Jones v. Nelson County

120 S.E. 140, 137 Va. 612, 1923 Va. LEXIS 184
CourtSupreme Court of Virginia
DecidedNovember 15, 1923
StatusPublished
Cited by1 cases

This text of 120 S.E. 140 (Jones v. Nelson County) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. Nelson County, 120 S.E. 140, 137 Va. 612, 1923 Va. LEXIS 184 (Va. 1923).

Opinion

Kelly, P.,

delivered the opinion of the court.

The county of Nelson undertook to build for the State of Virginia two and sixty-nine hundredths miles of macadam road. This undertaking on the part of the county was evidenced by a resolution of the board of supervisors, passed July 9, 1919, and by contract in writing dated July 16, 1919, between the latter and George P. Coleman, State Highway Commissioner. The total estimated amount to be received by Nelson county for this work was $34,936.00.

Thereafter, on August 30, 1919, the county sublet the contract for the construction of the road to W. C. Jones at an estimated cost of $33,400.30 upon the terms, plans and specifications provided for in the eon-[614]*614tract between the county and the State. There was some little uncertainty and confusion in the evidence as to whether any formal contract was executed between the county and the subcontractor, but it is clear, not only from the resolution adopted by the board of supervisors on August 30, 1919, but also by the whole subsequent course of dealings between the parties, that the subcontractor simply stepped into the shoes of the county, and that both parties considered themselves bound by the same terms as those which were embraced in the contract-between the county and the State Highway Commission.

Jones proceeded with the work until September 21, 1920, when he quit pursuant to directions received by him from the State Highway Department, ratified and approved by Nelson county. The work on the road had not been completed at that time, but was taken up and finished by the county of Nelson.

This litigation had its origin in an account which Jones rendered against the county, claiming the sum of $23,668.48 for work done and material furnished by him up to the time of his discharge. The account was presented by him to the board, which declined to pay. the same, or any part thereof, and he appealed to the circuit court, where a jury brought from Albemarle county returned a verdict in favor of the defendant. The court entered up a judgment on this verdict, and Jones then obtained this writ of error.

In the trial of the case in the circuit court the defendant was called upon for its grounds of defense, and filed a statement, the material part of which was as follows:

“The defendant expects to show that the said Jones went to work under said contract, and he did a part of said work; that he did not do the work in the manner [615]*615provided for in said contract under which he was working; that he was called upon to so do the work and refused to do it, and that thereupon in accordance with the terms of said contract the said department stopped him from doing any more work on said road, and had it completed at the costs of the said W. C. Jones in accordance with said contract.
“That upon the completion of said road there was left in the hands of the Highway Department, belonging to the said Jones, the sum of $670.65 which has been paid to said county of Nelson by the said State Highway Department, and which is now by the said county of Nelson, Va., paid into court for the said W. C. Jones, and which is in full of all amounts due the said Jones, in this cause, and which would have been paid before, but could not be paid until the completion of the work, which has taken place long since the bringing of this action.”

It will be observed that the gist of the defense relied upon was that Jones had failed to do the work in the manner required by the contract; that he was for that, reason discharged, and that the road was then completed at the cost of Jones, leaving a balance due him of only $670.55 which had been paid into court.

The evidence makes it clear that the claim-filed by Jones for over $23,000.00 was greatly exaggerated and that in no view of the case could the jury have properly found a verdict in his favor for anything like that amount; but there was evidence tending to prove that if, on September 21, 1920, the county had taken over the work from Jones and made a final settlement with him as of that date without regard to what it would cost to complete the job, he would have been entitled to a substantial sum, ranging from a minimum of about $4,000.00 to a maximum of about $6,000.00. The de[616]*616cisive question on this appeal is whether the county had the right to complete the work and charge Jones with the cost thereof in excess of what he could himself have charged the county for its construction. The rights of the parties in this respect are to be determined by the terms of the express contract between the Highway Commissioner and the county of Nelson, subsequently assigned to and assumed by Jones. That contract contained the following provision:

“Annulment of Contract: If at any time the State Highway Commissioner shall be of the opinion that the said work, or the replacing of any defective work or material when ordered is unnecessarily delayed and will not be finished within the time prescribed, he shall notify the contractor and his surety in writing to that effect. If the contractor should not, within three (3) days thereafter, take such measures as will, in the judgment of the State Highway Commissioner, insure the satisfactory progress of the work, the party of the first part may then notify the said contractor to dis- • continue all work under this contract and declare said contract forfeited, and relet the said work in whole or in part so far as not completed, or it may instead use all tools, materials, plant, appliances, houses, machinery, and other appurtenances used th the contractor on the date on which the three (3) days’ notice was given, and it may employ such additional force of labor and teams and purchase such additional materials and tools for the work as in the opinion of the State Highway Commissioner are required, and shall use and pay for said forces and materials, and the said party of the first part may withhold, from payment due or that may become due to the contractor, such sum or sums as it may judge necessary to secure payments for said forces and materials. All costs and charges incurred by the [617]*617Commissioner, together with the cost of completing the work under contract, shall be deducted from any moneys due or which may become due said contractor. In ease the expense so incurred by the Commissioner shall be less than the sum which would have been payable under the contract, if it had been completed by said contractor, then the said contractor shall be entitled to receive the difference, and in case such expense shall exceed the sum which would have been payable under the contract, then the contractor and the surety shall be liable and shall pay to the State the amount of said excess.”

It is to be observed that the right of the county to take over and complete the work at the cost of the contractor depended upon the giving of three days’ notice, and upon the contractor’s failure, after. such notice, to take such measures as would in the judgment of the Highway Commissioner insure satisfactory progress of the work; and, moreover, that if the work was taken over and completed at the risk and cost of the contractor, the same had to be done either by subletting the residue of the work, or if the county undertook to do it, it was to use all tools, materials and appliances in use by the contractor on the date of the giving of such notice, together with such additional force and material as might be necessary for that purpose.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fidelity & Casualty Co. v. Copenhaver Contracting Co.
165 S.E. 528 (Supreme Court of Virginia, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
120 S.E. 140, 137 Va. 612, 1923 Va. LEXIS 184, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-nelson-county-va-1923.