for operations, maintenance, and security associated with the spent fuel pool in which the SNF was stored for this approximately five-year period (dubbed “wet-pool costs”). Duke argues that had DOE accepted the SNF when Duke shut down Crystal River in early 2013 as DOE was contractually required to do, Duke would not have incurred these costs. In its complaint, Duke seeks to recover these wet-pool costs for the period January 1, 2014 through a date yet to be determined.

The Government challenges these costs in its partial motion to dismiss, asserting that the doctrine of collateral estoppel limits its liability. In round three, this Court made findings on foreseeability, culpability, and causation relating to Duke’s dry storage and contract termination costs flowing from the Crystal River delamination. The Government claims that the same legal and factual issues from that earlier proceeding underlie Duke’s

3 current claim for wet-pool costs and bars the Court from hearing this claim as a matter of law.

Procedural History

Plaintiffs’ complaint begins the fourth round of cases arising from DOE’s breach of the same contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Carolina Power & Light Co. v. United States
573 F.3d 1271 (Federal Circuit, 2009)
Indiana Michigan Power Company v. United States
422 F.3d 1369 (Federal Circuit, 2005)
Carolina Power & Light Co. v. United States
115 Fed. Cl. 57 (Federal Claims, 2014)
Carolina Power & Light Co. v. United States
82 Fed. Cl. 23 (Federal Claims, 2008)
Carolina Power & Light Co. v. United States
98 Fed. Cl. 785 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Duke Energy Progress, LLC v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duke-energy-progress-llc-v-united-states-uscfc-2019.