Tibbetts Contracting Corp. v. O & E Contracting Co.

206 N.E.2d 340, 15 N.Y.2d 324, 258 N.Y.S.2d 400, 1965 N.Y. LEXIS 1502
CourtNew York Court of Appeals
DecidedMarch 18, 1965
StatusPublished
Cited by29 cases

This text of 206 N.E.2d 340 (Tibbetts Contracting Corp. v. O & E Contracting Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tibbetts Contracting Corp. v. O & E Contracting Co., 206 N.E.2d 340, 15 N.Y.2d 324, 258 N.Y.S.2d 400, 1965 N.Y. LEXIS 1502 (N.Y. 1965).

Opinion

Van Voorhis, J.

Under a contract with defendant Vioe, defendant O & E agreed to do excavation, grading and drainage work on property which Vioe was developing for lease to S. Klein Department Stores, Inc. Plaintiff subcontracted to lay certain drainage pipes. In March, 1959 O & E removed its" equipment from the job site and on the basis of that and other alleged breaches of the contract Vioe declared O & E in default. Plaintiff completed the drainage work, to the knowledge of Vioe, after Vioe had declared the principal contract broken by O & E. O & E did not pay plaintiff and plaintiff filed a notice of mechanic’s lien for the amount owed to it by O & E. This action was commenced to foreclose the mechanic’s lien. Another action by Vioe against O & E for breach of contract commenced in New York C'ounty was consolidated with this action for trial. Defendant O & E alleged counter *331 claims against Vioe for amounts alleged to be due to it for work done under the contract. The counterclaim's, comprising the substance of Vice’s complaint in the consolidated action, were treated as cross complaints in the action to foreclose the mechanic’s lien.

The trial court found that O & E did not abandon or breach the contract, that O & E was entitled to recover from Vioe the balance due for work, labor and service's and materials furnished, plus loss of profits because of breach of contract by Vioe, that plaintiff was entitled to judgment against O & E for the amount due it and to establishment of its mechanic’s lien on the land. *

The Appellate Division found that Vioe was justified in terminating the contract with O & E for O & E’s refusal to comply with demands to resume performance of the contract, O & E’s removal of its equipment from the job site and its refusal to furnish a performance and payment bond; that a determination that Vioe owed O & E nothing at the time plaintiff filed its notice of lien would have been justified, and, therefore, no fund was in existence to which the lien attached and the lien was unenforeible at least through the subcontract with O & E; that, in order to prevent unjust enrichment of Vioe, plaintiff was entitled to relief (on a cause of action which was added pursuant to permission by the Appellate Division) in the form of a money judgment against Vioe on quasi-contract or constructive trust (implied in law) for work done and materials supplied by plaintiff, Vioe having permitted plaintiff to continue to perform under its subcontract and having fostered and promoted such performance by plaintiff.

Defendant Vioe argues, inter alia, in support of its appeal that the court below erred in holding that plaintiff is entitled to any judgment against Vioe; that it was error to grant the plaintiff’s motion to amend its complaint to allege a new cause of action against Vioe, because it was deprived of an opportunity to meet the issues raised by the new cause of *332 action, and because plaintiff did not appeal to the Appellate Division on account of the trial court’s adverse ruling in denying its-motion to amend by adding the cause of action on which recovery was allowed.

Defendant O & E argues on its appeal that the Appellate Division erred, both in law and fact, in holding that ‘ ‘ a damage award in favor of Vioe against O & E would have been justified ’ ’; that Vioe’s notice of contract termination was ineffective, unwarranted and improper under the provisions of the contract, and, in any event, was cancelled or waived by Vioe’s later conduct; that, at the time of the filing of plaintiff’s mechanic’s lien, a fund existed sufficient to pay the lien which was subject to -appropriate action to foreclose.

The plaintiff, also appealing, argues, inter alia, that O & E did not abandon the contract; that the permitting and acceptance of performance of plaintiff’s subcontract constituted a waiver in law of the termination of the contract, thus making Vioe liable -under its contract with O & E and to plaintiff.

Since the Appellate Division modified on the law and the facts, it is incumbent on us to decide which version of the facts more nearly accords with the evidence. Our conclusion is that the trial court’s findings are nearer to what is disclosed by the record than those of the Appellate Division, i.e., that Vioe rather than O & E broke the principal contract. We conclude that Vioe owes money to O & E, out of which Tibbetts (plaintiff) is entitled to be paid. In that posture of the case, it becomes immaterial whether Tibbetts could recover against Vioe on .some quasi-contract theory of unjust enrichment.

The contract between Vioe and O & E was entire; it provided a flat price of'$127,750 for the performance of “ all excavating, filling, drainage, grading and related work required by the Drawings and/or as described in this Specification, generally as follows” (cf. contract Exhibit A, p. 582) after which the work is more particularly described. Unit prices applied only to additions and/or deductions ”, resulting- from modification of the contract as the work progressed. The subcontract between O & E and Tibbetts, as has been stated, was for drainage. O & E happened to deal with Tibbetts in this manner: it came about that in preparing this site for an S. Klein Department Stores, Inc., shopping development in Yonkers, *333 Vioe had made a contract with Tibbetts January 30, 1959 for the laying of an 84-inch storm water drain which was not included in the drawings and specifications covering the drains to be installed by O & E under its contract with Yioe. O & E was, however, required under its contract to backfill and grade after the drainpipes had been installed under this contract between Yioe and Tibbetts. The drains were laid under that contract by March 18, 1959, although the manholes were not installed until a later date and the contract was not finally completed until June 14 or 15, 1959. It may be assumed that, weather permitting, these trenches could have been refilled before the manholes were installed, although there may be doubt that the grading could have been finished before then. While the work was in progress under the contract mentioned between Yioe and Tibbetts for the installation of the 84-inch drain, O & E sublet to Tibbetts, which was already on the job site, the completion of the drainage work covered by the contract between O & E and Yioe. Oral arrangements were made to that effect on March 3, 1959 for a stated price of $28,550 which, plus extras, amounted without dispute to the principal sum of $30,217. This work to be performed by O & E was commenced by Tibbetts under the subcontract on March 16 and completed June 15, 1959. No party to the litigation questions that the work by Tibbetts was satisfactorily completed. Tibbetts was paid by Yioe $91,500 August 27, 1959 for laying the 84-inch drain under its contract with Yioe. It has never been paid for the similar work subcontracted to it by O & E. Instead of billing Yioe it billed O & E under its subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosenblum v. Rosenblum
2018 NY Slip Op 4846 (Appellate Division of the Supreme Court of New York, 2018)
Obstfeld v. Thermo Niton Analyzers, LLC
112 A.D.3d 895 (Appellate Division of the Supreme Court of New York, 2013)
In Re Hirsch Elec. Co., Inc.
461 B.R. 167 (E.D. New York, 2011)
Abra Construction Corp. v. 112 Duane Associates
59 A.D.3d 263 (Appellate Division of the Supreme Court of New York, 2009)
Alden State Bank v. Sunrise Builders, Inc.
48 A.D.3d 1162 (Appellate Division of the Supreme Court of New York, 2008)
Automobile Coverage, Inc. v. American International Group, Inc.
42 A.D.3d 405 (Appellate Division of the Supreme Court of New York, 2007)
Great Am. Constr. Corp. v. Nobre, Inc.
2004 NY Slip Op 50564(U) (New York Supreme Court, Kings County, 2004)
Kool-Temp Heating & Cooling, Inc. v. Ruzika
6 A.D.3d 869 (Appellate Division of the Supreme Court of New York, 2004)
Timothy Coffey Nursery/Landscape, Inc. v. Gatz
304 A.D.2d 652 (Appellate Division of the Supreme Court of New York, 2003)
Sky-Lift Corp. v. Flour City Architectural Metals, Inc.
298 A.D.2d 214 (Appellate Division of the Supreme Court of New York, 2002)
Massachusetts Mutual Life Insurance v. Thorpe
260 A.D.2d 706 (Appellate Division of the Supreme Court of New York, 1999)
Spyder Enterprises, Inc. v. Ward
872 F. Supp. 8 (E.D. New York, 1995)
Metropolitan Life Insurance v. Noble Lowndes International, Inc.
643 N.E.2d 504 (New York Court of Appeals, 1994)
J.J. Flannery, Inc. v. Kerby Saunders, Inc.
155 A.D.2d 263 (Appellate Division of the Supreme Court of New York, 1989)
Lehmann v. State
123 A.D.2d 604 (Appellate Division of the Supreme Court of New York, 1986)
Young v. Whitney
111 A.D.2d 1013 (Appellate Division of the Supreme Court of New York, 1985)
Matter of Nicfur-Cruz Realty Corp.
50 B.R. 162 (S.D. New York, 1985)
Goodstein Construction Corp. v. City of New York
111 A.D.2d 49 (Appellate Division of the Supreme Court of New York, 1985)
Chicago Transit Authority v. Yellow Cab Co.
442 N.E.2d 546 (Appellate Court of Illinois, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
206 N.E.2d 340, 15 N.Y.2d 324, 258 N.Y.S.2d 400, 1965 N.Y. LEXIS 1502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tibbetts-contracting-corp-v-o-e-contracting-co-ny-1965.