United States ex rel. J. B. Van Sciver Co. v. United States Fidelity & Guaranty Co.

178 F. 721, 1910 U.S. App. LEXIS 5394
CourtU.S. Circuit Court for the District of Eastern Pennsylvania
DecidedMarch 12, 1910
DocketNo. 730
StatusPublished
Cited by14 cases

This text of 178 F. 721 (United States ex rel. J. B. Van Sciver Co. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Eastern Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. J. B. Van Sciver Co. v. United States Fidelity & Guaranty Co., 178 F. 721, 1910 U.S. App. LEXIS 5394 (circtedpa 1910).

Opinion

J. B. McPHERSON, District Judge.

1. This suit is brought upon a surety bond that was given to the United States under the act of 1894 (Act Aug. 13, 1894, c. 280, 28 Stat. 278 [U. S. Comp. St. 1901, р. 2523]) by a principal contractor (Neafie & Levy Company), and recovery is sought for labor done and materials furnished to the principal by a subcontractor, the J. B. Van Sciver Company. The claim arose in the summer of 1904. The Neafie & Levy Company received full payment from the United States about October 31st of that year, but has not paid any part of the subcontractor’s claim. In May, 1909, the Van Sciver Company applied to the War Department for a certified copy of the bond in order to begin suit thereon, and the present action was brought on May 28th. This is the same bond upon which two other, suits by subcontractors have already been brought and determined ; one suit being United States, to Use of Griscom-Spencer Co., v. United States Fidelity, etc., Co. (C. .C-) 173 Fed. 269, and the other being United States, to Use of Williamson Bros. Co., v. Same (C. C.) 171 Fed. 247. In the last-named case, Judge Lanning decided that the limitation of one year prescribed by the act-of 1905 (Act Feb. 24,1905, с. 778, 33 Stat. 811 [U. S. Comp. St. Supp. 1909, p. 948]), supplemental to the act of 1894, did not apply to the contract between the Neafie & Levy Company and the United States, because it was fully completed several months before the limitation was adopted. Judge Lanning’s ruling was approved by the Circuit Court of Appeals in its opinion delivered in the Griscom-Spencer Case, 178 Fed. 692, and I need do no more than refer to that decision as sufficient justification for overruling now the same defense.

2. The second defense requires some further consideration of the Griscom-Spencer suit. The Court of Appeals there held an affidavit by the surety to be insufficient because it merely averred that the creditor had favored the principal debtor without the knowledge or consent of the surety by extending the time wherein the debt might be paid. The creditor had taken the principal’s promissory note at three months and had it discounted, and during this period the principal had received from the United States the whole balance due upon his contract, and had shortly thereafter gone into the hands of a receiver. But the surety failed to aver actual injury from the creditor’s acts, or that the receivership had been caused by the principal’s insolvency; and, accordingly, the Court of Appeals decided that, since a surety company undertakes its obligation, not as a volunteer, but on the footing of a compensated business, the rule of strictissimi juris, which is ordinarily applied in relief of an individual voluntary surety, was not applicable, but that such a company must show actual injury by the creditor’s acts before it could claim relief from its obligation on that account. In the present suit the affidavit attempts to set up an extension of time granted by the Van Sciver Company, declaring that about October 28, 1904, the company .“accepted the promissory note of the Neafie & Levy Ship & Engine Building Company, dated October 28-, [723]*723190!, payable four months after date for $4,890.” The. receivership on October 31st is then averred, and it is added that the Neafie & Levy Company was “at that time insolvent.” It is therefore argued that the question is now presented which the Circuit Court of Appeals declined to decide in the Griscom-Spencer Case, namely, the effect of the principal's insolvency during the running of the note; and it is contended that a presumption of injury upon which the surety may rely arises from the bare happening of the debtor’s insolvency. But the surety’s chief difficulty is, I think, that there was no extension o f time in the present case, as will appear from the following paragraph in the statement of claim:

“That no part of the said sum lias been received by the said plaintiff Corporation. nor has the said plaintiff corporation grained any extension in time of payment to 1lie Neafie <& Levy ¡Ship & Engine Building (Company, although demand has frequently been made on them to pay, has refused Co make any X»aymenls, promptly or otherwise, to this plaintiff, which supplied both labor and materials in the prosecution of the work of the said Neafie & Bevy Ship <& Engine Building Company, in or about the construction of the said hulls as provided for in the said contract between the United States and the Neafie & Levy Ship & Engine Building Company. That upon the 28th day of October, A. I>. 3904, the said Neafie & Levy Ship & Engine Building Company did send to tlie said plaintiff corporation a promissory note in the sum of Ui.WkUiO. payable four months after date. That the said plaintiff corporation did not desire or request the aforesaid promissory note and did refuse to receive the same oilier than as collateral security, and not in payment or in extension of the aforesaid claim, and did, during the period between the date of the noie, that is to say, between October 28, 1904, and February 28, 190.1, make frequent, demands on the Neafie & Levy ,SIdp & Engine Building Company to pay the account as heretofore stated, and the said Neafie & Levy Company did frequently promise to pay. but did utterly fail so to do. That the aforesaid promissory note was not discounted by the said plaintiff corporation or received by them other than as evidence o,! indebtedness, and that neither the aforesaid account nor the promissory noto has been paid.”

The affidavit of defense does not deny, and therefore admits, these averments. It simply sets up that the Van Sciver Company “accepted” the promissory note, and this averment is entirely consistent with the statements that the note was only accept ed as collateral, was not taken in payment or in extension of the debt, and was not discounted for the plaintiff’s benefit. Since the statement of claim must be accepted as correct in these particulars, there was no extension of time, and the surety’s defense upon that ground is not well taken.

But, even if there had been a valid and binding extension, it would still be necessary to inquire whether the surety was injured thereby. The surety does not aver any actual harm, but relies upon the presumption of injury, and argues that the situation is analogous to the forging of a depositor's signature to a check, and his failure to notify the bank promptly upon his discovery of the crime. Counsel contends that in such á case tlie depositor loses his right of action if he fail to notify the bank promptly, and that “the law assumes — and does not find it necessary to conduct an inquiry to verify the assumption — that, had the notice been given promptly, the bank might have taken steps to protect itself”- — citing Trust Company v. Bank, 185 Pa. 586, 40 Atl. 91, and Bank v. Morgan, 117 U. S. 115, 6 Sup. Ct. 657, 29 L. Ed. 811. Whatever the rule may be in the case supposed, it seems to me more [724]*724pertinent to refer to the decision of the Supreme Court in Guaranty Co. v. Pressed Brick Co., 191 U. S. 416, 24 Sup. Ct. 142, 48 L. Ed. 242, in which not merely an analogous question, but the very question now under consideration (the rights of a surety company under a bond like this), was considered in some of its aspects. The syllabus sufficiently states the decision:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gebrueder Heidemann, KG v. AMR Corp.
746 P.2d 579 (Idaho Court of Appeals, 1987)
Gellis v. S. Gellis & Co., Inc.
322 A.2d 287 (Court of Chancery of Delaware, 1974)
Fred Christensen, Inc. v. Hansen Construction Co.
21 P.2d 195 (Oregon Supreme Court, 1933)
United States v. Quaker Industrial Alcohol Corp.
2 F. Supp. 863 (E.D. Pennsylvania, 1932)
Maryland Casualty Co. v. Ohio River Gravel Co.
20 F.2d 514 (Fourth Circuit, 1927)
Murray City v. Banks
219 P. 246 (Utah Supreme Court, 1923)
Standard Salt & Cement Co. v. National Surety Co.
158 N.W. 802 (Supreme Court of Minnesota, 1916)
People ex rel. T. B. Townsend Brick & Contracting Co. v. Bowen
187 Mich. 257 (Michigan Supreme Court, 1915)
Justice v. Empire State Surety Co.
209 F. 105 (E.D. Pennsylvania, 1913)
First National Bank v. Livermore
133 P. 734 (Supreme Court of Kansas, 1913)
Vulcan Steam Shovel Co. v. Flanders
205 F. 102 (E.D. Michigan, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
178 F. 721, 1910 U.S. App. LEXIS 5394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-j-b-van-sciver-co-v-united-states-fidelity-circtedpa-1910.