Englewood Terrace Ltd. Partnership v. United States

113 Fed. Cl. 718, 2013 U.S. Claims LEXIS 1863, 2013 WL 6244142
CourtUnited States Court of Federal Claims
DecidedNovember 22, 2013
DocketNo. 03-2209C
StatusPublished
Cited by3 cases

This text of 113 Fed. Cl. 718 (Englewood Terrace Ltd. Partnership v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Englewood Terrace Ltd. Partnership v. United States, 113 Fed. Cl. 718, 2013 U.S. Claims LEXIS 1863, 2013 WL 6244142 (uscfc 2013).

Opinion

OPINION

HORN, J.

The issue before this court is the result of a limited remand by the United States Court [720]*720of Appeals for the Federal Circuit in the above captioned case on one portion of the damages calculation previously determined by the court. The Federal Circuit affirmed most of the factual findings and legal conclusions of this court’s earlier opinion, but remanded to this court, for further review on the single issue of a possible reduction in the $3,272,217.00 award to the plaintiff, Englewood, of lost profits stemming from a breach by the United States Department of Housing and Urban Development (HUD) of the 2000 Housing Assistance Payment (HAP) contract between the plaintiff and the government. The Federal Circuit indicated in its decision that a remand is necessary “to determine an appropriate reduction in the award to the plaintiff (a reduction that could entirely eliminate the lost profits award).” Englewood Terrace Ltd. P’ship v. United States, 479 Fed.Appx. 969, 973 (Fed.Cir.2012) (Englewood VII) (not selected for publication).2 As stated by the Federal Circuit, the limited issue to be addressed on remand is a possible reduction of Englewood’s damages award “by any operational costs or expenses Englewood did not pay but would have been obligated to pay if HUD had not breached the HAP contract.” Id.

The relevant background and facts of the Englewood case have been addressed extensively by this court in its multiple, previous opinions, which, after a lengthy trial, found among other conclusions, that defendant, had breached the 2000 HAP contract it had entered into with Englewood, and that plaintiff was entitled to lost profits damages as a result of the defendant’s breach. See Englewood II, 79 Fed.Cl. 516; Englewood V, 94 Fed.Cl. 116. The relevant facts also were addressed on appeal in the opinion issued by the Federal Circuit. See generally Englewood VII, 479 Fed.Appx. 969. The findings of fact previously made by this court and the Federal Circuit are incorporated into this opinion with additional findings of fact based on this court’s review after the remand. Only the most relevant facts previously found are briefly reiterated below, including those specifically related to calculating “an appropriate reduction in the award to the plaintiff,” as mandated by the Federal Circuit. Id. at 973. The court also, once again, has reviewed the trial record, as well as the submissions of the parties on remand.

FINDINGS OF FACT

Englewood alleged, and both this court and the Federal Circuit agreed, that HUD breached the HAP contract between Englewood and HUD. The HAP contract provided for rent subsidies to be used by the tenants of South Pointe Towers (South Pointe), a high-rise apartment building in Chicago, Illinois. South Pointe was owned by Englewood Towers Limited Partnership. John J. Hayes was president of P.M. Group, Englewood Terrace Limited Partnership’s general partner, until December 13, 2002. Mr. Hayes’ P.M. One was the managing agent at South Pointe. On December 13, 2002, DSSA New Englewood Terrace LLC (DSSA), a sole proprietorship of Donald S. Samuelson, replaced P.M. Group as Englewood’s general partner. Earlier, on December 1, 2001, Mr. Samuelson’s DSSA Management, Inc., which was affiliated with Mr. Samuelson’s DSSA New Englewood Terrace LLC, replaced P.M. One as South Pointe’s managing agent.

The HAP contract at issue was executed in October 2000 and called for a one year term, followed by three automatic one-year renewals, which would have continued the contract through September 2004.3 This court previ[721]*721ously found that, in December 2000, HUD unilaterally amended the HAP contract, without Englewood’s authorization, into one consisting of a series of short term agreements with no automatic renewals. The short term agreements permanently ended on September 30, 2002, after the final short term agreement expired and all tenants had been given housing vouchers permitting them either to remain at South Pointe, or to relocate to other housing with their vouchers. This court found that HUD “should be held to the terms of the original HAP contract it made in October, 2000.” Englewood II, 79 Fed.Cl. at 535.

Englewood’s original claims stemmed from HUD’s termination of Englewood’s HAP contract with HUD. HUD based its termination of the HAP contract on its finding in a March 2, 2001 HUD inspection of South Pointe that Englewood had not provided decent, safe, and sanitary housing to tenants, as required by the HAP contract. After lengthy trial proceedings, this court found that HUD’s decision to terminate Englewood was made even before HUD had received Englewood’s plan to correct deficiencies identified in the March 2, 2001 HUD inspection. The court concluded that Englewood had not been afforded a full and meaningful opportunity to cure the deficiencies identified in the March 2, 2001 HUD inspection. The record reflects that, although HUD had urged that South Pointe be placed under new ownership and management, once new management and ownership was in place, under the direction of Mr. Samuelson, there appeared to be a reluctanee on the part of HUD to provide a meaningful opportunity for the new ownership and management to take corrective action. HUD also was unwilling to acknowledge any improvement at South Pointe after DSSA took over. HUD’s actions, thereby, undermined its contract termination action against Englewood.

On October 1, 2001, Edward Hinsberger, Director of the Chicago Office of Multifamily Housing for HUD, sent an email to Mr. Hayes and Mi-. Samuelson stating that “[t]he [Chicago] Housing Authority has advised us that they will begin issuing vouchers for the residents at South Pointe today____ As a result, the Sec. 8 [HAP] contract will be terminated once all of the residents receive their vouchers.” Mr. Hinsberger alleged at trial that vouchers did not begin to issue until June 2002.

The occupancy rate at South Pointe began to decline in the spring of 2002. It dropped below 85% in April 2002 and below 70% by June 2002. It continued to decrease steadily through October 2002, the month following the expiration of the HAP contract, when the occupancy rate dwindled to 35%. HUD phased out the HAP contract in stages. Whenever a tenant used the Chicago Housing Authority (CHAC) voucher, either to leave, or, if the unit was acceptable, to remain at South Pointe, HUD ceased to pay a HAP subsidy for that specific unit. HUD also permanently stopped HAP payments when a unit that had received the subsidy became vacant for any other reason.4 Dur[722]*722ing this time, the costs to ran South Pointe remained constant for Englewood, and it continued to pay high interest payments on its loan from Community Investment Corporation (CIC).

In January 2002, Englewood defaulted on its CIC loan. CIC filed a foreclosure action, which was voluntarily withdrawn in March 2002, and then reinstated in May 2002. CIC withdrew the action a second time after it received assurances that Englewood would obtain a new loan, insured by HUD, which would pay off the entire old mortgage and provide funds for a complete rehabilitation of South Pointe. This second loan was provided through Reilly Mortgage, a private financial institution, but was insured against default by HUD through the section 221(d)(4) loan program.5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bannum, Inc. v. United States
Federal Claims, 2021
Englewood Terrace Ltd. Partnership v. United States
629 F. App'x 977 (Federal Circuit, 2015)
VICI Racing, LLC v. T-Mobile USA, Inc.
87 F. Supp. 3d 697 (D. Delaware, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
113 Fed. Cl. 718, 2013 U.S. Claims LEXIS 1863, 2013 WL 6244142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/englewood-terrace-ltd-partnership-v-united-states-uscfc-2013.