Hi-Shear Technology Corp. v. United States

55 Fed. Cl. 418, 2003 U.S. Claims LEXIS 46, 2003 WL 1101471
CourtUnited States Court of Federal Claims
DecidedFebruary 27, 2003
DocketNo. 98-712C
StatusPublished
Cited by6 cases

This text of 55 Fed. Cl. 418 (Hi-Shear Technology Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hi-Shear Technology Corp. v. United States, 55 Fed. Cl. 418, 2003 U.S. Claims LEXIS 46, 2003 WL 1101471 (uscfc 2003).

Opinion

ORDER

HORN, Judge.

The court is in receipt of plaintiff’s “Motion for Reconsideration and Amendment” of the court’s August 29, 2002 opinion, awarding plaintiff $17,793.56 in damages. Following receipt of plaintiffs motion, the court ordered the plaintiff, Hi-Shear Technology Corporation (Hi-Shear), to file an additional brief specifically on recovery of damages based on the defendant’s decision not to exercise two option years, and the defendant was ordered to respond to plaintiff’s motion and additional brief.

FACTS

This case involves two requirements contracts, each with four option years. In April and July 1994, the United States Army Communications & Electronics Command (CE-COM) issued an invitation for bids based on an estimated need for parts to support AN/ TTC/TYC-39 Circuit Switches, which provide automatic switching for the Tri-Service Tactical Communications System. The plaintiff, Hi-Shear, bid on the contracts and the Army awarded the two contracts to Hi-Shear for an estimated quantity of parts. Both contracts awarded to the plaintiff were for one base year, with four option years. The government exercised its option to extend both contracts twice, but did not extend either contract for the third or fourth year, and only issued one order, in total, under one of the contracts for a total price of $153,300.00.

In May 1997, the plaintiff filed two certified claims with the contracting officer alleging that the government had breached its contract by negligently estimating its requirements and ordering significantly fewer parts than estimated. The contracting officer denied both of Hi-Shear’s claims stating that the government was not negligent because intervening events, including reduced funding, had substantially reduced the amount of parts needed by CECOM. Thereafter, the plaintiff filed suit in this court asserting that the government had negligently estimated the contract requirements and had not accounted for all reasonably available information concerning likely orders for goods when determining its estimated contract requirements.

In its August 29, 2002 opinion, the court found the government negligent for failing to properly estimate its contract requirements. Hi-Shear Tech. Corp. v. United States, 53 Fed.Cl. 420, 429, 444-45 (2002). The court determined that the government had failed to properly account for its net base average monthly demand, a quantity comprised of figures including unserviceable return rates, serviceable return rates, and spare parts on hand. A correct net base average monthly demand was necessary for the government to properly estimate its contract requirements. See id. Because of an Army directive requiring retention of asset on hand quantity records for only two years, however, specific evidence as to the number of assets the Army had on hand when it estimated its [420]*420contract requirements were not available to assess damages. Id. at 438. Thus, the court constructed an estimate of what the government’s requirements would have been had the government properly estimated its net base average monthly demand from the evidence presented, including trial testimony and exhibits. Id. The court based the plaintiffs damages award on all relevant information available to it and found for the plaintiff in the amount of $17,793.56. Id. at 445.

From the testimony and evidence provided, the court also found that the plaintiff would not have made a profit on the contract even if the government had not been negligent in its estimation. Hi-Shear Tech. Corp. v. United States, 53 Fed.Cl. at 444. The court, therefore, held that the plaintiff could not recover lost profits. Id. at 445. In its current motion, the plaintiff objects to the court’s formulation of damages and asks the court to reconsider its opinion.

STANDARD OF REVIEW

Plaintiff cites Rule 59 of the Rules of the United States Court of Federal Claims (RCFC) for its motion for reconsideration and asks the court to review its calculation of damages to “provide a dollar quantum more fairly reflective of Hi-Shear’s damages.” RCFC 59(a)(1) provides that reconsideration “may be granted to all or any of the parties and on all or part of the issues, for any of the reasons established by the rules of common law or equity applicable as between private parties in the courts of the United States.”

The United States Court of Appeals for the Federal Circuit has stated that: “The decision whether to grant reconsideration lies largely within the discretion of the [trial] court.” Yuba Natural Res., Inc. v. United States, 904 F.2d 1577, 1583 (Fed.Cir.1990); reh’g denied. See Citizens Fed. Bank, FSB, et al. v. United States, 53 Fed.Cl. 793, 794 (2002) (citing Yuba Natural Res., Inc. v. United States, 904 F.2d at 1583). To prevail, a motion for reconsideration “must be based upon manifest error of law, or mistake of fact, and is not intended to give an unhappy litigant an additional chance to sway the court.” Circle K Corp. v. United States, 23 Cl.Ct. 659, 664-65 (1991). See also Am-mex, Inc. v. United States, 52 Fed.Cl. 555, 557 (2002); Stelco Holding Co. v. United States, 42 Fed.Cl. 156, 157 (1998); Principal Mut. Life Ins. Co. v. United States, 29 Fed.Cl. 157, 164 (1993), aff'd, 50 F.3d 1021 (Fed.Cir.1995); reh’g denied. In order to prevail on a motion for reconsideration, the movant must show either that: (a) an intervening change in the controlling law has occurred; (b) evidence not previously available has become available; or (e) that the motion is necessary to prevent manifest injustice. See Bishop v. United States, 26 Cl.Ct. 281, 286 (1992); see also Strickland v. United States, 36 Fed.Cl. 651, 657 (1996). “A court, therefore, will not grant a motion for reconsideration if the movant ‘merely reasserts ... arguments previously made ... all of which were carefully considered by the Court.’” Ammex, Inc. v. United States, 52 Fed.Cl. at 557 (quoting Principal Mut. Life Ins. Co. v. United States, 29 Fed.Cl. at 164) (emphasis in original). See Frito-Lay of P.R., Inc. v. Canas, 92 F.R.D. 384, 390 (D.P.R.1981).

DISCUSSION

In its motion for reconsideration, the plaintiff alleges that: 1) the court’s decision is incomplete because it fails to calculate what the contract prices would have been based on corrected estimated contract requirements; 2) the resolution of the issue of quantities on hand is contrary to law and to any semblance of fairness; and 3) the court’s formulation of damages was contrary to the principles of commercial law. The plaintiffs assertions attack the court’s use of an estimation model to determine the government’s corrected contract estimate and to establish the plaintiffs damages. Indeed, the plaintiff states that “The Primary Issue Is Whether Plaintiffs Damages Should Be Calculated In Accordance With The Restatement Of Contracts Or By A ‘Model’ Constructed Of Suppositions,” and asserts that the court’s estimation is contrary to commercial law principles leading to an “absurd result.” In addition, the plaintiff argues that the government’s failure to exercise the final two option years of the contract is irrelevant in determining damages because the government had the right [421]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

URS Federal Services, Inc. v. United States
102 Fed. Cl. 674 (Federal Claims, 2012)
Magic Brite Janitorial v. United States
72 Fed. Cl. 719 (Federal Claims, 2006)
Hi-Shear Technology Corporation v. United States
356 F.3d 1372 (Federal Circuit, 2004)
FOUNDATION INTERN. v. ET Ige Const.
78 P.3d 23 (Hawaii Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
55 Fed. Cl. 418, 2003 U.S. Claims LEXIS 46, 2003 WL 1101471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hi-shear-technology-corp-v-united-states-uscfc-2003.