Bluebonnet Savings Bank, F.S.B., and Stone Capital, Inc. (Formerly Known as Cfsb Corporation), and James M. Fail v. United States

339 F.3d 1341, 2003 U.S. App. LEXIS 16195
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 7, 2003
Docket19-2235
StatusPublished
Cited by72 cases

This text of 339 F.3d 1341 (Bluebonnet Savings Bank, F.S.B., and Stone Capital, Inc. (Formerly Known as Cfsb Corporation), and James M. Fail v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bluebonnet Savings Bank, F.S.B., and Stone Capital, Inc. (Formerly Known as Cfsb Corporation), and James M. Fail v. United States, 339 F.3d 1341, 2003 U.S. App. LEXIS 16195 (Fed. Cir. 2003).

Opinion

PER CURIAM.

The United States appeals from the judgment of the United States Court of Federal Claims awarding damages of $132,398,200 to plaintiff James M. Fail for the government’s breach of contract. Bluebonnet Sav. Bank, FSB v. United States, 52 Fed.Cl. 75 (2002). The Court of Federal Claims interpreted our previous opinion in this case as requiring entry of a damages award for plaintiff in that amount, with no further factual analysis by the trial court. In this opinion, we clarify that our prior opinion was not meant to foreclose any further inquiry by the Court of Federal Claims into the issue of damages. We therefore vacate the judgment *1343 and remand to allow the trial court to conduct such proceedings as that court deems necessary to determine the proper quantum of damages.

I

This case is one of a number of “Wins-tar” cases arising from the savings and loan crisis of the 1980s. See generally United States v. Winstar Corp., 518 U.S. 839, 116 S.Ct. 2432, 135 L.Ed.2d 964 (1996). The Federal Home Loan Bank Board sought to address the crisis by inducing private parties to bail out failed savings and loan institutions, or “thrifts,” mainly in Texas and other southwestern states. Pursuant to that program, plaintiff James M. Fail and other investors acquired a group of failing thrifts and merged them into Bluebonnet Savings Bank, FSB. As part of the agreement to acquire the thrifts, Mr. Fail and his thrift holding company, CFSB Corporation, agreed to infuse $120 million into Bluebonnet over a two-year, period. In return, the government agreed to provide approximately $3 billion in cash assistance to Bluebonnet and to grant Bluebonnet regulatory forbearances through the Federal Home Loan Bank Board. The forbear-ances included permitting Bluebonnet (1) to operate with reduced capital level requirements, (2) to pay dividends as long as Bluebonnet maintained those capital level requirements, and (3) to treat subordinated debt as regulatory capital.

In 1989, however, Congress enacted the Financial Institutions Reform, Recovery, and Enforcement Act (“FIRREA”). The new statute and its regulations limited Bluebonnet’s ability to pay dividends and increased Bluebonnet’s capital level requirements. Mr. Fail, CFSB Corporation (now renamed Stone Capital, Inc.), and Bluebonnet filed suit charging that the enforcement of FIRREA and its regulations had the effect of breaching the contract offering regulatory forbearances. The plaintiffs claimed that as a result of the breach they experienced increased costs in financing their required cash infusions into Bluebonnet.

Mr. Fail had financed part of the initial cash infusion through short-term loans from financier Robert Shaw. Mr. Fail continued borrowing money from Mr. Shaw and allowing the loans to roll over until a total of $140 million in short-term loans from Mr. Shaw came due in 1992. Unable to secure long-term financing and facing default on the short-term loans, Mr. Fail entered into a more complex financing agreement with Mr. Shaw, which was referred to as the Economic Benefits Agreement (“EBA”). Under the EBA, Mr. Fad agreed to pay approximately $59 million to Mr. Shaw up front. Mr. Shaw agreed to provide long-term financing for the remaining $81 million due on the short-term loans in exchange for receiving a 49 percent equity interest in CFSB’s profits. The plaintiffs contended that if there had been no breach Mr. Fail would have been able to obtain all-debt financing through long-term loans at an interest rate of 13.5 percent. The plaintiffs thus sought two categories of damages: those damages related to the EBA, which flowed from the relinquishment of the 49 percent equity interest in CFSB; and those damages not related to the EBA, which resulted from the increased loan interest and lender fees that plaintiffs had to pay as a result of the breach. The value of the equity interest that Mr. Fail relinquished is reflected in a document called the Memo Account.

The Court of Federal Claims granted partial summary judgment for the plaintiffs on the issue of liability, see Bluebonnet Sav. Bank, FSB v. United States, 43 Fed.Cl. 69 (1999), and conducted a trial to establish the extent of the damages. Following the trial, the court denied the plaintiffs’ request for damages in its entirety *1344 and entered judgment for the government. See Bluebonnet Sav. Bank, FSB v. United States, 47 Fed.Cl. 156 (2000). While the court held that increased financing costs were foreseeable and that the breach caused the plaintiffs to incur increased financing costs, the court concluded that it could not determine the amount of that increase with reasonable certainty. As part of that decision, the court ruled that the Memo Account was not a reliable basis for establishing the plaintiffs’ actual EBA-related costs, i.e., the value of the equity interest surrendered to Mr. Shaw as part of the EBA.

On appeal, this court reversed in part. See Bluebonnet Sav. Bank, FSB v. United States, 266 F.3d 1348 (Fed.Cir.2001). We upheld the trial court’s findings that increased financing costs were foreseeable and that the government’s breach caused the plaintiffs to incur increased costs. We also upheld the trial court’s rejection of the plaintiffs’ claim for what were referred to as “non-EBA-related damages.” We agreed with the court’s conclusion that the plaintiffs had failed to establish those damages to a reasonable certainty, inasmuch as there was no evidence that the plaintiffs would have obtained long-term loans at the assumed rate of 13.5 percent. However, we reversed the conclusion of the trial court that the Memo Account did not provide a fair and reasonable basis from which to assess the EBA-related costs. We remanded the case for the trial court “to formulate an appropriate award of EBA-related damages as determined by the payments already made by Fail to Shaw under the EBA, and the value of the EBA debt as calculated in the Memo [Account].” Id. at 1358.

On remand, the Court of Federal Claims declined to reopen the record. Noting that “[t]he Federal Circuit held that Bluebonnet persuasively argued that it was entitled to the entire cost of the EBA as an award of damages,” the court stated that it “interprets the Federal Circuit’s mandate to require that the court add the $5,400,392 [paid to Mr. Shaw under the EBA] to the $126,997,808, which represents the value of the EBA debt as calculated in the Memo [Account], in order to arrive at the damage award in this case. The court is constrained by the mandate of the Federal Circuit.” Bluebonnet Sav. Bank, FSB v. United States, 52 Fed.Cl. 75, 77 (2002). The court therefore awarded a judgment of $132,398,200 to Mr. Fail. The government appeals from that judgment.

II

This appeal turns on the proper interpretation of our prior opinion in this case, and in particular the extent to which our mandate prohibited the trial court from conducting further proceedings on remand to determine the proper damages award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Omega Patents, LLC v. Calamp Corp.
13 F.4th 1361 (Federal Circuit, 2021)
Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2021
Community Health Choice, Inc. v. United States
970 F.3d 1364 (Federal Circuit, 2020)
Clear Creek Community Services District v. United States
132 Fed. Cl. 223 (Federal Claims, 2017)
Canpro Investments, Ltd v. United States
130 Fed. Cl. 320 (Federal Claims, 2017)
Financial & Realty Services, LLC v. United States
128 Fed. Cl. 770 (Federal Claims, 2016)
Entergy Gulf States, Inc. v. United States
125 Fed. Cl. 678 (Federal Claims, 2016)
System Fuels, Inc. v. United States
125 Fed. Cl. 331 (Federal Claims, 2016)
Northrop Grumman Computing Systems, Inc. v. United States
120 Fed. Cl. 460 (Federal Claims, 2015)
Sacramento Municipal Utility District v. United States
120 Fed. Cl. 270 (Federal Claims, 2015)
Englewood Terrace Ltd. Partnership v. United States
479 F. App'x 969 (Federal Circuit, 2012)
Entergy Nuclear Fitzpatrick, LLC v. United States
101 Fed. Cl. 305 (Federal Claims, 2011)
Power Authority of State of New York v. United States
103 Fed. Cl. 780 (Federal Claims, 2011)
Energy Northwest v. United States
641 F.3d 1300 (Federal Circuit, 2011)
OK's Cascade Co. v. United States
97 Fed. Cl. 635 (Federal Claims, 2011)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
339 F.3d 1341, 2003 U.S. App. LEXIS 16195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bluebonnet-savings-bank-fsb-and-stone-capital-inc-formerly-known-as-cafc-2003.