Church of Immaculate Conception v. Curtis

153 N.W. 259, 130 Minn. 111, 1915 Minn. LEXIS 526
CourtSupreme Court of Minnesota
DecidedJune 18, 1915
DocketNos. 19,241, 19,305—(149, 150)
StatusPublished
Cited by9 cases

This text of 153 N.W. 259 (Church of Immaculate Conception v. Curtis) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Church of Immaculate Conception v. Curtis, 153 N.W. 259, 130 Minn. 111, 1915 Minn. LEXIS 526 (Mich. 1915).

Opinion

Taylor, C.

The defendants Brioschi-Minuti Co. a copartnership, entered into a contract with plaintiff on November 8,1912, to plaster and decorate the Pro-Cathedral, then in process of construction in the city of Minneapolis, and to furnish all the material and perform all the labor required therefor, for the sum of $20,868 and gave a bond with the Maryland Casualty Co. as surety to secure the faithful performance of the contract. They agreed to complete the work within nine months from the date of the contract, and, at the end of each 30 day period, were to be paid 90 per cent of the architect’s estimate of the value of the materials furnished and work performed during such period. They made preparations for the work during the winter and began the actual work about April 1, 1913, and proceeded therewith until the latter part of September, 1913, and during this period received payments amounting in the aggregate to the sum of $15,500. They were unable to pay their workmen the wages which became due and payable on September 26, and the workmen quit. The contractors requested plaintiff to advance sufficient funds to meet this payroll. Plaintiff declined to do so, but promised the workmen to see them paid and they returned to work. On October 1, the sum of $1,800 became due the contractors under the estimate of the architect. The contractors presented their payroll,' with a written order directing plaintiff to pay the same to the workmen. Plaintiff expected to receive its funds from an insurance company with which it had arranged for a loan secured by a mortgage on the [114]*114property. On October 2, the insurance company notified plaintiff that a lien for lumber had been filed against the property which must be removed before the money would be paid over. On October 3, pursuant to a written order from the contractors, plaintiff paid this lien in the sum of $893 and also paid the payroll in the sum of $368.67. On October 4, plaintiff again applied to the insurance company for its money and was again refused, for the reason that another lien had been filed for lime and cement. Upon an order from the contractors, plaintiff advanced the money and paid this lien in the sum of $2,507.80, on October 4. As soon as plaintiff could find the managing partner of the contractors, and on October 5 or 6 plaintiff requested him to furnish a list of all lienable claims. This list was furnished on October 8, and on October 9 plaintiff mailed a written notice informing the surety company of the situation. The contractors informed plaintiff that they were unable to pay the claims then due or to proceed with the work under the contract, and after the surety had waived its right to complete the contract, an arrangement was made, whereby the contractors acted as superintendents for plaintiff during the remainder of the work and plaintiff paid for the labor and material. The work was completed under and in accordance with this arrangement. The contractors superintended the work, and audited and approved all claims and expenditures, and gave written orders to plaintiff to pay the same, and thereupon plaintiff paid them. No payments were made by plaintiff except upon such written orders. At the completion of the work, plaintiff had paid, a considerable amount over and above the contract price, and subsequently brought this action against the contractors and their surety to recover the excess so paid. At the conclusion of the trial, the court directed a verdict for plaintiff, and thereafter the contractors and the surety made separate motions for a new trial, and took separate appeals from the orders denying their respective motions.

1. The contract provided that, whenever the architect should certify that the contractors were not furnishing proper and sufficient workmen or materials, or were not prosecuting the work with proper diligence, and such default should continue for three days after [115]*115written notice thereof, plaintiff should have the right to furnish such labor and materials and deduct the cost thereof from the.contract price. The contract further provided that, in case the architect should certify that the default was sufficient ground therefor, plaintiff should have the right to terminate the employment of the contractors, and to take possession of the work and complete it at the expense of the contractors. The contract also provided that the amount to be allowed plaintiff, for expenditures under the above provisions, should be determined by the architect, and that such determination should be conclusive upon the parties.

Defendants contend that plaintiff cannot maintain this action, for the reason that the architect never certified that the contractors were in default, and never determined the amount of the expense incurred by plaintiff in completing the contract. We cannot sustain this contention. If plaintiff had completed the work, or taken part in completing it, against the will of the contractors, and solely by virtue of the power conferred by the contract, the rule invoked by defendants would be applicable, but such is not this case. The contractors themselves informed plaintiff they were unable to go on with the work, and that such was the fact is not questioned. There was never any controversy or dispute between the parties for the architect to settle. The contractors conceded that they were financially unable to proceed further under the contract, but wished to remain upon the work and to superintend it until completed, because they thought that remaining in charge of the work would enable them to overcome, in part, the unfavorable effect which inability to complete the contract would have upon their prospects for securing similar work in the future. Plaintiff consented and, by agreement then made, they remained and supervised and directed the remainder of the work and plaintiff bore the entire expense necessary to complete it. This was in effect an abandonment of the contract'by the contractors. The expenditures made by plaintiff in completing the contract were determined, approved and certified to by the contractors themselves at the time they were made, and the amount necessarily so expended is not only admitted but has never been in dispute. All the questions which the contract provided that the [116]*116architect should determine were determined and decided by the parties themselves, and submitting them to the architect would have been merely an empty form. There was no controversy for him to decide. The contract is a form in general use which has been considered and construed by various courts, and it is well settled that the provisions in question do not apply where the contract has been abandoned, or where there are no unsettled questions for the architect to determine. Smith v. Jewell, 104 Md. 269, 65 Atl. 6; George A. Fuller Co. v. Doyle, 87 Fed. 687; Heidbrink v. Schaffner, 147 Mo. App. 632, 127 S. W. 418; Fraenkel v. Friedmann, 199 N. Y. 351, 92 N. E. 666.

2. The surety company contends that it was not seasonably notified of the default of the contractors. The bond provided:

“This bond is executed upon the following express condition: (1) That said surety shall be notified in writing of any act on the part of said principals or their agents or employees, which shall involve a loss for which said surety is responsible hereunder immediately after the occurrence of such act shall have come to the knowledge of the duly authorized representative of the obligee.”

Although plaintiff sought to communicate with local representatives of the surety company before that date, no written notice was sent to the company until October 9, 1913.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sherman v. Marden
525 N.W.2d 550 (Court of Appeals of Minnesota, 1994)
Klennert v. Dorholt
386 N.W.2d 383 (Court of Appeals of Minnesota, 1986)
Miller v. Hughes
105 N.W.2d 693 (Supreme Court of Minnesota, 1960)
National Tea Co. v. McDonough
227 N.W. 205 (Supreme Court of Minnesota, 1929)
Johnson v. Laurence
214 N.W. 24 (Supreme Court of Minnesota, 1927)
Kildall Fish Co. v. Giguere
162 N.W. 671 (Supreme Court of Minnesota, 1917)
Macleod v. National Surety Co.
158 N.W. 619 (Supreme Court of Minnesota, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
153 N.W. 259, 130 Minn. 111, 1915 Minn. LEXIS 526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/church-of-immaculate-conception-v-curtis-minn-1915.