Fraenkel v. . Friedmann

92 N.E. 666, 199 N.Y. 351, 1910 N.Y. LEXIS 1245
CourtNew York Court of Appeals
DecidedOctober 11, 1910
StatusPublished
Cited by17 cases

This text of 92 N.E. 666 (Fraenkel v. . Friedmann) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fraenkel v. . Friedmann, 92 N.E. 666, 199 N.Y. 351, 1910 N.Y. LEXIS 1245 (N.Y. 1910).

Opinion

Chase, J.

This is an action to foreclose a mechanic’s lien. The plaintiff entered into a contract with the defendant to do certain work, and furnish certain materials, for which he was to be paid $1,050. There was a delay in carrying out the contract, and the time in which it was to be completed was twice extended by the defendant. The defendant claims that it was not then completed. The architect refused from time to time to give the plaintiff a certificate showing that he had partially completed his contract according to the terms thereof, and when the plaintiff asserted that he had fully completed the contract, and asked for a final certificate from the architect, it was refused. The defendant had, however, without the architect’s certificate, given the plaintiff $300 on account. Subsequent to the extended time for the completion of the contract the defendant terminated the plaintiff’s employment. Thereafter a mechanic’s lien was filed, upon which, about a year thereafter, this action was brought and the plaintiff claims that the defendant is indebted to him in the sum of $750, being the amount agreed to be paid pursuant to the contract, less the payment made thereon.

The court before whom the action was tried made findings of fact by which it appears that the plaintiff did not perform the work and furnish the materials required to be performed and furnished under the contract, either wholly or substan *353 tially, and that lie deviated from the terms of the contract in many particulars, some of which are' stated in the findings. Judgment was directed dismissing the plaintiff’s complaint. From the judgment entered thereon an appeal was taken to the Appellate Division, where it was affirmed by a divided court. The plaintiff insists that there is no evidence to sustain the material findings of fact relating to his failure to substantially perform his contract. It is unnecessary to review the evidence relating to such findings or to determine the 'merit of the plaintiff’s claim in view of the conclusion we have reached upon another branch of the case.

In the contract is a provision as follows:

“Art. Y. Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architect, the owner shall be at liberty, after three days’ written notice to the contractor, to provide any such labor or materials, and to deduct the cost" thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work and to enter upon the promises and take possession for the purpose of completing the work included under this contract, of all materials, tools and appliances thereon, and to employ any other person or persons to finish the work and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if- the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor; but if such expense *354 shall exceed such unpaid balance, the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided, either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the architect, whose certificate thereof shall be conclusive upon the parties.”

The right therein given to terminate the employment of the plaintiff is permissive to the owner. 'It is for the benefit of the owner and not for the benefit of the contractor. In case of a failure by the contractor as specified in the section “ the owner shall be at liberty ” as therein provided to take advantage of the provisions of that section of the contract, lie is not compelled to do so. That section of the contract does not take away from the owner his right to terminate and cancel the contract in case of substantial failure of the contractor to perform his contract. Where a building contract provides that the materials shall be furnished and labor performed for a gross sum and by a day fixed in the contract for the full completion thereof, and the contractor fails to perform by the day so fixed the owner may insist on his strict legal right and put an end to the contract. (Deeves & Son v. Manhattan Life Ins. Co., 195 N. Y. 324.) In such a case where the day fixed by the contract for the full completion thereof is extended and there is a failure to perform by the day so extended the owner may as upon the day fixed in the contract put an end to the contract.

In this case the time for the plaintiff to complete his contract was extended, and the trial court has found that plaintiff had not at that time (the day fixed in the contract for the completion thereof) and has not at any time performed the work and furnished the materials required to be performed and furnished under the contract either wholly or substantially.” It was optional, therefore, with the defendant, after the day on which the time for the completion of the contract liad been extended, to put an end to the contract and stand upon his legal, rights or terminate the plaintiff’s employment as provided by the contract and proceed under the contract to *355 complete the work and furnish the materials as provided for therein. The defendant’s exercise of the option appears in a letter written upon the business paper of the architect and addressed to the plaintiff. It was delivered to the plaintiff June 20, and the following is a copy thereof:

“ Dear Sir : I beg to notify you that by reason of your continued neglect to perform your contract and vour failure to supply workmen and materials to complete the same and your performance of the work contrary to the plans and specifications prepared by the architect and your failure to complete the work by the 15th of May, the time fixed in the contract, notwithstanding the numerous notices hereinbefore sent you by me, and the architect having certified to your refusal and failure as sufficient ground for the termination of your employment by me, I hereby advise you that your employment as contractor is terminated and I shall enter upon the said premises and take possession for the purpose of completing the work included in the contract myself, and shall employ such persons and provide such materials therefor as I deem proper and necessary.

“ Very truly yours,

“ JONATHAN FRIEDMANN.”

The letter does not appear to be a cancellation of the contract or an assertion by the defendant that he intends to stand upon his legal rights, but a statement first of his reasons for the termination of the plaintiff’s employment as contractor, followed by a notice of such termination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Soundwall Construction Corp. v. Moncarol Construction Corp.
56 Misc. 2d 892 (New York Supreme Court, 1968)
Plowden & Roberts, Inc. v. Conway
192 So. 2d 528 (District Court of Appeal of Florida, 1966)
Schmidt v. Duggan
15 Misc. 2d 108 (New York Supreme Court, 1958)
Louis Greenberg, Inc. v. Pioneer Syndicate, Inc.
284 A.D. 294 (Appellate Division of the Supreme Court of New York, 1954)
Kempa v. Moell
283 A.D. 681 (Appellate Division of the Supreme Court of New York, 1954)
International Harvester of America, Inc. v. Whelan
247 A.D. 215 (Appellate Division of the Supreme Court of New York, 1936)
Rollin v. Grand Store Fixture Co.
231 A.D. 47 (Appellate Division of the Supreme Court of New York, 1930)
Dempsey v. Mount Sinai Hospital
186 A.D. 334 (Appellate Division of the Supreme Court of New York, 1919)
Federal Heating Co. v. City of Buffalo
99 Misc. 121 (New York Supreme Court, 1917)
American Radiator Co. v. City of New York
177 A.D. 578 (Appellate Division of the Supreme Court of New York, 1917)
Church of Immaculate Conception v. Curtis
153 N.W. 259 (Supreme Court of Minnesota, 1915)
E. F. Keating Co. v. City of New York
84 Misc. 561 (New York Supreme Court, 1914)
Wakeham & Miller v. Roman Catholic Church of St. Paul
150 A.D. 159 (Appellate Division of the Supreme Court of New York, 1912)
General Supply & Construction Co. v. Goelet
149 A.D. 80 (Appellate Division of the Supreme Court of New York, 1912)
Herrmann Grace v. . Hillman
96 N.E. 741 (New York Court of Appeals, 1911)
Steiger v. London
141 A.D. 382 (Appellate Division of the Supreme Court of New York, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
92 N.E. 666, 199 N.Y. 351, 1910 N.Y. LEXIS 1245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fraenkel-v-friedmann-ny-1910.