Dempsey v. Mount Sinai Hospital

186 A.D. 334, 174 N.Y.S. 386, 1919 N.Y. App. Div. LEXIS 5845
Appellate Division of the Supreme Court of the State of New York·Decided February 7, 1919·Published·Cited by 8 cases

Opinions

Laughlin, J.:

On the 2d of June, 1915, the appellant entered into a contract with the Mount Sinai Hospital • for the excavation of the premises described in the complaint in the borough of Manhattan, New York, and the erection thereon of certain buildings, and thereafter the appellant sublet the excavation work to the defendant the F. H. Chapman Contracting Company. The respondent company Dittmar Powder Works, Inc., furnished explosives to the subcontractor for use and which were used in making the excavation,, and the other respondents performed labor for the subcontractor in making the excavation and they all duly filed liens therefor. The uncontroverted evidence shows that at the time these liens were filed, no amount was due or owing by the general contractor to the subcontractor, but the subcontractor had at those times performed work and labor and furnished material amounting in value to more than the amount of the liens filed, for which it had not been paid but no part thereof became due and payable owing to the usual provision of the contract by which only eighty-five per cent of the value of the work performed was due and payable at the contract rates, as the work progressed, and by which the remaining fifteen per cent was not to become due and payable until forty days after the entire completion of the work by the subcontractor. The lien [336] of the respondent Nutley was filed on the 13th of September, 1916, and that of the respondent Torpey on the fourteenth of the same month and of the other respondent on the following day. The subcontractor abandoned the work on the 16th of September, 1916, and was adjudicated a bankrupt on the twenty-third of the same month. At the time the subcontractor abandoned the work, it had been paid the sum of $59,557.03, leaving a balance on the contract price of the work of $4,319.67, which was considerably less than the fifteen per cent which the appellant was authorized to reserve under the contract. Owing to the abandonment of the work by the subcontractor, the appellant was obliged, at the risk of liability to the owner for a breach of its contract, to proceed and finish the work of the subcontractor, which it did at a cost .of considerably more than the balance unpaid on the contract. Of course if there had been a surplus of the amount repaid on the subcontract after completion of the work by the contractor acting under the contract, the liens would have attached thereto but otherwise there was no fund to which they could attach. (Van Clief v. Van Vechten, 130 N. Y. 571; Brainard v. County of Kings, 155 id. 538; Anisansel v. Coggeshall, 83 App. Div. 491; Fraenkel v. Friedmann, 199 N. Y. 351, 356; Herrmann & Grace v. Hillman, 203 id. 435; American Radiator Co. v. City of New York, 223 id. 193; White v. Livingston, 69 App. Div. 361; affd., 174 N. Y. 538; Rodbourn v. S. L. Grape & Wine Co., 67 id. 215; Graf v. Cunningham, 109 id. 369; Murphy v. City of Watertown, 112 App. Div. 670; Upton Co. v. Flynn, 169 id. 79; affd., 218 N. Y. 674; Martin v. Flahive, 112 App. Div. 347.) It is uncontroverted not only that no amount was due or owing to the subcontractor at the time the liens were filed, but that no amount thereafter became due or owing from the appellant to the subcontractor under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Dempsey v. Mount Sinai Hospital, 186 A.D. 334, 174 N.Y.S. 386, 1919 N.Y. App. Div. LEXIS 5845 (N.Y. Ct. App. 1919).

186 A.D. 334 (Dempsey v. Mount Sinai Hospital) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

East Hills Metro, Inc. v. J.M. Dennis Construction Corp.
183 Misc. 2d 439 (New York Supreme Court, 2000)
Blandford Land Clearing Corp. v. National Union Fire Insurance
260 A.D.2d 86 (Appellate Division of the Supreme Court of New York, 1999)
Ace Contracting Co. v. Garfield & Arma Associates
148 Misc. 2d 475 (New York Supreme Court, 1990)
Philan Department of the Borden Co. v. Foster-Lipkins Corp.
39 A.D.2d 633 (Appellate Division of the Supreme Court of New York, 1972)
Tibbetts Contracting Corp. v. O & E Contracting Co.
206 N.E.2d 340 (New York Court of Appeals, 1965)
E. F. Curialle & Co. v. Kenray Realty Corp.
25 Misc. 2d 745 (New York Supreme Court, 1960)
Lorber v. Eskof Real Estate, Inc.
21 Misc. 2d 308 (New York Supreme Court, 1959)
North American Iron Works, Inc. v. G. Dekimpe, Inc.
232 A.D. 579 (Appellate Division of the Supreme Court of New York, 1931)