Nello L. Teer Co. v. North Carolina State Highway Commission

143 S.E.2d 247, 265 N.C. 1, 1965 N.C. LEXIS 937
CourtSupreme Court of North Carolina
DecidedJuly 23, 1965
Docket536
StatusPublished
Cited by44 cases

This text of 143 S.E.2d 247 (Nello L. Teer Co. v. North Carolina State Highway Commission) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nello L. Teer Co. v. North Carolina State Highway Commission, 143 S.E.2d 247, 265 N.C. 1, 1965 N.C. LEXIS 937 (N.C. 1965).

Opinion

Bobbitt, J.

Decision on this appeal requires construction of the statute under which Teer initiated this proceeding. This statute, while no longer a part of our: statutory law, is applicable to the present litigation. It must be considered and construed in the context of well established legal principles stated below.

Absent waiver, the State is immune from suit. Smith v. Hefner, 235 N.C. 1, 6, 68 S.E. 2d 783; Ferrell v. Highway Commission, 252 N.C. 830, 833, 115 S.E. 2d 34. It is noted that the provisions of Section 9, Article ÍV, of the Constitution of North Carolina of 1868, relating to claims against the State, by virtue of the comprehensive amendment of Article IV in 1961 are now a part of Section 10, Subsection 1, of Article IV of the Constitution of North Carolina.

The Highway Commission is an unincorporated agency of the State. Except as provided in the Tort Claims Act, G.S. 143-291 et seq., the Highway Commission is not subject to suit in tort. Schloss v. Highway Com., 230 N.C. 489, 492, 53 S.E. 2d 517; Floyd v. Highway Commission, 241 N.C. 461, 85 S.E. 2d 703. Nor is the Highway Commission, unless otherwise provided by statute, subject to suit on contract or for breach thereof. Dalton v. Highway Com., 223 N.C. 406, 27 S.E. 2d 1. Moreover, under our decisions, acts permitting suit, being “in derogation of the sovereign right of immunity," are to be “strictly construed." Floyd v. Highway Commission, supra.

The basic rule is that the Highway Commission is not subject to suit except in the manner expressly provided by statute. Sherrill v. Highway Commission, 264 N.C. 643, 646, 142 S.E. 2d 653, and cases cited; Ferrell v. Highway Commission, supra, and cases cited. An exception to this basic rule is well established, to wit: Where private property is taken for a public purpose by a governmental agency having the power of eminent domain under circumstances such that no procedure provided by statute affords an applicable or adequate remedy, the owner, *10 in the exercise of his constitutional rights, may maintain an action to obtain just compensation therefor. Sherrill v. Highway Commission, supra, and cases cited; Ferrell v. Highway Commission, supra, and cases cited.

G.S. 136-28, at all times pertinent to decision herein, contained the following provision: “All contracts over one thousand dollars that the Commission may let for construction, or any other kinds of work necessary to carry out the provisions of this chapter, shall be let, after public advertising, under rules and regulations to be made and published by the State Highway Commission, to a responsible bidder, the right to reject any and all bids being reserved to the Commission; except that contracts for engineering or other kinds of professional or specialized services may be let after the taking and consideration of bids or proposals from not less than three responsible bidders without public advertisement.” G.S. Vol. 3B, 1958 Replacement. It is noted that G.S. 136-28 was amended in 1963 (S.L. 1963, c. 525) by substituting “five thousand dollars ($5,000.00)” for “one thousand dollars.” G.S. Yol. 3B, 1964 Replacement.

By the weight of authority, a statutory requirement for competitive bids constitutes “a jurisdictional prerequisite to the exercise of the power of a public corporation to enter into a contract.” Fonder v. City of South Sioux Falls, 71 N.W. 2d 618, 53 A.L.R. 2d 493 (S.D.), and cases cited.

This statement, supported by cited cases, appears in 135 A.L.R. 1266 : “In general, but subject to certain limitations and exceptions which are considered in subsequent subdivisions of this annotation, statutes requiring the letting of public contracts to the lowest bidder are regarded as rendering invalid and unenforceable subsequent agreements to pay one to whom a public contract has been duly, awarded additional compensation for extras or additional labor and materials not included in the original contract, at least where the additional compensation exceeds the amount for which public contracts may be made without competitive bidding.”

“Persons dealing with the public agency are presumed to know the law with respect to the requirement of competitive bidding and act at their peril.” Miller v. McKinnon, 124 P. 2d 34 (Cal.), and cases cited; 49 Am. Jur., States, Territories, and Dependencies § 86; 81 C.J.S., States § 113, pp. 1087-1088. This includes knowledge that the officials and agents of the public agency may not waive the sovereign right of immunity or act in violation of statutory requirements. 19 Am. Jur., Estoppel § 166.

This Court has held a purported public contract not made in conformity with the (similar) requirements of G.S. 143-129 is void, but *11 that performance and acceptance of construction work imposes an obligation to pay the reasonable and just value of the work done and •materials furnished. Even so, such recovery excludes profits and such reasonable and just value cannot exceed actual cost. Hawkins v. Dallas, 229 N.C. 561, 50 S.E. 2d 561, and cases cited. Compare Insulation Co. v. Davidson County, 243 N.C. 252, 90 S.E. 2d 496, and see 35 N.C.L.R. 188, 239.

After compliance with requirements of G.S. 136-28, the contract of July 8, 1958, for Project No. 8.13438, was awarded to Teer. Teer’s work was interrupted and delayed on account of another contractor’s failure to perform properly the contract (Project No. 8.13437) covering rough grading, drainage and shoulder work. Teer performed extensive extra work to remedy these deficiencies, such work being prerequisite to the performance of Teer’s contract. The fact now emphasized is that Teer, well within the prescribed number of working days, completed on October 14, 1960, the work called for in its written contract of July 8, 1958.

Whether such deficiencies were of such character and magnitude as to constitute sufficient ground for rescission by Teer of its contract with the Highway Commission need not be determined. Suffice to say, Teer made no attempt to rescind but performed the extra (remedial) work as directed by the Highway Commission’s engineers in addition to that required to perform its contract of July 8, 1958.

Pertinent provisions of the Standard Specifications for Roads and Structures, published October 1, 1952 by the Highway Commission, include the following:

“4.4 ExtRA WoRK. The contractor shall perform unforeseen work, for which there is no price included in the contract whenever it is deemed necessary or desirable in order to complete fully the work as contemplated, and such extra work shall be performed in accordance with the specifications and as directed; provided, however, that before any extra work is started a supplemental agreement shall be entered into, or a written extra work order issued by the Engineer to do the work.
“If it is possible to agree upon equitable prices, the contractor and Commission shall enter into a supplemental agreement to cover any and all the extra work necessary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N.C. Bar and Tavern Ass'n v. Stein
Supreme Court of North Carolina, 2025
Norman v. N.C. Dept. of Transportation
North Carolina Industrial Commission, 2007
Dixon v. N.C. Department of Correction
North Carolina Industrial Commission, 2006
Hardison v. N.C. Department of Correction
North Carolina Industrial Commission, 2006
Mapco v. North Carolina Dept. of Transp.
625 S.E.2d 787 (Court of Appeals of North Carolina, 2006)
Welch Contracting, Inc. v. North Carolina Department of Transportation
622 S.E.2d 691 (Court of Appeals of North Carolina, 2005)
Barrera v. N.C. D.O.C.
North Carolina Industrial Commission, 2005
Shaw v. N.C. D.O.C.
North Carolina Industrial Commission, 2004
Thompson v. N.C. D.O.C.
North Carolina Industrial Commission, 2004
Ward v. N.C. National Guard
North Carolina Industrial Commission, 2003
Williams v. N.C. D.O.C.
North Carolina Industrial Commission, 2003
Companies v. North Carolina Department of Transportation
587 S.E.2d 426 (Court of Appeals of North Carolina, 2003)
Battle Ridge Cos. v. Dept. of Transp.
587 S.E.2d 426 (Court of Appeals of North Carolina, 2003)
Moore v. N.C. D.O.C.
North Carolina Industrial Commission, 2003
Pharr v. N.C. D.O.T.
North Carolina Industrial Commission, 2003
Williams v. N.C. Dept. of Corr.
North Carolina Industrial Commission, 2003
Sprinkle v. N.C. Wildlife Resources Commission
North Carolina Industrial Commission, 2003
Midgett v. N.C. Department of Transporation
North Carolina Industrial Commission, 2001
Data General Corp. v. County of Durham
545 S.E.2d 243 (Court of Appeals of North Carolina, 2001)
Jenkins v. Public Service Co. of NC
518 S.E.2d 6 (Court of Appeals of North Carolina, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
143 S.E.2d 247, 265 N.C. 1, 1965 N.C. LEXIS 937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nello-l-teer-co-v-north-carolina-state-highway-commission-nc-1965.