Blankenship Construction Co. v. North Carolina State Highway Commission

222 S.E.2d 452, 28 N.C. App. 593, 1976 N.C. App. LEXIS 2785
CourtCourt of Appeals of North Carolina
DecidedMarch 3, 1976
Docket7526SC727
StatusPublished
Cited by7 cases

This text of 222 S.E.2d 452 (Blankenship Construction Co. v. North Carolina State Highway Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blankenship Construction Co. v. North Carolina State Highway Commission, 222 S.E.2d 452, 28 N.C. App. 593, 1976 N.C. App. LEXIS 2785 (N.C. Ct. App. 1976).

Opinion

BROCK, Chief Judge.

It is appropriate to preface this opinion by acknowledging the well-established rule that the Commission is not subject to suit except in the manner provided by statute. Teer Co. v. Highway Commission, 265 N.C. 1, 143 S.E. 2d 247 (1965). General Statute 136-29 establishes the procedure for the settlement of claims against the Commission by a contractor who has not received “such settlement as he claims to be entitled to under his contract.” This language has been construed to mean that recovery is possible only within the terms and framework of the contract. Teer Co. v. North Carolina State Highway Comm., *602 4 N.C. App. 126, 166 S.E. 2d 705 (1969). Thus the general question raised by this appeal is whether the Contractor is entitled to compensation in excess of the original contract price under the provisions of its contract with the Commission.

The Contractor’s claim for additional compensation is governed by several provisions of the “Standard Specifications for Roads and Structures” incorporated into the construction contract. The first is entitled “Changed Conditions”; in particular, Section 4.3A, “Alteration of Plans or Character of Work”:

“The Commission reserves the right to make, at any time during the progress of the work, such increases or decreases in quantities and such alterations in the details of construction, including alterations in the grade or alinement of the road or structure or both, as may be found to be necessary or desirable. Such increases or decreases and alterations shall not invalidate the contract nor release the Surety, and the Contractor agrees to accept the work as altered, the same as if it had been a part of the original contract.
“Under no circumstances shall alterations of plans or of the nature of the work involve work beyond the termini of the proposed construction except as may be necessary to satisfactorily complete the project.
“Unless such alterations and increases or decreases materially change the character of the work to be performed or the cost thereof, the altered work shall be paid for at the same unit prices as other parts of the work. If, however, the character of the work or the unit costs thereof are materially changed, an allowance shall be made on such basis as may have been agreed to in advance of the performance of the work, or in case no such agreement has been reached, then the altered work shall be paid for by force account in accordance with Article 9.U.
“No claim shall be made by the Contractor for any loss of anticipated profits because of any such alteration, or by reason of any variation between the approximate quantities and the quantities of work as done.
“Should the Contractor encounter or the Commission discover during the progress of the work conditions at the site differing materially from those indicated in the con *603 tract, which conditions could not have been discovered by reasonable examination of the site, the Engineer shall be promptly notified in writing of such conditions before they are disturbed. The Engineer will thereupon promptly investigate the conditions and if he finds they do so materially differ and cause a material increase or decrease in the cost of performance of the contract, an equitable adjustment will be made and a supplemental agreement entered into accordingly.
“In the event that the Commission and the Contractor are unable to reach an agreement concerning the alleged changed conditions, the Contractor will be required to keep an accurate and detailed cost record which will indicate not only the cost of the work done'under the alleged changed conditions, but the cost of any remaining unaffected quantity of any bid item which has had some of its quantities affected by the alleged changed conditions, and failure to keep such a record shall be a bar to any recovery by reason of such alleged changed conditions. Such cost records will be kept with the same particularity as force account records and the Commission shall be given the same opportunity to supervise and check the keeping of such records as is done in force account work.” (Emphasis added.)

According to this language, whether a material change in the character of the work is induced by increases or decreases in quantities or alterations in the details of construction by the Commission, or the result of unexpected conditions at the site, the Contractor is required to notify the Commission of the changed condition (s) and negotiate an “allowance” or “equitable adjustment” to be embodied in a supplemental agreement. In the case of altered work, if no agreement can be reached, the altered work shall be paid for by force account. Similarly, in the case of work done under changed conditions, if the Contractor and Commission fail to negotiate a supplemental agreement, the Contractor must keep cost records of such work “with the same particularity as force account records.”

In addition to the procedures discussed above for compensation for changed conditions, the contract provides for payment of “Extra Work,” Section 4.4. Extra work is defined as “construction for which there is no unit or lump sum contract price” (Section 1.26). Payment for extra work is predicated on a determination by the Engineer that there is extra work to be *604 performed and an authorized modification providing for the performance of extra work. If the Contractor and Engineer agree on the price for the extra work, a supplemental agreement should be issued in conjunction with the authorized modification; if no agreement is reached for the price of extra work, the Contractor must furnish “a force account notice” in conjunction with the authorized modification (Sections 4.4 [A] [1] and [2]). In the event the Engineer disagrees that there is extra work and issues a written denial of the Contractor’s request for an authorized modification, but the Contractor intends to seek compensation for performing such alleged extra work, the following procedures apply:

“. . . [The Contractor] shall notify the Engineer in writing of his intention to file a claim for such payment and shall receive written acknowledgement from the Engineer that such notification has been received before he begins any of the alleged extra work. In such case the Contractor will be required to keep an accurate and detailed cost record which will indicate the cost of performing the extra work. Such cost records will be kept with the same particularity as force account records and the Commission shall be given the same opportunity to supervise and check the keeping of such records as is done in force account work.
“The Contractor’s claim to increased compensation as provided herein will be limited to the amount which would have been due the Contractor if payment for the work had been made on a force account basis as provided by Article 9.4.” (Section 4.4C.)

Therefore, whether the work performed falls in the category of “altered work,” “work done under the changed conditions,” or “extra work,” the procedures for obtaining additional compensation are generally the same.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neal & Co., Inc. v. City of Dillingham
923 P.2d 89 (Alaska Supreme Court, 1996)
Centex-Rodgers Const. Co. v. Wake County
993 F.2d 228 (Fourth Circuit, 1993)
New Pueblo Constructors, Inc. v. State
696 P.2d 203 (Court of Appeals of Arizona, 1984)
S. J. Groves & Sons & Co. v. State
273 S.E.2d 465 (Court of Appeals of North Carolina, 1980)
General Specialities Co. v. Nello L. Teer Co.
254 S.E.2d 658 (Court of Appeals of North Carolina, 1979)
Inland Bridge Co. v. North Carolina State Highway Commission
227 S.E.2d 648 (Court of Appeals of North Carolina, 1976)
Blankenship Construction Co. v. NORTH CAROLINA STATE HIGHWAY CO.
230 S.E.2d 765 (Supreme Court of North Carolina, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
222 S.E.2d 452, 28 N.C. App. 593, 1976 N.C. App. LEXIS 2785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blankenship-construction-co-v-north-carolina-state-highway-commission-ncctapp-1976.