Standard Accident Insurance v. Copper Hills Motor Hotels, Inc.

406 P.2d 248, 2 Ariz. App. 46, 1965 Ariz. App. LEXIS 413
CourtCourt of Appeals of Arizona
DecidedOctober 7, 1965
DocketNo. 1 CA-CIV 110
StatusPublished

This text of 406 P.2d 248 (Standard Accident Insurance v. Copper Hills Motor Hotels, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Accident Insurance v. Copper Hills Motor Hotels, Inc., 406 P.2d 248, 2 Ariz. App. 46, 1965 Ariz. App. LEXIS 413 (Ark. Ct. App. 1965).

Opinion

STEVENS, Chief Judge.

Copper Hills Motor Hotels, Inc., a corporation, recovered a judgment on a bond wherein Standard Accident Insurance Co., a corporation, was the surety. The bond was executed to guarantee the payment of laborers and materialmen in connection with the construction of improvements to real property. The surety appeals.

Copper Hills is the owner-operator of a motel. Peter J. Wurts has been the President and General Manager of this corporation at all times material to this opinion. Paramount Builders was a corporation duly licensed as a contractor and at all times material to this opinion, William G. Spurr was its President. In 1960 Copper Hills called for bids for the construction of an addition to the motel. Paramount was the successful bidder and. a contract for the construction was executed on 1 July 1960. The work commenced shortly after the execution of the contract and was completed by mid September of the same year. The contract contained the following provisions:

“3. CONTRACT PRICE AND PAYMENT METHOD.
Owner shall pay to Contractor the sum of $35,500 in consideration of the performance of the obligations undertaken by Contractor herein. The said sum shall be deposited, before commencement of construction, in cash, and/or by the assignment of construction loan proceeds. The entire contract price shall be advanced to Contractor at least as rapidly as set out below:
“1. $10,000.00 when Foundations, 1st floor and rough plumbing is complete.
“2. $7,000.00 when walls are erected and 2d floor is in place.
“3. $7,000.00 when rough framing, electrical, plumbing and sheet metal are complete.
“4. $7,000.00 when ready for paint.
“5. $4,500.00 when complete.

In the process of construction, extras were incurred in the sum of $1,468.85, resulting in an overall contract obligation from Copper Hills to Paramount in the sum of $36,968.85. Pursuant to the terms of the contract, Paramount was obligated to secure a performance bond and this was secured from Standard, Paramount paying the required bond premium. In the bond Paramount was the principle, Standard was the surety and Copper Hills was referred to as the “Owner”, being the beneficiary, the bond being in the principal sum of $35,500. The bond provided in part:

“That the Owner shall faithfully and punctually perform all the terms and conditions of said contract to be performed by the Owner.”

[48]*48On the 31st dajr of May, 1960, Spurr, President of Paramount, requested Wurts’, President of Copper Hills, financial assistance and the two men went to a bank where a $10,000 loan was secured, Wurts and Spurr as individuals signing a demand note in that sum. The money was for the use of Paramount in its corporate status. Both Wurts and Spurr intended that the money be repaid in approximately two weeks. The loan was made by the bank on the individual credit of Wurts. Paramount received and used the money in its business, Wurts testifying that he knew that the purpose of the loan was for the immediate corporate needs of Paramount in relation to existing payrolls and current expenses. This was corroborated by the testimony of Spurr. Wurts and Spurr both testified that the fact of the loan had no bearing upon the fact that Paramount was the successful bidder for the enlargement of the motel.

There had been two or three prior loans from Wurts to Spurr’s business interests. Wurts was interrogated as to whether or not he had had any prior experience with Spurr in relation to the repayment of previous loans and whether or not it was necessary “to keep after him in order to get him to repay the loans”. Wurts replied in the affirmative and also testified that “on all prior occasions, I had found that I had to make several requests for payment; if I did not, the note was prone to continue on, so I had to instigate those actions at that time”.

The first three progress payments were made by Copper Hills to Paramount as specified in the contract; $10,000 being paid by check dated 1 August 1960; $7,000 being paid by check dated 4 August 1960; and $7,000 being paid by check dated 16 August 1960. In the meantime, no part of the $10,000 loan had been paid. About this time Wurts asked Spurr (in Spurr’s capacity as President of Paramount) if it would be possible for Wurts to apply the funds which were coming • from Copper Hills to Paramount out of the construction contract to the payment of the note. Wurts testified that “at this time it was past due some amount. I was desirous of retiring the note; having the debt taken care of. I had asked him if he would mind using these funds to pay this obligation to which he concurred”. On or about the 22nd day of August, Wurts asked Spurr for the entire $7,000 progress payment which was then due. The $7,000 was disbursed by Copper Hills as follows: (1) a check for $3,846.67 was given to Paramount and by Paramount deposited in its bank account; and (2) a check for $3,153.33 was made payable to Paramount and by Paramount endorsed to Wurts who then deposited the check in his personal account. The $153.33 represented interest which was due on the $10,000 loan. These checks were issued on the 22nd day of August and on the 31st day of August Wurts paid $153.33 in interest to the bank. Wurts did not make a payment on the principal of the debt, he retained the use of the $3,000. When asked why he was unable to secure the entire $7,000 progress payment, Wurts. testified that Spurr requested that a portion of it be retained by his corporation to meet current expenses. When asked whether or not Spurr had told him that he needed the money desperately, Wurts replied that he did not recall that terminology although that he realized that the word “desperately” was in the deposition and in any event, Spurr convinced him that he had a need for the money.

On the 9th of September 1960, Copper Hills issued a $2,000 check payable to Wurts which check Wurts endorsed and deposited in his personal account, this check being charged against the money which Copper Hills owed to Paramount on the contract. On the 12th day of September 1960, Paramount paid the sum of $2,000 directly to the bank and this money was applied on the principal on the note. As of that date there remained an unpaid principal balance due to the bank in [49]*49the sum of $8,000. On the 15th day of September the following sums remaining due on the contract were paid:

Final Draw.....$ 4,500.00
Extras ...... 1,468.85
TOTAL . . $ 5,968.85

This was "paid” by Copper Hills to Paramount in the following manner:

Interest on the loan in the sum of $24.75 was paid by a check to Wurts and by Wurts deposited in his personal account.

$5,000 was retained by Copper Hills and a bookkeeping entry was made offsetting advances on loans which Copper Hills had made to Wurts.

$944.10 was paid to Paramount and retained by Paramount. Spurr had agreed to this method of payment. Wurts renewed the note in December and at a later date paid it in full.

Standard had no knowledge of the arrangements between Wurts and Spurr whereby Copper Hills received credit for in excess of $8,000 on the contract obligation. Shortly after the “final payment” as above set forth, liens in excess of $26,000 were filed against the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Webb v. Crane Co.
80 P.2d 698 (Arizona Supreme Court, 1938)
American Surety Co. v. Plank & Whitsett, Inc.
165 S.E. 660 (Supreme Court of Virginia, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
406 P.2d 248, 2 Ariz. App. 46, 1965 Ariz. App. LEXIS 413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-accident-insurance-v-copper-hills-motor-hotels-inc-arizctapp-1965.