American Surety Co. v. Plank & Whitsett, Inc.

165 S.E. 660, 159 Va. 1, 1932 Va. LEXIS 169
CourtSupreme Court of Virginia
DecidedSeptember 22, 1932
StatusPublished
Cited by14 cases

This text of 165 S.E. 660 (American Surety Co. v. Plank & Whitsett, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Surety Co. v. Plank & Whitsett, Inc., 165 S.E. 660, 159 Va. 1, 1932 Va. LEXIS 169 (Va. 1932).

Opinion

Hudgins, J.,

delivered the opinion of the court.

Statement of Facts

Mrs. May B. Cooper and Mrs. Ruth C. Whitsett were the owners of two lots, one in Salem and one in Blacksburg. They made a contract with Plank & Whitsett, Inc., wherein the corporation agreed to bear a part of the cost of the [5]*5erection of a theater building in Salem and lease it after completion, with an option to purchase. A similar contract was made with Blacksburg Realty Corporation for the erection and leasing of a theater building in Blacksburg. All the stock in the two corporations was owned or controlled by the same parties; R. F. Plank was active manager of both corporations.

On April 23, 1929, R. F. Plank, in the name of Plank & Whitsett, Inc., as owners, made a contract with Morris C. Miller & Son, general contractors, for the erection of the theater building on the Salem lot, the cost of which building, including extras, totalled $58,743.65. On the same day R. F. Plank, in the name of Blacksburg Realty Corporation made a similar contract with Morris C. Miller & Son for the erection of a theater building in Blacksburg. The agreed cost of the construction of this building, including extras, totalled $69,918.

For the erection of the theater building in Salem the contractor was required to give bond for the faithful performance of his contract. No such bond was required of the contractor for the erection of the building in Blacks-burg. On May 18, 1929, Morris C. Miller & Son, as principal, and American Surety Company, as surety, executed the required bond in the penal sum of $46,000, payable to Plank & Whitsett, Inc., as obligee. The condition of this bond reads thus:

“ * * * if the principal shall faithfully perform the contract on his part, and satisfy all claims and demands, incurred for the same, and shall fully indemnify and save harmless the owner from all cost and damage which he may suffer by reason of failure so to do, and shall fully reimburse and repay the owner all outlay and expense which the owner may incur in making good any such default, and shall pay all persons who have contracts directly with the principal for labor or materials, then this obligation shall be null and void; otherwise it shall remain in full force and effect.”

[6]*6The contract contained the following provisions for payments to be made the contractor:

“On or about the tenth day of each month eighty-five per cent of the value, based on the contract prices, of labor and materials incorporated in the work and of material suitably stored at the site thereof up to the first day of that month, as estimated by the architect, less the aggregate of previous payments; and upon substantial completion of the entire work a sum sufficient to increase the total payments to eighty-five per cent of the contract price.

“ * * * Final payment shall be due fifteen days after substantial completion of the work, provided the work be then fully completed and the contract fully performed. * * *

“Before issuance of final certificate the contractor shall submit evidence satisfactory to the architect that all pay rolls, material bills, and other indebtedness connected with the work have been paid.”

Before any payments became due under either contract and on the sapie day that the bond was executed, the owners loaned to Morris C. Miller & Son $5,000, and by July 20th had increased the amount of this loan to $35,000, which sum was evidenced by four notes—No. 1 dated May 18, for $5,000; No. 2 dated May 27, for $15,000; No. 3 dated June 24, for $5,000; and No. 4 dated July 20, for $10,000—all payable to Plank & Whitsett and signed by Morris C. Miller & Son. It was agreed that these notes should be paid by deducting $4,000 a month, beginning July 1st, from the sums to become due the contractor for the erection of either, or both, buildings. By October 10, 1929, $20,000 of the $35,000 had been collected in this manner.

On October 19, 1929, Plank & Whitsett answered the following questions, submitted to them by the surety, thus:

“Has the contract been fully and satisfactorily completed? No.

“Amount of work completed to date. About half (putting on roof).

[7]*7“Total amount paid to contractors. $24,324.60.

“Amount of retained percentage. 15%.

“Have all labor and material bills been paid? Unable to determine.”

Again on January 2, 1930, the same questions were submitted and the same answers given, except it was stated that eighty per cent of the work had been completed and $34,854.60 had been paid the contractor.

On January 12 and 20, 1930, notices were given that unless improvement was made in the progress of the work on the Salem building the owners would take charge and complete the same. Pursuant to these notices, on January 29, 1930, the owners assumed charge and later completed the building. Plank & Whitsett thereupon rendered the following account to the contractor and the surety company.

“Original contract amount.......$ 46,000.00

Amount added to contract to date. 12,743.65

Total contract to date..................... $ 58,743.65

Total certified prior to Jan. 29, 1930......... 38,444.60

Total uncertified to date................... $ 20,299.05

Total cost of construction after

Jan. 29/30 ................$ 13,759.84

Penalty for 154 days’ delay @

$20.00 .................... 3,080.00

Claims by owner for unpaid balance of advanced amount

to M. C. Miller & Son....... 9,709.00

Total due owner ........................ $ 26,548.34

Total uncertified to date.................. 20,299.05

Balance due by Miller & Son.............. $ 6,249.29”

Upon the default of the contractor it appeared that $18,000 was due by the contractor for unpaid bills for labor [8]*8performed and material used in the Salem building. Parties holding these claims took the necessary steps to perfect mechanics’ liens and filed suit against the owners, Plank & Whitsett, Inc., the contractor and American Surety Company to enforce their liens against the building and to obtain judgment against the contractor and the surety.

The trial court held that, by reason of advances made, the owners were not liable to the contractor, and hence the laborers and materialmen were entitled to no liens on the building, but gave judgment for the amount of the claims against the contractor and the surety. No appeal was sought from this decree. The surety company paid the judgments and immediately filed an answer and cross-bill, claiming that it was entitled to reimbursement from the owners for the sum of $18,000 and $108.68 costs. From an adverse decree the surety appealed.

Opinion

The surety contends that it is entitled to reimbursement from the owners because they changed the terms of the contract by making large premature payments to the contractor and failing to retain fifteen per cent of the agreed costs of construction, and in so doing were guilty of bad faith, amounting to fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Columbia Realty Venture, L.L.C. v. Dang
83 Va. Cir. 258 (Fairfax County Circuit Court, 2011)
XL Specialty Ins. Co. v. Dept. of Transp.
611 S.E.2d 356 (Supreme Court of Virginia, 2005)
Continental Insurance v. City of Virginia Beach
908 F. Supp. 341 (E.D. Virginia, 1995)
Southwood Builders, Inc. v. Peerless Insurance
366 S.E.2d 104 (Supreme Court of Virginia, 1988)
Standard Accident Insurance v. Copper Hills Motor Hotels, Inc.
424 P.2d 154 (Arizona Supreme Court, 1967)
Standard Accident Insurance v. Copper Hills Motor Hotels, Inc.
406 P.2d 248 (Court of Appeals of Arizona, 1965)
Graybar Electric Co. v. Manufacturers Casualty Co.
122 A.2d 624 (Supreme Court of New Jersey, 1956)
Hochevar v. Maryland Casualty Co.
114 F.2d 948 (Sixth Circuit, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
165 S.E. 660, 159 Va. 1, 1932 Va. LEXIS 169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-surety-co-v-plank-whitsett-inc-va-1932.