Opinion

Olaek, J.

This cause is presented upon complaint and demurrer. The complaint avers authority conferred upon the City of Greensboro by its charter to provide water supplies either by erecting waterworks itself or,by contract, and that *329 in pursuance thereof the city contracted with the Greensboro Water Company to furnish said city “with pure and wholesome water for the use of its citizens and of force at all times sufficient to protect the inhabitants of the city against loss by fire,” giving to said Company exclusive rights of eminent domain over its streets, alleys, sidewalks and public grounds for the purpose of laying and operating water-mains, pipes, hydrants, stands, etc.; that subsequently all the rights and property of said water company passed by sale to the defendant, who at the same time assumed all the duties and obligations imposed by the aforesaid contract, and both the defendant and the city had acquiesced in the same; that by virtue of said contract it was stipulated and agreed inter alia that the Water Company should “supply the city and inhabitants' with pure, good and wholesome water, suitable for all domestic, sanitary and fire purposes, and for individual use;” should “erect and maintain settling basins, filtering galleries, reservoirs, water-towers, pump-houses and other appurtenances and attachments necessary or expedient for the proper conducting and carrying on said waterworks, so as to afford at all times the most adequate supply for all domestic uses and the greatest protection against fire.” The remainder of the complaint is as follows:

■ 8. That it was also stipulated and agreed by and under said contract that the said Water Company should use only first-class machinery, pipes, hydrants, valves, pumps, etc., in connection with said waterworks, and that the said works should be complete in all its details with a capacity to furnish one and a half million gallons of water every twenty-four hours against a pressure of two hundred feet head. And should erect a storage water tank whose top water level should be one hundred feet above the surface of the ground at the center of the public square and to be of a capacity of 100,000 *330 gallons of water, and that tbe same shall be filled by tbe said Water Company to its top every day an hour before sundown. And for tbe extinguishment of fire in said city tbe Company shall erect a pump-house and put therein a pumping engine which shall be kept ready at all times to supply the needed fire pressure.

9. That it was further stipulated and agreed by and under said contract that the said Water Company should erect and put in seventy-five hydrants at such places as the city might designate, and for the rents of which said City of Greensboro was to pay them annually $2,875. And in pursuance of such agreement and compliance therewith on the part of the city, the Water Company did erect, and their successors, the Greensboro Water Supply Company, had in possession and use at the times hereinafter mentioned, two hydrants — one a hundred and the other about two hundred feet distant from plaintiff’s store-houses which were destroyed by fire on the date hereinafter mentioned.

10. That by the terms of said contract it was further stipulated and agreed that the said Water Company should keep a pressure of water for fire purposes sufficient to throw six streams of water from six hydrants, to a vertical height of 100 feet in still air, each stream being taken from one hydrant and with 100 feet of hose and a one-inch ring nozzle and the said Company shall constantly, day and night, except from unavoidable accidents, keep all the said hydrants supplied with water for fire service and shall keep them in good order for said service.

11. That said contract was made with the said Greensboro Water Company and extended to and acquiesced in by their successors, the defendant Greensboro Water Supply Company, for the use and benefit of all its property owners and inhabitants — among which was the plaintiff, who was a *331 property owner in said city, at tbe times hereinafter referred to and for several years prior thereto, in common with that of other citizens of said city, which said property was taxed at its full value to raise money with which to pay said hydrant rents.

12. That on the night of the- day of June, 1897, a fire broke out in a building some thirty feet distant from plaintiff’s store-rooms on-the south side of South Elm street in said city; that the fire alarm was at once turned on and in less than ten minutes thereafter the Greensboro Eire Company arrived at said fire with their hose, fire engine and other appurtenances necessary for the ready extinguishment of said fire. That the said fire company attached its hose, which were in every respect adequate and sufficient for the demands of the occasion, as plaintiff is advised and believed, to the two hydrants above mentioned, one 100 feet from said store-rooms and the other about 200 feet distant, each of which said hydrants were sufficiently near to said store and lot to have afforded water adequate for the ready extinguishment of said fire, if the proper pressure had been on same.

13. That notwithstanding the'promptness of the fire company in reaching said fire and the perfect sufficiency of its equipments to convey the water to same, the defendant, as plaintiff is advised and believes, persistently, carelessly and negligently refused to furnish said hydrants above described and referred to with a sufficient pressure of water to extinguish said fire, and by reason of such tortious and negligent conduct on the part of the defendant the said fire spread from the building in which it originated and ignited the storeroom of the plaintiff.

14. That after the fire had spread to and caught on flames the building of the plaintiff the- said fire company, as plaintiff is advised and believes, was still present with its hose, ladders, buckets, engine, etc., ready to use its every effort to *332 extinguish same, and while the said fire company had its hose attached to said hydrants sufficiently near, with the proper pressure, to have quickly extinguished same and saved plaintiff’s property from burning, the defendant persistently refused, neglected and omitted to have the fire pressure agreed to and required by its contract and only furnished pressure sufficient to throw a stream ten feet from end of said regulation hose, by carelessly, negligently and wrongfully failing to keep any water in its water tank, or even its hydrants and pipes full, and not having its pumping-engine at work; by reason of which negligent, wrongful and tortious conduct on the part of the defendant, the plaintiff’s property was totally destroyed by fire, and by reason of such loss she has been damaged in the sum of $5,000.

15. That the said fire originated in an adjacent building to plaintiff’s, and that the destruction of her property by same was not occasioned by any mistake, carelessness, or negligence on her part, but solely on account of the careless, willful and wanton neglect on the part of the defendant to furnish the hydrants above referred to with the water which they were required, and had obligated themselves to do, and upon their doing of which plaintiff confidently relied.

16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Canestrino v. Powell
56 S.E.2d 566 (Supreme Court of North Carolina, 1949)
Coleman v. . Mercer
49 S.E.2d 405 (Supreme Court of North Carolina, 1948)
Chipley v. . Morrell
45 S.E.2d 129 (Supreme Court of North Carolina, 1947)
Abrams v. . Insurance Co.
29 S.E.2d 130 (Supreme Court of North Carolina, 1944)
General American Life Insurance v. Stadiem
25 S.E.2d 202 (Supreme Court of North Carolina, 1943)
Boone v. . Boone
9 S.E.2d 383 (Supreme Court of North Carolina, 1940)
In Re Estate of Cooke
292 N.W. 96 (Supreme Court of Minnesota, 1940)
Wolff v. Employers Fire Ins. Co.
140 S.W.2d 640 (Court of Appeals of Kentucky (pre-1976), 1940)
Bailey v. . Light Co.
195 S.E. 64 (Supreme Court of North Carolina, 1938)
McDonald v. Pend Oreille Mines & Metals Co.
65 P.2d 1250 (Washington Supreme Court, 1937)
James v. Sartin Dry Cleaning Co.
181 S.E. 341 (Supreme Court of North Carolina, 1935)
First Carolinas Joint Stock Land Bank v. Page
173 S.E. 312 (Supreme Court of North Carolina, 1934)
Brantley v. . Collie
171 S.E. 88 (Supreme Court of North Carolina, 1933)
Nosse v. Rose
186 N.E. 622 (Ohio Court of Appeals, 1933)
Tipton v. Sparta Water Co.
57 S.W.2d 793 (Tennessee Supreme Court, 1933)
Kentucky Utilities Co. v. Farmers' Co-Op. Stock Yards Co.
54 S.W.2d 364 (Court of Appeals of Kentucky (pre-1976), 1932)
Benton v. Board of Education of Cumberland County
161 S.E. 96 (Supreme Court of North Carolina, 1931)
First Carolinas Joint Stock Land Bank of Columbia v. Courtway
157 S.E. 864 (Supreme Court of North Carolina, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
46 L.R.A. 513, 32 S.E. 720, 124 N.C. 328, 1899 N.C. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gorrell-v-greensboro-water-supply-co-nc-1899.