Peraton, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 10, 2025
Docket62853
StatusPublished

This text of Peraton, Inc. (Peraton, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peraton, Inc., (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Peraton, Inc. ) ASBCA No. 62853 ) Under Contract No. N00178-05-D-4395 )

APPEARANCES FOR THE APPELLANT: Kevin P. Mullen, Esq. Caitlin A. Crujido, Esq. Morrison & Foerster LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Allison M. McDade, Esq. Navy Chief Trial Attorney Devin A. Wolak, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE WOODROW

This appeal concerns a cost-plus-fixed-fee, level-of-effort task order issued to Peraton, Inc. (Peraton or appellant) for technical systems engineering support services for the Navy’s Fleet Systems Engineering Team (FSET). The Navy issued the FSET I task order under the Seaport Enhanced (Seaport-e) Multiple Award Contract vehicle, an indefinite delivery, indefinite quantity (IDIQ) contracting mechanism designed to streamline service acquisition for the Navy.

This appeal is being conducted pursuant to the Board’s Rule 11 procedures, which permit the parties to waive a hearing and submit the matter for decision on the written record. Pursuant to Rule 11, the Board decides the weight to be given any evidence and may make findings of fact on disputed facts. Board Rule 11(d). This proceeding determines only Peraton’s entitlement to the claimed costs, not the specific amounts.

This appeal involves identical legal issues as the appeals of Vectrus Systems Corporation (Vectrus) in ASBCA Nos. 62685 and 62949, involving a successor contract, known as the FSET II contract. Peraton and Vectrus share the same counsel and the Vectrus appeal was briefed on the same schedule pursuant to Board Rule 11.

The central dispute is whether Peraton is entitled to its full fixed fee based on the Navy’s initial estimated hours, despite the Navy’s actual requirements being substantially lower. Peraton contends its fixed fee represents the agreed-upon profit, while the Navy maintains it is obligated to pay only for actual costs plus a fee proportionate to the work performed.

We conclude that Peraton has been paid its fee in accordance with the express terms of the contract and that it is not entitled to any additional fee. For the reasons stated below, we deny the appeal.

FINDINGS OF FACT

I. The FSET I Contract

1. On May 31, 2005, the Navy awarded Contract No. N00178-05-D-4395 to ITT Industries, Inc., Systems Division (R4, tab 107 at GOV7508). ITT Industries is a corporate predecessor to the appellant, Peraton, Inc. This contract is known as the “FSET I contract.” The FSET I contract is part of the multiple award Seaport Enhanced (Seaport-e) contract vehicle designed to streamline acquisition for the Navy, United States Marine Corps, and other Navy activities (id. at 7515).

2. The FSET I contract is an indefinite-delivery, indefinite quantity contract with a minimum government obligation of $2,501 (id. at 7509, 7513, 7515). It contemplates the issuance of multiple task orders requiring the provision of “qualified personnel, materials, facilities, equipment, test instrumentation, data collection and analysis hardware and software, and other services that will support the Navy in the execution of their missions” in 22 specified fields of expertise (id. at 7515-19).

3. The terms and conditions set forth in the FSET I contract apply to all task orders issued pursuant to the contract (id. at 7524). The contract incorporates Federal Acquisition Regulation (FAR) 52.216-18, ORDERING (OCT 1995), which states that “[i]n the event of a conflict between a delivery order or task order and this contract, the contract shall control” (id. at 7553).

4. The FSET I contract permits the award of cost-plus fixed-fee IDIQ orders (id. at 7525). A “cost-plus fixed-fee” contract is a cost reimbursement contract that provides for payment to the contractor of a negotiated fee that is fixed at the inception of the contract. The fixed fee does not vary with actual cost, but may be adjusted as a result of changes in the work to be performed under the contract. FAR 16.306(a).

5. FAR 16.306(d) describes two types of cost-plus-fixed-fee contracts: completion and term. Completion contracts define a specific deliverable and budget, allowing for increased effort without increased fee if the project goes over budget. The FSET-II task order is “term” form contract, meaning that the contract defines a level of effort over a specific time, with payment upon satisfactory completion of that period. FAR 16.306(d).

2 6. The FSET I contract provides for the issuance of “term” task orders, which it describes as follows:

The term form [of task order] describes the scope of work in general terms and obligates the contractor to devote a specified level of effort for a stated period of time. Under this form [of task order], if the performance is considered satisfactory by the Government, the fixed fee is payable at the expiration of the agreed-upon period and upon contractor certification that the level of effort specified in the order has been expended in performing the contract work.

(R4, tab 107 at 7525)

7. The FSET I contract includes clause SEA 5252.216-9122, LEVEL OF EFFORT (DEC 2000). Subsection (a) of the clause states:

(a) The Contractor agrees to provide the total level of effort specified in the next sentence in performance of the work described in Sections B and C of this contract. The total level of effort for the performance of this contract shall be (to be completed for each order) total man-hours of direct labor, including subcontractor direct labor for those subcontractors specifically identified in the Contractor’s proposal as having hours included in the proposed level of effort.

(Id. at 7526) (emphasis in original) Pursuant to this clause, the contractor agrees to dedicate a specific number of hours (level of effort or LOE) to the project (as detailed in Sections B & C of the contract, which describe what work needs to be done). This includes hours worked by any subcontractors the contractor uses. This number will be filled in when each specific order is placed.

8. Subsection (e) of clause SEA 5252.216-9122 addresses when the contractor accelerates the work. It provides that, if the contractor foresees exhausting the allocated hours (level of effort or LOE) before the contract end date, it must notify the Task Order Contracting Officer in writing, proposing an acceleration plan at no additional cost or fee, along with a proposal for continued work through the contract term. If the contracting officer (CO) approves the proposal, then it becomes a binding agreement via contract modification. Id. at 7527

3 9. Subsection (f) of SEA 5252.216-9122 addresses when the government accelerates the work. It provides that the CO can order the contractor to speed up the work and use all the budgeted hours before the contract’s end date. This order will specify how much faster the work needs to go and the new, shorter deadline. The contractor has five days to acknowledge the order. Id. at 7527.

10. Subsection (g) addresses when the actual hours are less than the budgeted hours. Under subsection (g) of SEA 5252.216-9122, if the contractor does not use all of the budgeted hours, the CO can either reduce the contractor’s profit proportionally to the unused hours or make the contractor keep working until all the hours are used up, without paying any extra fee. “If the total level of effort specified in paragraph (a) above is not provided by the Contractor during the period of this contract, the Task Order Contracting Officer, at its sole discretion, shall either (i) reduce the fee of this contract” pursuant to the following formula:

Fee Reduction = Fee (Required LOE – Expended LOE) Required LOE

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Hi-Shear Technology Corporation v. United States
356 F.3d 1372 (Federal Circuit, 2004)
Hi-Shear Technology Corp. v. United States
53 Fed. Cl. 420 (Federal Claims, 2002)
Fluor Enterprises, Inc. v. United States
64 Fed. Cl. 461 (Federal Claims, 2005)
AMTEC Corp. v. United States
69 Fed. Cl. 79 (Federal Claims, 2005)
Clearwater Forest Industries, Inc. v. United States
650 F.2d 233 (Court of Claims, 1981)
Amtec Corp. v. United States
239 F. App'x 585 (Federal Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Peraton, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/peraton-inc-asbca-2025.