Fitger Brewing Co. v. American Bonding Co. of Baltimore

149 N.W. 539, 127 Minn. 330, 1914 Minn. LEXIS 890
Supreme Court of Minnesota·Decided November 20, 1914·No. Nos. 18,748-(243)·Published·Cited by 15 cases

Opinion

Bunn, J.

On a former appeal in tbis case an order sustaining a general demurrer to tbe complaint was reversed. 115 Minn. 78, 131 N. W. 1067. Defendant American Bonding Co. tben answered, and there was a trial by tbe court without a jury. Tbe decision was .in favor of defendant bonding company, and plaintiff appealed from an order refusing a new trial.

Tbe contention of plaintiff is that tbe conclusion of law that plaintiff is not entitled to recover is not justified by tbe findings of fact.

Tbe action as against defendant bonding company is to recover on a contractor’s bond given by tbe company as surety and defendant Hilliard as principal; tbe recovery sought is for money paid by plaintiff to satisfy lien claims after tbe same bad been adjudged valid charges against its property. Tbe decision of tbe court below was [332] that the action was barred because not brought within the time limited by the policy. The conditions of the bond pertinent to this question are:

“Any suits at law or proceedings in equity brought or to be brought against said surety to recover any claim hereunder must be instituted within six (6) months after the first breach of said contract; and in no event shall any action or proceeding be brought against the surety hereunder after the expiration of six months after the date of the completion of the work under said contract.”

The bond provided that “the ‘owner’, in estimating his damages, may include the claims of mechanics and materialmen arising out of the performance of the contract, and paid by him only when the same, by the statutes of the state where the contract is to be performed, are valid liens against said property.”

Hilliard did not perform the terms of the contract, in that he did not pay for the labor and materials used in the construction of the building. April 23, 1909, plaintiff duly notified defendant bonding company of this fact. Hilliard in fact abandoned the work early in April, 1909, and plaintiff completed the building on or prior to May 1; 1909, expending $56.70 in so doing.

Liens against the property were filed by mechanics and material-men. An action was begun to enforce these liens. It does not definitely appear from the findings when the liens were filed, or the action commenced, but defendant bonding company was given notice of the pendency thereof in July, 1909, and requested to defend, which it declined to do. Judgment declaring the claims to be valid, liens against plaintiff’s property was entered February 4, 1910. The bonding company refused to pay, and plaintiff, on February 10, 1910, paid the full amount of the claims adjudged liens against the property.

The present action was commenced April 11, 1910, more than six months after May 1, 1909, the date of the completion of the building, but only two months after the judgment establishing the validity of the lien claims. On the former appeal the complaint did not show when the building was completed, and it was therefore held that the provision of the bond, limiting the right to bring actions thereon to [333] a period ending six months after the date of the completion of the .work under the contract, was not involved. The opinion on the former appeal disposed of the provision requiring suits to be brought within six months after the first breach of the contract. It held that fhe complaint showed no breach that created a liability on the bond until the payment by the owner of valid lien claims. The findings show a breach for which an action on the bond could have been maintained when the contractor abandoned the work, but plaintiff made no claim for such breach. Whether this breach was sufficient to set in motion the first six months limitation, is one of the questions involved here, but it is not this limitation that governed the trial court in its decision.

The decision below was that the action was barred, because not brought within six months after completion of the work under the ■contract. If this is correct, it disposes of the case, and it will be unnecessary to consider the other limitation, or any other question.

Free access — add to your briefcase to read the full text and ask questions with AI

Fitger Brewing Co. v. American Bonding Co. of Baltimore, 149 N.W. 539, 127 Minn. 330, 1914 Minn. LEXIS 890 (Mich. 1914).

149 N.W. 539 (Fitger Brewing Co. v. American Bonding Co. of Baltimore) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rory v. Continental Insurance
703 N.W.2d 23 (Michigan Supreme Court, 2005)
Rowe v. Stufflebeam
89 N.W.2d 875 (Supreme Court of Iowa, 1958)
City of Des Plaines v. B — W Construction Co.
42 N.E.2d 343 (Appellate Court of Illinois, 1942)
Odegard v. General Casualty & Surety Co.
44 F.2d 31 (Eighth Circuit, 1930)
National Tea Co. v. McDonough
227 N.W. 205 (Supreme Court of Minnesota, 1929)
Watters v. Fisher
139 A. 842 (Supreme Court of Pennsylvania, 1927)
Johnson v. Laurence
214 N.W. 24 (Supreme Court of Minnesota, 1927)
Chicago, Rock Island & Pacific Railway Co. v. Theobald Flour Mills Co.
191 N.W. 920 (Supreme Court of Minnesota, 1923)
Gintjee v. Knieling
170 P. 641 (California Court of Appeal, 1917)
Kildall Fish Co. v. Giguere
162 N.W. 671 (Supreme Court of Minnesota, 1917)
Fort Dodge, Des Moines & Southern Railroad v. Burns
177 Iowa 51 (Supreme Court of Iowa, 1916)
Church of Immaculate Conception v. Curtis
153 N.W. 259 (Supreme Court of Minnesota, 1915)