American Surety Co. v. Broadway Improvement & Investment Co.

271 P. 19, 39 Wyo. 195, 1928 Wyo. LEXIS 100
CourtWyoming Supreme Court
DecidedOctober 16, 1928
Docket1369
StatusPublished
Cited by3 cases

This text of 271 P. 19 (American Surety Co. v. Broadway Improvement & Investment Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Surety Co. v. Broadway Improvement & Investment Co., 271 P. 19, 39 Wyo. 195, 1928 Wyo. LEXIS 100 (Wyo. 1928).

Opinions

Tidball, District Judge.

The parties will be referred to as in the trial court.

The plaintiff and defendant Martin Robinson made an agreement on October 25th, 1923, by the terms of which Robinson was to provide all the material and perform all the work for the construction of a one-story brick storeroom and showroom in Casper, Wyoming, for the price of $23,000.00. The contract provided that the building should be erected according to designated plans and specifications prepared by Rainwater and Epling, architects, *200 which were made a part of the contract. The contract provided further:

“It is understood and agreed by and between the parties hereto that the said party of the first part (Robinson) shall buy all lumber, steel, brick and other material now on said premises which was bought to be used in connection with this contract for use in the erection of said building. ’ ’

The contract further provided that the party of the second part. (Broadway Improvement and Investment Company) should pay upon estimates of the architects as the work progressed eighty-five percent of such estimates and withhold payment of fifteen percent until thirty days after the building was completed and until the jDroduction of proper evidence to show that all labor and material claims had been paid so that no liens could be filed on the building. It was further agreed that all disputes between the parties should be settled by the architects named in the contract and that “their decision shall be considered final.” The building was to be completed and ready for occupancy “not later than January 1st, 1924.” There was a further stipulation in the contract for a surety bond in the sum of $5,000 payable to the Improvement Company indemnifying it “in full against all loss and damage which said party of the second part may sustain under this contract by reason of liens or other damage which may accrue and that said party of the second part may be required to pay.”

The bond was duly executed by the builder with the defendant surety company as surety, in the sum of $5,000 on November 9th, 1923. The bond recites that,

“Whereas, the principal has entered into a written contract dated.191. — , with the obligee for the erection of a brick building on Lot 13 in Block 100, a copy of which is hereto annexed, Now, therefore, the condition of this obligation is such, that if the prin *201 cipal shall indemnify the obligee against any loss or damage directly arising by reason of the failure of the principal to faithfully perform said contract, then this obligation shall be void.”

The bond further provided that in the event of any default on the part of the principal, a written statement of the particular facts showing such default and the date thereof should be delivered to the surety by registered mail at its office in Denver, Colorado, promptly, and, in any event, within ten days after the obligee or his representative or the architect should learn of such default; that the surety should have the right within thirty days after the receipt of such statement to proceed with the performance of the contract. Another condition of the bond was that no claim, suit or action by reason of any default should be brought against the principal or surety after April 15th, 1924, nor should recovery be had for damages accruing after that date. The bond further provided that no change should be made in such plans and specifications which would increase the amount to be paid the principal more than tern percentum of the penalty of the bond without the written consent of the surety. The building contract above referred to was attached to and became a part of the bond.

In October, 1923, and after the execution of the building contract but before the bond was executed, another agreement was entered into between Robinson, the builder, and the Broadway Improvement and Investment Company, which contract was never accepted by the surety company and concerning the execution of which it had no notice at the time its bond was executed. This contract .recited the execution of the former building contract and then provided that “it is the intention and purpose of this agreement that such terms and character of payment be particularly specified and agreed upon between the parties hereto, ’ ’ and then it is provided that ‘ ‘ a credit in *202 the sum of Four Thousand Four Hundred ($4,400.00) Dollars shall be allowed and given by the party of the first part to the party of the second part” upon the contract price of $23,000, “upon account of certain lumber and brick which are at this date upon the site where said building is to be erected.” It then provided that $15,000 cash should be paid upon estimates as provided in the building contract and the balance of the total building price in the sum of $3,600 was covered by a promissory note in that amount running from R. N. Van Sant to the Broadway Improvement and Investment Company and endorsed without recourse to Robinson.

The suit is brought for the purpose of recovering the sum of $4,448.63, which plaintiff claims it was compelled to pay above the contract price of $23,000 on account of the failure of the defendant Robinson to pay for labor and material, as a result of which failure liens were filed against the building in question.

The original petition was filed on November 18th, 1924. The ease was tried and the District Court gave the plaintiff judgment in the sum of $3,936.00, together with interest and costs, against the surety company, Robinson not having been served with summons.

The surety company contends that the judgment was erroneous for several reasons:

1. The action was not brought within the time limited in the bond, to-wit: April 15th, 1924.

2. Certain changes, were made in the construction of the building so that the plans and specifications were departed from.

3. Plaintiff failed to show it had been damaged in the amount found by the trial court or in any amount.

4. The obligee failed to retain the fifteen percent of estimates as provided in the contract.

5. The contract executed subsequent to the building contract, by virtue of which the price of the material on the ground was fixed at $4,400 and the Yan Sant note was *203 agreed upon, was not binding upon tbe surety company and materially altered tbe -contract tbe performance of which tbe bond insured.

6. Tbe court erred in tbe admission of evidence.

7. Tbe surety company was not notified of tbe default of tbe contractor in tbe manner provided in tbe bond.

We shall discuss these propositions in tbe order named.

Tbe action was not commenced until November 18th, 1924, whereas tbe bond as above noted provided that action should be commenced on or before April 15th, 1924. We have examined all tbe cases cited by both parties on this proposition, and many not cited, and there are undoubtedly some eases bolding tbe obligee to a strict compliance with such prevision. See Lesher v. U. S. Fidelity and Guaranty Company, 239 Ill. 502, 88 N. E. 208; Walters v. Fisher, 291 Pa. 311, 139 Atl. 842.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richardson Associates v. Lincoln-Devore, Inc.
806 P.2d 790 (Wyoming Supreme Court, 1991)
Central Contractors Co. v. Paradise Valley Utility Co.
634 P.2d 346 (Wyoming Supreme Court, 1981)
Industrial Equipment Corp. v. Builders Insurance
108 P.R. Dec. 290 (Supreme Court of Puerto Rico, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
271 P. 19, 39 Wyo. 195, 1928 Wyo. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-surety-co-v-broadway-improvement-investment-co-wyo-1928.