Hi-Shear Technology Corporation v. United States

356 F.3d 1372, 2004 WL 187144
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 15, 2004
Docket03-5077
StatusPublished
Cited by68 cases

This text of 356 F.3d 1372 (Hi-Shear Technology Corporation v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hi-Shear Technology Corporation v. United States, 356 F.3d 1372, 2004 WL 187144 (Fed. Cir. 2004).

Opinion

*1374 SCHALL, Circuit Judge.

This suit arises from two spare parts requirements contracts between the United States Army Communications & Electronics Command (“CECOM”) and Hi-Shear Technology Corporation (“Hi-Shear”). Following a trial, the Court of Federal Claims held that CECOM had breached the contracts by negligently overestimating in its invitations for bids (“IFBs”) the number of spare parts that would be required during the contract period. Hi-Shear Tech. Corp. v. United States, 53 Fed.Cl. 420, 422 (2002). The court awarded Hi-Shear damages in the amount of $17,793.56, plus interest. Id. at 445; Hi-Shear Tech. Corp. v. United States, 55 Fed. Cl. 418 (2003) (denying Hi-Shear’s motion for reconsideration).

On appeal, Hi-Shear argues that our decision in Rumsfeld v. Applied Cos., Inc., 325 F.3d 1328 (Fed.Cir.), cert. denied, — U.S. -, 124 S.Ct. 462, 157 L.Ed.2d 370 (2003), requires reversal and the award of damages in the form of an equitable adjustment in contract price. Because we conclude that the Court of Federal Claims employed a reasonable method to calculate damages, and because that method is not inconsistent with our decision in Applied Cos., we affirm the court’s decision.

BACKGROUND

I.

The two requirements contracts called for Hi-Shear to provide spare parts for the AN/TTC/TYC-39 circuit switch (“T-39 Circuit Switch”). 1 The T-39 Circuit Switch has over 3,000 individual spare parts, approximately 1,100 of which were managed by CECOM in the procurement at issue in this case. Hi-Shear, 53 Fed. Cl. at 423. In connection with the procurement, CECOM identified the particular spare parts that were appropriate for multi-year contracts. It then grouped those parts into acquisition packages based on similarity of materials and components. Id. at 424. Once the parts were allotted between acquisition packages, CECOM calculated the quantities that would be required for each spare part within each package. Id. For pricing purposes, each part was assigned one of three quantity ranges for each year of the contract. Id. Because of well recognized economies of scale, CECOM expected bidders to offer a different price for each quantity range. Id.; see, e.g., Crown Laundry & Dry Cleaners, Inc. v. United States, 29 Fed. Cl. 506, 524 (1993) (“[T]he work estimate provided the basis for the bid price submitted to the government. The larger the number of work items listed in the work estimates, the lower the cost allocation per item of work performed. The lower the number of work items listed in the work estimates, the higher the cost allocation per item of work performed.”).

The acquisition packages eventually matured into IFBs. Each IFB described a one-year requirements contract, with a government option to extend the contract for up to four years. For each line item, each IFB set forth three estimated quantity ranges (Ranges A, B and C), as well as a specific estimated contract quantity. Hi-Shear, 53 Fed. Cl. at 425. In the case of each line item, the estimated contract quantity corresponded to the “lower end of the middle” quantity range for the item. Id. The IFBs also stated that, in the case of each line item, bidders were to provide unit prices for each of the quantity ranges for each of the five possible ordering years. Id. at 424. Hi-Shear submitted bids in response to two IFBs. In doing so, in the case of each line item, it bid the *1375 same price for each quantity range for all five years, contrary to what CECOM had expected. Id. at 425. Hi-Shear asserted that it priced its bids based on the total estimated requirements for each contract, rather than based on the quantity ranges in the IFBs. Id. In due course, Hi-Shear was awarded the two contracts for which it bid, contract F301 and contract F305. Ultimately, contract F301 covered nine line items, while contract F305 covered seven fine items.

As it turned out, the requirements estimates in the IFBs failed to take into account two important factors of which CE-COM was aware, or should have been aware. Id. at 432. First, CECOM failed to consider that the level of need for parts would be affected by an increase in the number of parts on hand based on new incentives for field units to return defective or damaged parts. Id. Second, the requirements estimates did not take into account the number of parts on hand at the time the estimates were made. Id. As a result of neglecting this information, CE-COM used the base average monthly demand, rather than the net base average monthly demand for the parts involved in the procurement. Id. at 424. As a result, the spare parts requirements set forth in the IFBs, and thereafter stated in the contracts, were overestimated.

Subsequently, although CECOM extended both contracts twice, it only issued one order under contract F301 and two orders under contract F305. Id. at 425. The order under contract F301 was for $153,300.00 worth of spare parts, which represented less than twelve percent of the total estimated quantity of parts for that contract. The total value of orders under contract F305 was $92,805.97, representing less than twenty percent of the total estimated quantity of parts for that contract.

When CECOM chose not to exercise any options after the second option year under either contract, Hi-Shear filed certified claims with the contracting officer. Id. at 425, 427. Hi-Shear claimed breach of contract damages in the amount of $310,319 under contract F301 and $53,330 under contract F305. Id. In its claims, Hi-Shear sought to recover the fixed overhead and general and administrative (“G & A”) costs that it alleged it would have incurred, as well as the gross profit it stated it would have made, under each contract had the government purchased all of the estimated requirements for the base year and each of the four option years stated in the IFBs. Id. at 426.

II.

After the contracting officer denied its claims, Hi-Shear timely filed suit in the Court of Federal Claims under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (2000). Following a trial, the court held that CECOM had breached the two requirements contracts by negligently overstating, in the IFBs, its estimated requirements for spare parts. However, the court disagreed with Hi-Shear’s damages assessment and awarded only $17,793.56 in total damages for both contracts.

Before the Court of Federal Claims, Hi-Shear sought damages spread over the base year and the four option years of each contract, even though CECOM only extended each contract twice. Hi-Shear, 53 Fed. Cl. at 435. Relying on Dangfeng Shen Ho v. United States, 49 Fed. Cl. 96, 107 (2001), aff'd,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bitmanagement Software Gmbh v. United States
124 F.4th 1368 (Federal Circuit, 2025)
Sage Acquisitions LLC v. Hud
119 F.4th 973 (Federal Circuit, 2024)
David Boland, Inc.
Armed Services Board of Contract Appeals, 2024
Mecom v. Morris
N.D. Oklahoma, 2022
Bonilla-Mead v. United States
Federal Circuit, 2019
Kellogg Brown & Root Services, Inc.
Armed Services Board of Contract Appeals, 2018
Shell Oil Company v. United States
896 F.3d 1299 (Federal Circuit, 2018)
Vistas Construction of Illinois, Inc.
Armed Services Board of Contract Appeals, 2016
EJB Facilities Services
Armed Services Board of Contract Appeals, 2015
Dobyns v. United States
118 Fed. Cl. 289 (Federal Claims, 2014)
Stockton East Water District v. United States
761 F.3d 1344 (Federal Circuit, 2014)
Supreme Foodservice Gmbh v. United States
109 Fed. Cl. 369 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
356 F.3d 1372, 2004 WL 187144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hi-shear-technology-corporation-v-united-states-cafc-2004.