United States Fidelity & Guaranty Co. v. Rice

148 F. 206, 78 C.C.A. 164, 1906 U.S. App. LEXIS 4317
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 4, 1906
StatusPublished
Cited by23 cases

This text of 148 F. 206 (United States Fidelity & Guaranty Co. v. Rice) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Rice, 148 F. 206, 78 C.C.A. 164, 1906 U.S. App. LEXIS 4317 (8th Cir. 1906).

Opinion

ADAM S, Circuit Judge.

On June 15, 1901, Rice, the defendant in error, employed one Davis to furnish material and construct in the cit> of Pueblo a certain brick and frame building, and a contract was entered into between them to that end. The contract, among other things, required the contractor, Davis, to complete the building on or before December 1, 1901, and provided that the owner should pay him for his work and materials used the total sum of $14,465, of which 85 per cent, was payable as the work progressed and the remaining L5 per cent, within 10 da)'S after the building should be completed and accepted by the owner. Simultaneously with the execution of the contract the contractor, as principal, and the United States Fidelity & Guaranty Company, the plaintiff in error, as surety, executed and delivered to Rice, the owner, a bond, in the penal sum of $5,000, in-demnifjdng him against loss or damage which might result from auv breach of the contract by the 'contractor. The obligation of the bond, however, was subject to the following conditions and provisions:

“First. That no liability shall attach to the surety hereunder unless, in the event of any default on the part of the principal in the performance of any of 1he terms, covenants or conditions of the said contract, the obligee shall promptly upon knowledge thereof, and in any event not later than thirty days after the occurrence of such default, deliver to the surety at its office in the city of Baltimore, written notice thereof with a statement of the principal facts showing such default and the date thereof. * * * Second. That in caso of such default on the part of the principal, ti» surety shall have the right, if it so desires, to assume and complete or procure the completion of said contract, and in case of such default, the surety shall be subrogated and entitled to all the rights and properties of the principal arising out of the said contract and otherwise, including all securities and indemnities theretofore received by the obligee, and all deferred payments, retained percentages and credits, due to the principal at tile time of such default, or to become due thereafter by the terms and dates of'the contract.”

The contractor failed to perform bis contract, and suit was brought against the surety oti the bond. One of the defenses interposed by the surety company was that the contractor failed to complete the building on or before December 1, 1901, as required by the contract, and that plaintiff, the owner, failed promptly or within B0 days thereafter to notify it of snch failure or default. The record shows that the facts constituting this defense arc fully proved. In other words, it was shown that the building .was not completed on December 1st as required by the contract, and that no notice of any kind was given by the owner to the surety company of that default as required by the bond. The Circuit Court entertaining the opinion that the time within which notice of default was fo be given was not of the essence of the contract submitted the issues to the jury, which returned a verdict on which judgment was entered for the plaintiff below for $3,462.715. Defenses other than that above referred to were interposed by the surety company, and other assignments of error have been urged upon our attention; but, as we arc unanimously of opinion that the defense above [208]*208referred to was conclusive of the rights of the parties and that the court below erred in not instructing a verdict for the defendant as requested, we find no occasion for considering any other questions.

The parties, by clear and unambiguous language, contracted that no liability should attach to the surety company unless it received notice of any default on the part of the contractor promptly upon knowledge thereof by the owner, and, in any event, not later than 30 days after any such default to the end that it might avail itself, if it desired, of the opportunities furnished by the bond for protecting itself. We think that stipulation of the contract was as binding upon the owner as the obligation to pay was upon the surety company. It was a' most reasonable stipulation. Its purpose was to protect the surety company against the consequences of any default by providing that, on the occasion of any default whatsoever, it might have the opportunity of determining its effect upon its own liability and of acting accordingly. It may well be that if the surety company had been notified promptly, as required by the bond, of the default by the contractor in failing to complete the building by December 1st, it would have assumed the completion of the building, prevented further payments by the owner to the contractor, and at least secured the sum of $2,899.50, which was paid to the contractor after the default, and to that extent have diminished' its own liability. However that may be, the parties contract for no liability on the bond unless such notice should be given. It was not given, and, in our opinion, that fact conclusively exonerates the surety company from liability?-. The time for giving the notice, at any rate the ultimatum of 30 days after any default, was from the nature of the case-■'intended to be and was of the essence of the contract. Whether the notice should be given before the expiration of 30 days might depend upon the owner’s knowledge of an existing default, and whether it was “promptly” given after such knowledge had been acquired might depend on many considerations, and be a debatable question of fact. But obviously the surety company had a pul-póse in binding the owner to give notice of any default — at the latest —within 30 days thereafter.- The imposition of that duty upon the owner tended to insure inspection of the work by the owner, prevent indifference on his part concerning its progress, and to afford the surety company an opportunity to protect itself as provided in its bond. That ultimatum was, in our opinion, reasonable and enforceable. But whether it was reasonable or not is of no consequence. The parties were sui juris, capable of making their own contracts and undertook to do so, and whatever they clearly and distinctly agreed upon is binding upon them. This court recently had occasion in National Surety Company v. Long, 60 C. C. A. 623, 125 Fed. 887, to consider and determine the question just discussed, and the conclusion there reached is reinforced and confirmed by further reflection given to the question in this case. On the authority of that case, as well as on the general principles of the law of contracts, we are unable to sustain the judgment rendered in the Circuit Court.

It is accordingly reversed, with directions to grant a new trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BAYER & MINGOLLA CONSTRUCTION CO. INC. v. Deschenes
205 N.E.2d 208 (Massachusetts Supreme Judicial Court, 1965)
Dairymen's Co-Operative Sales Co. v. Maryland Casualty Co.
11 F. Supp. 423 (W.D. Pennsylvania, 1934)
Union Indemnity Co. v. Lang
71 F.2d 901 (Ninth Circuit, 1934)
Shaw v. New Amsterdam Casualty Co.
164 A. 916 (Supreme Court of Pennsylvania, 1932)
Southern Surety Co. v. MacMillan Co.
58 F.2d 541 (Tenth Circuit, 1932)
Odegard v. General Casualty & Surety Co.
44 F.2d 31 (Eighth Circuit, 1930)
Thompson v. American Surety Co. of New York
42 F.2d 953 (Eighth Circuit, 1930)
Southern Surety Co. v. Slayton
41 F.2d 693 (Sixth Circuit, 1930)
Community Bldg. Co. v. Maryland Casualty Co.
8 F.2d 678 (Ninth Circuit, 1925)
United States Fidelity & Guaranty Co. v. Gray
1925 OK 144 (Supreme Court of Oklahoma, 1925)
Suzuki v. National Surety Co.
290 F. 942 (Second Circuit, 1923)
American Indemnity Co. v. Board of Trustees
200 S.W. 592 (Court of Appeals of Texas, 1918)
Kildall Fish Co. v. Giguere
162 N.W. 671 (Supreme Court of Minnesota, 1917)
Schwab v. Bridge
149 P. 603 (California Court of Appeal, 1915)
Lackland v. Edwin
165 S.W. 314 (Supreme Court of Missouri, 1914)
Beech Grove Improvement Co. v. Title Guaranty & Surety Co.
98 N.E. 373 (Indiana Court of Appeals, 1912)
Lakeside Land Co. v. Empire State Surety Co.
117 N.W. 431 (Supreme Court of Minnesota, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
148 F. 206, 78 C.C.A. 164, 1906 U.S. App. LEXIS 4317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-rice-ca8-1906.