Board of Trustees of Robstown Independent School Dist. v. American Indemnity Co.

228 S.W. 105, 1921 Tex. App. LEXIS 660
CourtTexas Commission of Appeals
DecidedFebruary 23, 1921
DocketNo. 170-3180
StatusPublished
Cited by1 cases

This text of 228 S.W. 105 (Board of Trustees of Robstown Independent School Dist. v. American Indemnity Co.) is published on Counsel Stack Legal Research, covering Texas Commission of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Trustees of Robstown Independent School Dist. v. American Indemnity Co., 228 S.W. 105, 1921 Tex. App. LEXIS 660 (Tex. Super. Ct. 1921).

Opinion

SPENCER, J.

Plaintiff in error, the board of trustees of Robstown independent school district, brought this action against C. D. Patterson, as principal, and defendant in error, American Indemnity Company, a corporation, as surety, to recover upon a bond executed by them to secure the faithful performance of a contract by Patterson to erect for the Robstown independent school district a school house at Robstown, Tex., which contract had been breached by Patterson.

The school district, through the board of trustees, transferred to Patterson bonds of the district which had been voted and issued as means of providing the necessary funds for the erection of a school building.

Patterson was duly cited by publication, but failed to appear, and. upon motion of plaintiffs in error the cause as to him was dismissed. Defendant in error answered, seeking to be discharged upon the grounds: (1) That the contract required the completion of the building within a period of six months from the date of the delivery of the bonds to Patterson, and the bond required plaintiffs in error to give defendant in error written notice within thirty days of any default in the performance of any of the terms of the contract, and that the building was not completed within the time stipulated nor was the written notice required by the bond given ; and (2) that the contract between Patterson and the board of trustees was illegal and void as against public policy, in that the statutory requirements with reference to securing a school building permit and the sale of the bonds and the deposit of the proceeds from the sale of same had not been complied with.

The case was tried before the court without the aid of a jury, and judgment rendered in favor of plaintiffs in error for the sum of $20,160. Upon appeal the Court of Civil Appeals was of opinion that the failure- of the plaintiffs in error to give the surety written notice of Patterson’s failure to complete the building within six months after the delivery of the bonds to him was a breach of the provision of the bond requiring written notice to it within thirty days after notice of default had come to plaintiffs in error, and that such failure operated to release the surety; whereupon it reversed and rendered the judgment. (Civ. App.) 200 S. W. 592.

The .bonds were delivered to Patterson on the 7th or 8th of January, 1914. The building was abandoned by him in October, 1914, and before it was completed. Written notice within thirty days after the abandon-[106]*106’merit in October, 1914, was given to defendant in error by plaintiffs in error, but no notice prior thereto was ever given, of Patterson’s failure to complete tbe building, and neither was any statement in writing of the delays ever made and' presented to the owner or architect by Patterson as provided in the plans and specifications. Thus it becomes necessary to construe the contract to determine whether plaintiff in error was required to give written notice at the expiration of six months after the delivery of the bonds to Patterson of Patterson’s failure to complete the building within that time; and this involves the further question of whether, in the character of delays that postponed the completion of the building beyond the six months after the delivery of the bonds, Patterson was required to make a written statement within eight days of each such delay, to be certified by the owner or architect,- in order to exclude such delays in computing the six-month period.

Section 1 of the contract reads:

“The contractor, for the consideration hereinafter mentioned, doth * * * promise and ■agree * * * that he will within the space of six (6) months, from the delivery of the bonds, in a good and workmanlike manner, * * * build and finish a two-story brick school building, on such lot as is selected, and designated by the said board of trustees, in the town of Robstown, * * * according to :the plans and specifications drawn, submitted and accepted by the said board of trustees from Messrs. Adams & Adams, architects, of San Antonio, Tex., which said plans and specifications are hereto attached and made a part hereof.”

Section 9 of the contract reads:

“It is further agreed and understood by and between the parties hereto that the contractor shall not be held responsible for any delay in the completion of said school building beyond the time as specified in paragraph 1 hereof, by reason of fires, acts of Providence, and other acts beyond the control of the said contractor.”

The specifications for the contract contained this provision:

“The entire work is to be completed and fit for occupancy (as. set forth herein and by accompanying drawings) by-.' The contractor shall be entitled to one day in addition to said stipulated time for each day’s delay resulting from additional work or changes in work required from■ time to time, or for specific delays from other causes, [italics ours] as may be approved by the architects or owners which additional time must be stated by the contractor in writing within eight days of such delay, giving dates and causes, which, if correct, shall be certified by the architect or owner. Should the contractor neglect to ask for additional time within the time specified above, it is mutually, agreed that no just claim exists, or shall exist, for an extension of time.”

The indemnity bond contained the following provision with reference to notice:

“Provided, however, that in the event of any default on the part of said principal in the performance of any of the terms, covenants, or conditions of said contract, or in the event of any claim, demand, judgment, lien, cost or fee being obtained or made against said obligee, for or on account of the prosecution of the work as aforesaid, written notice, with a statement of the principal facts showing such claim, demand, judgment, lien, cost or fee and the date thereof, shall within thirty days after the same shall have come to the notice of the said obligee be given to the American Indemnity Company, at its office in the city of Galveston, Texas.”

It is clear, we think, Patterson was to have six months, exclusive of such time as he might be entitled to on account of delays contemplated by the provisions of the sections quoted, in which to complete the building.

The trial court found that, due to weather and other conditions, delays occurred in the construction of the building, and also that notice of Patterson’s default in the performance of his contract was given to defendant in error in accordance with the contract; and, although the court did not specifically find the time excluded on account of delays brought the six-month period allowed in which to complete the building to within thirty days of the written notice of abandonment, the findings are susceptible of no other construction, and we must in support of the judgment, but without' passing upon the sufficiency of the evidence, assume that it intended to so find. But, inasmuch as the notice required by the plans and specifications was not given, are plaintiffs in error entitled to have the time occasioned by the delays found by the court excluded in computing the six months’ time?

It is readily seen that the subject-matter of the provision in the plans and specifications is separate and distinct from the subject-matter contained in section 9 of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Indemnity Co. v. Board of Trustees
233 S.W. 878 (Court of Appeals of Texas, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
228 S.W. 105, 1921 Tex. App. LEXIS 660, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-trustees-of-robstown-independent-school-dist-v-american-texcommnapp-1921.