Wisconsin Electric Power Co. v. United States

90 Fed. Cl. 714, 71 ERC (BNA) 1473, 2009 U.S. Claims LEXIS 697, 2009 WL 5178375
CourtUnited States Court of Federal Claims
DecidedDecember 18, 2009
DocketNo. 00-697 C
StatusPublished
Cited by24 cases

This text of 90 Fed. Cl. 714 (Wisconsin Electric Power Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisconsin Electric Power Co. v. United States, 90 Fed. Cl. 714, 71 ERC (BNA) 1473, 2009 U.S. Claims LEXIS 697, 2009 WL 5178375 (uscfc 2009).

Opinion

OPINION

MEROW, Senior Judge.

Wisconsin Electric Company (“WE”) claims damages in excess of $90 million representing costs incurred in mitigating the government’s failure to perform its contractual obligations to collect, remove, transport and dispose of spent nuclear fuel (“SNF”) discharged from WE’s Point Beach nuclear generating facility on the shores of Lake Michigan. Electricity rates charged WE’s customers have included over $215 million dollars in fees WE paid to the government for this disposal service, which was to commence not later than January 31, 1998, but which has yet to occur.

The court has jurisdiction over these claims. 28 U.S.C. § 1491(a); PSEG Nuclear, L.L.C. v. United States, 465 F.3d 1343 (Fed.Cir.2006). The Department of Energy’s (“DOE’s”) partial breach of its Standard Contract with nuclear utilities is well established. Carolina Power & Light Co. v. United States, 573 F.3d 1271, 1273 (Fed.Cir.2009) (“Carolina Power II”) (citing Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1376-77 (Fed.Cir.2005) (“Ind. Mich. II”) and Me. Yankee Atomic Power Co. v. United States, 225 F.3d 1336, 1343 (Fed.Cir.2000)); Pac. Gas & Elec. Co. v. United States, 536 F.3d 1282, 1284 (Fed.Cir.2008) (“PG & E II”) (“A series of eases has established that [721]*721DOE has partially breached the contract by failing to begin its performance on January 31, 1998.”) (citing cases); Yankee Atomic Elec. Co. v. United States, 536 F.3d 1268, 1272 (Fed.Cir.2008) (“Yankee II”) (“[DOE’s] failure to perform beginning on January 31, 1998 constituted a partial breach of the contract.”); Sacramento Mun. Util. Dist. v. United States, 293 Fed.Appx. 766, 769 (Fed.Cir.2008) (“SMUD II”); Me. Yankee, 225 F.3d at 1342 (“The breach involved all the utilities that had signed the contract — the entire nuclear electñc industry”) (emphasis added). On October 8, 2004, this court granted WE’s Motion for Partial Summary Judgment on Liability, to the extent that DOE’s failure timely to begin disposal activities with respect to WE’s SNF and/or high-level radioactive waste (“HLW’) covered by the Standard Contract comprised a partial breach. Accordingly, this Opinion concerns mitigation damages.

DOE never commenced performance of its contractual disposal obligation, but the contract was not repudiated. At all relevant times DOE continued to collect the fees required under the contract. Accordingly, nuclear utilities may recover appropriately established incurred costs in mitigating DOE’s partial breach, but may not recover future expenses. Ind. Mich. II, 422 F.3d at 1375-77. “ ‘If the breach of an entire contract is only partial, the plaintiff can recover only such damages as he or she has sustained, leaving prospective damages to a later suit in the event of future breaches.’ ” Yankee II, 536 F.3d at 1282 (citing Ind. Mich. II., 422 F.3d at 1376). Indeed, such “later” suits have begun to be filed.1 WE’s claim in this litigation is limited to costs incurred through February 28, 2007. In September of 2007, WE sold the Point Beach plant to a Florida Power and Light Company (“FP & L”) subsidiary. As a result, WE will not incur any “future damages” and this litigation comprises WE’s entire damage claim for the government’s breach of its contractual obligations.

The Point Beach facility has two reactors. A spent fuel pool (“wet pool”) between the two reactor units holds the fuel assemblies that have been discharged from the reactors after they have become “spent,” that is relatively inefficient for producing electricity. The pool has the capacity to hold a limited number of assemblies. At the time Point Beach was designed, SNF was removed from the site for reprocessing and reuse. The wet pool capacity was adequate for this method of operation. Reprocessing of SNF was subsequently eliminated with the result that the SNF remained in the pool and as discharges continued, capacity became a problem. The Nuclear Waste Policy Act of 1982, Pub.L. 97-425 (codified at 42 U.S.C. §§ 10101-10270) (“NWPA”), requires that nuclear utilities and the government, represented by DOE, enter into Standard Contracts wherein DOE agreed to remove, transport and dispose of utilities’ SNF starting no later than January 31, 1998. WE responded to DOE’s lack of contractual performance by building an on-site dry storage facility for SNF referred to as an Independent Spent Fuel Storage Installation (“ISFSI”) to serve as a substitute for the disposal DOE would have otherwise provided. WE’s claimed mitigation costs consist of the ISFSI construction, including internal labor, overhead, cost of capital and other expenses, the cost of casks for dry storage of SNF, expenditures in pursuit of private fuel storage at another location and Nuclear Regulatory Commission (“NRC”) fees.

Given liability, the government concedes WE is entitled to recover $12,548,930. The balance of WE’s claimed damages are assailed as not foreseeable, not established with reasonable certainty, or costs that would have been incurred even absent a government breach — or were caused by reasons other than government delays. The government also insists WE’s otherwise recoverable mitigation costs should be reduced by a variety of additional expenses that the government contends WE would have incurred if DOE had performed its contractual obligations.

[722]*722Trial on damages was held on September 10, 2007 through October 16, 2007. Twenty-seven witnesses testified; hundreds of exhibits and numerous deposition designations were admitted. Extensive post-trial briefs were filed, with supplemental briefing following the Federal Circuit decisions in Yankee 11, PG & E II and SMUD II (collectively referred to on occasion hereinafter as the Yankee trio). Oral argument was held on September 26, 2008. A motion for reconsideration and to recall the mandate in the Yankee trio, along with a motion for reconsideration of an order denying a motion for enlargement of time to file a petition for panel rehearing and/or a petition for rehearing en banc, was denied by the Federal Circuit on August 6, 2009. Following the Federal Circuit’s Decision in Carolina Power II, additional briefs were filed in the instant matter on August 5th and 14th, 2009. A petition for rehearing and rehearing en banc in Carolina Power II was denied by the Federal Circuit on November 3, 2009.

With appreciation for the excellent efforts and cooperation of all counsel involved, the court finds that in the main, WE’s mitigation decisions were foreseeable, commercially reasonable and substantially caused by DOE’s failure to perform its contractual obligations. But for DOE’s contractual performance failure, the costs awarded herein would not have been incurred by WE. The amount of the costs awarded were established with reasonable certainty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dairyland Power Cooperative v. United States
123 Fed. Cl. 220 (Federal Claims, 2015)
System Fuels, Inc. v. United States
120 Fed. Cl. 635 (Federal Claims, 2015)
Sgs-92-X003 v. United States
118 Fed. Cl. 492 (Federal Claims, 2014)
Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Power Authority v. United States
99 Fed. Cl. 661 (Federal Claims, 2011)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)
Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Entergy Nuclear Fitzpatrick, LLC v. United States
93 Fed. Cl. 739 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
Boston Edison Co. v. United States
93 Fed. Cl. 105 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
90 Fed. Cl. 714, 71 ERC (BNA) 1473, 2009 U.S. Claims LEXIS 697, 2009 WL 5178375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-electric-power-co-v-united-states-uscfc-2009.