Dempsey v. Mount Sinai Hospital

186 A.D. 334, 174 N.Y.S. 386, 1919 N.Y. App. Div. LEXIS 5845
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 7, 1919
StatusPublished
Cited by8 cases

This text of 186 A.D. 334 (Dempsey v. Mount Sinai Hospital) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dempsey v. Mount Sinai Hospital, 186 A.D. 334, 174 N.Y.S. 386, 1919 N.Y. App. Div. LEXIS 5845 (N.Y. Ct. App. 1919).

Opinions

Laughlin, J.:

On the 2d of June, 1915, the appellant entered into a contract with the Mount Sinai Hospital • for the excavation of the premises described in the complaint in the borough of Manhattan, New York, and the erection thereon of certain buildings, and thereafter the appellant sublet the excavation work to the defendant the F. H. Chapman Contracting Company. The respondent company Dittmar Powder Works, Inc., furnished explosives to the subcontractor for use and which were used in making the excavation,, and the other respondents performed labor for the subcontractor in making the excavation and they all duly filed liens therefor. The uncontroverted evidence shows that at the time these liens were filed, no amount was due or owing by the general contractor to the subcontractor, but the subcontractor had at those times performed work and labor and furnished material amounting in value to more than the amount of the liens filed, for which it had not been paid but no part thereof became due and payable owing to the usual provision of the contract by which only eighty-five per cent of the value of the work performed was due and payable at the contract rates, as the work progressed, and by which the remaining fifteen per cent was not to become due and payable until forty days after the entire completion of the work by the subcontractor. The lien [336]*336of the respondent Nutley was filed on the 13th of September, 1916, and that of the respondent Torpey on the fourteenth of the same month and of the other respondent on the following day. The subcontractor abandoned the work on the 16th of September, 1916, and was adjudicated a bankrupt on the twenty-third of the same month. At the time the subcontractor abandoned the work, it had been paid the sum of $59,557.03, leaving a balance on the contract price of the work of $4,319.67, which was considerably less than the fifteen per cent which the appellant was authorized to reserve under the contract. Owing to the abandonment of the work by the subcontractor, the appellant was obliged, at the risk of liability to the owner for a breach of its contract, to proceed and finish the work of the subcontractor, which it did at a cost .of considerably more than the balance unpaid on the contract. Of course if there had been a surplus of the amount repaid on the subcontract after completion of the work by the contractor acting under the contract, the liens would have attached thereto but otherwise there was no fund to which they could attach. (Van Clief v. Van Vechten, 130 N. Y. 571; Brainard v. County of Kings, 155 id. 538; Anisansel v. Coggeshall, 83 App. Div. 491; Fraenkel v. Friedmann, 199 N. Y. 351, 356; Herrmann & Grace v. Hillman, 203 id. 435; American Radiator Co. v. City of New York, 223 id. 193; White v. Livingston, 69 App. Div. 361; affd., 174 N. Y. 538; Rodbourn v. S. L. Grape & Wine Co., 67 id. 215; Graf v. Cunningham, 109 id. 369; Murphy v. City of Watertown, 112 App. Div. 670; Upton Co. v. Flynn, 169 id. 79; affd., 218 N. Y. 674; Martin v. Flahive, 112 App. Div. 347.) It is uncontroverted not only that no amount was due or owing to the subcontractor at the time the liens were filed, but that no amount thereafter became due or owing from the appellant to the subcontractor under the contract.

The appellant’s contention is that in these circumstances there was no fund to which the liens of the respondents ever attached, and the respondents contend that the amounts of their respective hens had been earned by the subcontractor at the time the hens were filed, and that upon the work being performed by the appellant the amounts earned at the time the hens were filed became due and payable from the owner to the general contractor, and that their hens attached thereto. [337]*337They concede that the liability of the owners to lienors is limited to the contract price of the work and it is so expressly provided in section 4 of the Lien Law (Consol. Laws, chap. 33 [Laws of 1909, chap. 38], as amd. by Laws of 1916, chap. 507). But they claim that by virtue of a sentence inserted in section 4 of the Lien Law, as revised by chapter 418 of the Laws of 1897 (Gen. Laws, chap. 49), the Legislature intended to give to a person performing labor for or furnishing materials to a contractor or subcontractor for an improvement, other than a public improvement, a lien for the amount earned and unpaid at the time of filing the notice of lien and for any sum subsequently earned under the contract without regard to whether or not it was due or ever became due or payable to the contractor or subcontractor for whom the labor was performed or to whom the materials were furnished. That sentence is as follows: “ If labor is performed for, or materials furnished to, a contractor or sub-contractor for an improvement, the lien shall not be for a sum greater than thé sum earned and unpaid on the contract at the time of filing the notice of lien, and any sum subsequently earned thereon.” That provision, first enacted some twenty-two years ago, has been continued in the Lien Law ever since. The decision from which the appeal is taken is the first so construing these provisions so far as the reports show. It is conceded that if this were a public improvement the lienors would have no claim and it has been so held in cases arising under the Lien Law since those provisions were inserted (Wright v. Schoharie Valley R. Co., No. 11,116 App. Div. 542; affd., 191 N. Y. 549; Herrmann & Grace v. Hillman, 203 id. 435; Lawrence v. Dawson, 34 App. Div. 211; 50 id. 570; affd., 167 N. Y. 609. See, also, American Radiator Co. v. City of New York, 223 id. 193); but the phraseology of section 5 of the Lien Law, which relates to public improvements, differs from the phraseology quoted from section 4 in that it is declared that the lienors shall have a lien to the extent of the amount due or to become due ” on the contract. (See, also, § 5, added by Laws of 1911, chap. 873, as amd. by Laws of 1916, chap. 507.) If the sentence herein quoted had been a revision of statutory provisions relating to the subject and the phraseology had been changed [338]*338from due to earned, there would be force in the contention made by counsel for the respondents; but inasmuch as the sentence was a new enactment it does not necessarily follow that by the adoption of this phraseology specifying the amount earned and unpaid, instead of the amount due and unpaid, there was any legislative intent to differentiate between the rights of lienors under private contracts and such rights under contracts for public improvements. The lien Law of 1897 was drafted and presented to the Legislature by the Commissioners of Statutory Revision, and the provisions thereof, so far as here material, were enacted as so recommended without change. (Assembly Documents, 1897, vol. 22, p. 379 et seq.) The report of the Commissioners and their note to section 4 show that there was no intent to change the then existing law on the point now under consideration, and, therefore, no intent to change the former law is to be imputed to the Legislature in thus enacting the lien Law as reported by the revisers and as the law had been well settled prior to that time to the effect that contractors had the same right as owners with respect to the limitation of their liability for work performed under subcontracts

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Hills Metro, Inc. v. J.M. Dennis Construction Corp.
183 Misc. 2d 439 (New York Supreme Court, 2000)
Blandford Land Clearing Corp. v. National Union Fire Insurance
260 A.D.2d 86 (Appellate Division of the Supreme Court of New York, 1999)
Ace Contracting Co. v. Garfield & Arma Associates
148 Misc. 2d 475 (New York Supreme Court, 1990)
Philan Department of the Borden Co. v. Foster-Lipkins Corp.
39 A.D.2d 633 (Appellate Division of the Supreme Court of New York, 1972)
Tibbetts Contracting Corp. v. O & E Contracting Co.
206 N.E.2d 340 (New York Court of Appeals, 1965)
E. F. Curialle & Co. v. Kenray Realty Corp.
25 Misc. 2d 745 (New York Supreme Court, 1960)
Lorber v. Eskof Real Estate, Inc.
21 Misc. 2d 308 (New York Supreme Court, 1959)
North American Iron Works, Inc. v. G. Dekimpe, Inc.
232 A.D. 579 (Appellate Division of the Supreme Court of New York, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
186 A.D. 334, 174 N.Y.S. 386, 1919 N.Y. App. Div. LEXIS 5845, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dempsey-v-mount-sinai-hospital-nyappdiv-1919.