American Indemnity Co. v. Board of Trustees

200 S.W. 592, 1918 Tex. App. LEXIS 53
CourtCourt of Appeals of Texas
DecidedJanuary 2, 1918
DocketNo. 5914.
StatusPublished
Cited by5 cases

This text of 200 S.W. 592 (American Indemnity Co. v. Board of Trustees) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Indemnity Co. v. Board of Trustees, 200 S.W. 592, 1918 Tex. App. LEXIS 53 (Tex. Ct. App. 1918).

Opinion

MOURSUND, J.

The board of trustees of the Robstown independent school district, in its corporate capacity, sued C. D. Patterson, as principal, and American Indemnity Company, as surety, upon a bond for the faithful performance of a contract between Patterson and said board of trustees to ' erect a school building for said school district, which contract was breached by Patterson. Tho pleadings of the parties are lengthy, and their nature will be sufficiently disclosed in discussing the various assignments of error. The case was dismissed as to Patterson, and upon a trial without a jury judgment was rendered against the American Indemnity Company for $20,160.

The findings of fact and conclusions of law of the trial court are lengthy, and therefore, instead of copying the same in full, we will, as we dispose of the assignments of error, copy of state the substance of those to which the assignments relate.

The contract provided, in substance, that Patterson should, within six months from the ■ date of the delivery to him of a certain $20,-000 issue of Robstown independent school district bonds, erect a two-story brick building. The bonds were delivered to Patterson on the 7th or 8th of January, 1914. When Patterson abandoned the building in October, 1914, it was about 55 per cent, completed. The specifications for the construction of the building contained the following provision:

“The contractor shall be entitled to one day in addition to said stipulated time for each day’s delay resulting from additional work or changes in work required from time to time or for specific delays from other causes, as may be approved by the architects or owners, which additional time must be stated by the contractor in writing within eight days of such delay, giving dates and causes, which if correct, shall be certified by the architect or owner. Should the contractor neglect to ask for additional time, within the time specified above, it is mutually agreed that no just claim exists or shall exist for an extension of time.” ,

*593 No request by the contractor for additional time was made in the manner specified. The court’s twentieth finding of fact reads:

“I find that due to weather and other conditions delays occurred in the progress of construction of said building, on account of which Patterson did not make, and the board of trustees did not require him to make, application in writing for additional time,- as provided in said contract, but said board of trustees waived said requirement of said contract.”

The indemnity bond contained the following provision:

“Provided, however, that in the event of any default on the part of said principal in the performance of any of the terms, covenants, or conditions of said contract, or in the event of any claim, demand, judgment, lien, cost, or fee being obtained or made against the said obligee, for or on account of the prosecution of the work as aforesaid, written notice thereof with a statement of the principal facts showing such claim, demand, judgment, lien, cost, or fee, and the date thereof, shall within thirty days after the same shall have come to the notice of the said obligee, be given to the American Indemnity Company at its office in the city of Galveston, Tex.”

The first notice given by the board to the indemnity company consisted of a letter written by Mr. Herrington, superintendent of Robstown schools, dated October 1, 1914, calling attention to the fact that the contract required the completion of the building by the 7th day of July, 1914, and that the building was little more than half completed, and Patterson had practically quit work. The court’s twenty-fourth, twenty-seventh, and thirty-third findings of fact are as follows:

“(24) I find that as soon as said board of trustees ascertained that said Patterson had abandoned said building, and within 30 days after said building had been so abandoned, said hoard of trustees in writing notified said American Indemnity Company that said building had been abandoned, and demanded that said American Indemnity Company perform said contract and complete and finish said building.”
“(27) I find that defendant American Indemnity Company had notice that said school building was not completed, furnished, and equipped in accordance with said contract within the time stipulated in said contract.”
“(33) I further find that there was no provision in the contract in this cause requiring 20 per cent, to be withheld by the board of trustees until the completion of said building, and that the bond sued on in this cause contained no such provision, and that the bond executed by the American Indemnity Company as surety did not provide that said American Indemnity Company should have the right, after default by Patterson, at its option, to assume or sublet said contract and to proceed thereunder as if no default or abandonment had occurred, and that said bond did not contain any provision, in case of default by Patterson, entitling the American Indemnity Company to subrogation, and that the bond contained no provision providing that failure to give notice of default should release the surety.”

The court’s sixth, seventh, and eighth' conclusions of law are as follows:

“(6) I find that a failure to, comply with that provision in the bond sued on as to notice would not release the surety from liability in the absence of a showing as to its materiality in the absence of a provision in the contract itself providing that the same should release the surety, or that the surety should have the right to-enter upon and take possession of the material on the ground, and become subrogated to the rights of the principal.”
“(7) I find that the defendant American Indemnity Company, the surety, had notice that the building was not completed within six months from the date of the delivery of the-bonds to Patterson.
“(8) I find that notice of Patterson’s default in the performance of his contract was given to the American Indemnity Company, the surety, in accordance with the contract.”

The first .eight assignments of error relate to the issue of notice, it being contended, with regard to questions of fact, that the-court’s findings of fact numbered 24, 27, and 33 are contrary to the great preponderance of the evidence, and that the evidence fails to show that notice as provided for in the'bond was given by the trustees to the indemnity company of the default of Patterson in failing to complete the building within the time contracted for, and further that the evidence does not show that the company had actual notice of such default, and with regard to questions of law that the court’s conclusions numbered 6, 7, and 8 are erroneous, and that in order for the trustees to recover it was incumbent upon them to allege and prove compliance on their part with the provision in the bond with respect to notice, regardless of whether or not the company had actual notice of the default.

[1]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burdon v. Burdon's Administratrix
9 S.W.2d 220 (Court of Appeals of Kentucky (pre-1976), 1928)
Citizens' Guaranty State Bank of Hutchins v. National Surety Co.
258 S.W. 468 (Texas Commission of Appeals, 1924)
American Indemnity Co. v. Board of Trustees
233 S.W. 878 (Court of Appeals of Texas, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
200 S.W. 592, 1918 Tex. App. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-indemnity-co-v-board-of-trustees-texapp-1918.