Portland General Electric Co. v. United States

107 Fed. Cl. 633, 2012 U.S. Claims LEXIS 1519
CourtUnited States Court of Federal Claims
DecidedNovember 30, 2012
DocketNo. 04-09C
StatusPublished
Cited by8 cases

This text of 107 Fed. Cl. 633 (Portland General Electric Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portland General Electric Co. v. United States, 107 Fed. Cl. 633, 2012 U.S. Claims LEXIS 1519 (uscfc 2012).

Opinion

OPINION

BRUGGINK, Judge.

This is an action for partial breach of contract based on the Department of Energy’s (“DOE”) failure to pick up and dispose of spent nuclear fuel from plaintiffs’ nuclear-fueled electric generation facility beginning on January 31, 1998. A number of related cases have been decided by the court. Liability was established previously and is not at issue. See Me. Yankee Atomic Power Co. v. United, States, 225 F.3d 1336, 1337-40 (Fed.Cir.2000) (“Maine Yankee”); N. States Power Co. v. United States, 224 F.3d 1361, 1367 (Fed.Cir.2000). A two-week trial on damages was held October 31, 2011, to November 10, 2011, with additional testimony heard on January 5, 2012. The parties have submitted post-trial briefing, and post-trial oral argument was heard June 5, 2012. For the reasons set out below, plaintiffs are entitled to judgment pursuant to the rulings herein, but in an amount to be determined with further input from the parties.

BACKGROUND

Plaintiffs are joint owners of the Trojan Nuclear Power Plant (“Trojan”) near Rainier, Oregon. Portland General Electric Company operated Trojan on behalf of its fellow owners from 1975 until its shutdown and defueling in January 1993. The plant was originally licensed to operate until February 8, 2011, but was shut down earlier for reasons not related to defendant’s breach.

I. The Standard Contract

In 1982, Congress enacted the Nuclear Waste Policy Act (“NWPA”), 42 U.S.C. §§ 10101-10270 (2006). The NWPA codified the federal government’s “responsibility to provide for the permanent disposal of high-level radioactive waste and such spent nuclear fuel as may be disposed of in order to protect the public health and safety and the environment.” Id. § 10131(a)(4). The NWPA provided a process for storage and disposal of high level waste and spent nuclear fuel (hereafter referred to collectively as “SNF”). The NWPA authorized the Secretary of Energy to enter into contracts with owners and generators of SNF to dispose of such material. Pursuant to section 302 of the NWPA, the Standard Contract for the disposal of SNF was developed; it is published at 10 C.F.R. § 961.11 (2012).

On June 13, 1983, Portland General Electric Company (“PGE”), on behalf of itself, the Eugene Water and Electric Board, and Pacific Power & Light (a predecessor-in-interest of PacifiCorp), entered into a written contract with defendant known as the “Contract for Disposal of Spent Nuclear Fuel and/or High Level Radioactive Waste, U.S. Department of Energy Contract No. DE-CR01-83NE4406” (the “Standard Contract”). The material terms of the Standard Contract are published at 10 C.F.R § 961.11. In this contract, plaintiffs agreed to purchase DOE’s services for disposal of SNF produced by the Trojan facility. The contract required defendant to begin disposing of SNF by January 31, 1998. 42 U.S.C. § 10222(a)(5)(B). Defendant has not yet begun disposal of SNF. That start date was shared with the entire [638]*638nuclear industry. Article VI.B.l of the Standard Contract established the Oldest Fuel First (“OFF”) priority system. Under that schedule, in conjunction with the 1987 Annual Capacity Report1 rate, DOE should have picked up the last of Trojan’s fuel in 2010.

The Standard Contract also contains a provision allowing utilities, with DOE’s approval, to exchange their allocated SNF pickup dates. That provision states that the “Purchaser shall have the right to exchange approved delivery commitment schedules with parties to other contracts with DOE for disposal of SNF and/or HLW; provided, however, that DOE shall, in advance have the right to approve or disapprove, in its sole discretion, any such exchanges.” Standard Contract, art. V(E). In referring to this provision, the Federal Circuit noted, “[t]he Standard Contract included provisions setting priority for acceptance of waste (generally through an oldest fuel first (OFF) scheme) and allowed utilities to swap approved delivery commitment schedules (the Exchanges provision).” Pac. Gas & Elec. Co. v. United States, 536 F.3d 1282, 1285 (Fed.Cir.2008).

Courts have held that the NWPA created a duty on the part of the DOE to begin disposing of SNF. In Indiana Michigan Power Co. v. Department of Energy, 88 F.3d 1272 (D.C.Cir.1996), utility companies challenged DOE’s interpretation of the NWPA. The agency had taken the position that it would be unable to accept SNF by early 1998 and that it had no duty to do so in the absence of a functioning nuclear repository. The D.C. Circuit disagreed and held that section 302(a)(5)(B) of the NWPA created an obligation on the part of DOE, reciprocal to the utilities’ obligation to pay, to start disposing of SNF by January 31, 1998. Id. at 1277.

Despite the ruling in Indiana Michigan, DOE informed utility companies that it would not begin to collect the SNF by the 1998 deadline. The companies then sought a writ of mandamus to compel DOE to dispose of the SNF. In Northern States Power Co. v. United States Department of Energy, 128 F.3d 754, 756 (D.C.Cir.1997) (“Northern States I”), the D.C. Circuit reaffirmed its ruling in Indiana Michigan, noting that “[petitioners have established that they have a clear right to relief.” Id. at 756. The court refused to grant the broader mandamus relief sought by the utilities, however, noting that the Standard Contract “provides a potentially adequate remedy if DOE fails to fulfill its obligations by the deadline.” Id. Nevertheless, it held that the petitioners’ ability to enforce the contract “would be frustrated if DOE were allowed to operate under a construction of the contract inconsistent with [its] prior conclusion that the NWPA imposes an obligation on DOE ‘without qualification or condition.’ ” Id. at 759 (quoting Indiana Michigan, 88 F.3d at 1276). Consequently, the court ordered “DOE to proceed with contractual remedies in a manner consistent with the NWPA’s command that [DOE] undertake an unconditional obligation to begin disposal of the SNF by January 31, 1998.” Id. at 760. The mandamus “preelude[d] DOE from concluding that its delay [was] unavoidable on the ground that it has not yet prepared a permanent repository or that it has no authority to provide storage in the interim.” Id.

II. Plaintiffs’ Mitigation Efforts

Plaintiffs made the decision to close and then fully decommission the Trojan plant in 1993. By the mid-1990s, PGE had no confidence that DOE would begin picking up spent fuel in 1998 or anytime soon thereafter. Stephen M. Quennoz, Vice President of Nuclear Operations and Generation at PGE, testified that PGE estimated it to be at least 16 years before a DOE facility would be operational. Tr. 1637-38.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dairyland Power Cooperative v. United States
123 Fed. Cl. 220 (Federal Claims, 2015)
Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Carolina Power & Light Co. v. United States
115 Fed. Cl. 57 (Federal Claims, 2014)
Sacramento Municipal Utility District v. United States
109 Fed. Cl. 660 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
107 Fed. Cl. 633, 2012 U.S. Claims LEXIS 1519, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portland-general-electric-co-v-united-states-uscfc-2012.