Kildall Fish Co. v. Giguere

162 N.W. 671, 136 Minn. 401, 1917 Minn. LEXIS 581
CourtSupreme Court of Minnesota
DecidedMay 11, 1917
DocketNos. 20,107—(35)
StatusPublished
Cited by3 cases

This text of 162 N.W. 671 (Kildall Fish Co. v. Giguere) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kildall Fish Co. v. Giguere, 162 N.W. 671, 136 Minn. 401, 1917 Minn. LEXIS 581 (Mich. 1917).

Opinion

Bunn, J.

July 24, 1914, plaintiff and defendants P. C. Giguere & Son entered into a written contract, by the terms of which defendants were to erect a warehouse for plaintiff on land owned by it in consideration of the sum of $58,500. To secure the faithful performance of this contract defendants Giguere & Son, as principal, and defendant American Surety Company, as surety, on August 4, 1914, executed and delivered to plaintiff a bond in the penal sum of $29,250. This action is on this bond, the breach alleged being the failure of the contractors to pay certain claims for material and labor, with the result that mechanics’ liens were filed against the property, which plaintiff was compelled to pay. The case was tried by the court without a jury, and a decision rendered in favor of plaintiff and against both principal and surety for the amount which plaintiff was thus compelled to pay with interest. Defendant [403]*403surety company appeals from an order denying its motion for a new trial. 1

It is not disputed that the contractors failed to pay claims for material and labor, that the liens filed therefor were valid and enforceable, or that plaintiff was compelled to and did pay these claims to obtain releases of the liens. It is admitted that the contractors have not refunded to plaintiff any part of the sums so paid, as the contract required, and that the appellant has not indemnified plaintiff for this failure of the contractors to faithfully perform their contract. In brief, a breach of the bond and appellant’s liability therefor is clear, unless one or more of the defenses here urged is sustained. We will state and dispose of the contentions of appellant in their order.

1. The bond contained the provision that “no change shall be made in such plans and specifications which shall increase the amount to be paid the principal more than ten per centum of the penalty of this instrument without the written consent of the surety.” It is claimed that this provision was violated, and that in consequence the surety was entitled to at least a reduction of its liability, if not to an absolute release. The penalty of the instrument was $29,250, and the provision would permit to be paid the principal an increase of $2,925 due to changes in the plans and specifications. It is admitted that there was a change in the original plans which increased the contract price $1,109.60, and it may be conceded that other claims of extras involving some changes in the plans made the total increase in the contract price $2,169.10, which is less than 10 per cent of the penalty of the bond. The surety claims that there were additional changes in the plans and specifications which made a total increase of $5,718.48. Plaintiff contends that these extras involved no changes.in the plans or specifications, added nothing to the contract price, but were material and labor furnished plaintiff by the contractors after the practical completion of the contract under separate contracts, and paid for at an agreed price, being the actual amount paid by the 'contractors for labor, the invoice price of materials, with 10 per cent added for “supervision,” four per cent for “overhead,” and the amount paid by the contractors for liability insurance. The trial court found the facts to be as claimed by plain[404]*404tiff, and that the increase in the contract price occasioned by changes in the plans and specifications was less than 10 per cent of the penalty of the bond. It is not entirely clear how these additional contracts did not increase the total price paid by plaintiff to the contractors, but it is fairly clear that this did not involve changes in the plans and that the surety was not prejudiced. We will content ourselves with saying that we think there was no such violation of the provision in question as would defeat the liability of the surety, and the surety concedes that it is not possible to determine in “money value” the prejudice or damage to the surety, so as to fix the extent of a pro tanto reduction of liability.

2. The contract was to be performed by December 15, 1914. There were delays and the contractors did not finish the work until March 1, 1915. • The bond required plaintiff to give the surety written notice of any default on the part of the principal and the date thereof within 10 days after plaintiff or its representative or the architect should learn of such default. This was not done, no notice being given of the failure to complete the building by the time specified. Appellant claims that the failure to give this notice discharged the surety. It is true that the failure to complete the building at the time specified was technically a default on the part of the contrators, but the trial court found, and the finding is not challenged, that plaintiff has not at any time claimed any default on the part of the contractors because of such failure to complete the work at the time specified. Neither does plaintiff make any claim in this action for any loss to it on that account. The only default for which plaintiff seeks to recover is the failure of the contractor to pay mechanic’s lien claims. Except for the element of prejudice to the surety by failure to give the notice required, the case is controlled by prior decisions of this court. Lakeside Land Co. v. Empire State Surety Co. 105 Minn. 213, 117 N. W. 431; Fitger Brewing Co. v. American Bonding Co. of Baltimore, 115 Minn. 78, 131 N. W. 1067; Pulaski Hall Assn. v. American Surety Co. 123 Minn. 222, 143 N. W. 715; Fitger Brewing Co. v. American Bonding Co. 127 Minn. 330, 149 N. W. 539; Church of Immaculate Conception v. Curtis, 130 Minn. 111, 153 N. W. 259. It is the settled doctrine of these eases that a delay in the completion of the building on time may not have resulted in damages, and [405]*405may in any event be waived by the owner, and if so waived, does not constitute a default or breach of the contract which makes either the contractor or his surety liable, and therefore that the failure to give this-notice does not release -the surety. The doctrine of these cases is severely criticized by appellant in this ease, and it may be admitted that there are respectable authorities contra, and room for argument. But we have declared and applied the rule so often and so recently that we do not feel disposed to consider the question an open one in this state.

There is one element in the present case that did not exist in any of the cases referred to, or at least received no attention from the court. This may be called the element of prejudice to the surety by the failure to apprise it of the contractors’ default. In the Lakeside Land Company case, referring to the case of U. S. Fidelity & Guaranty Co. v. Rice, 148 Fed. 206, 78 C. C. A. 164, the court -called attention to the provision in the bond in that case to the effect that, in the event of default on the part of the contractor, the surety should have the right, if it so desired, to assume or complete the contract, and be subrogated to all the rights and properties of the principal arising out of the contract. Mr. Justice Lewis noted that there was no such condition either in the bond or the contract in the ease then before the court, and distinguished the Bice case because of this provision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Odegard v. General Casualty & Surety Co.
44 F.2d 31 (Eighth Circuit, 1930)
Lumber Co. v. . Johnson
97 S.E. 732 (Supreme Court of North Carolina, 1919)
Guilford Lumber Manufacturing Co. v. Johnson
177 N.C. 44 (Supreme Court of North Carolina, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
162 N.W. 671, 136 Minn. 401, 1917 Minn. LEXIS 581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kildall-fish-co-v-giguere-minn-1917.