Wilson & English Construction Co. v. New York Central Railroad

240 A.D. 479, 269 N.Y.S. 874, 1934 N.Y. App. Div. LEXIS 10679
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 9, 1934
StatusPublished
Cited by22 cases

This text of 240 A.D. 479 (Wilson & English Construction Co. v. New York Central Railroad) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson & English Construction Co. v. New York Central Railroad, 240 A.D. 479, 269 N.Y.S. 874, 1934 N.Y. App. Div. LEXIS 10679 (N.Y. Ct. App. 1934).

Opinion

Scudder, J.

This action is to recover $30,639.27 as damages for alleged acts of omission of the defendant which plaintiff claims prevented it from completing on time certain construction work covered by a contract between them. Plaintiff alleges that what could and should have been finished while the season was open, and on or before November 7, 1929, was thrown into freezing weather, necessitating an additional cost to the plaintiff of $30,639.27 in excess of its normal cost.

The contract provides for the construction by plaintiff of a spur of defendant’s railroad, the work to be done at unit prices, and to be finished within 125 working days from June 12, 1929, the contract date.

It is alleged that the defendant agreed that it had the right of way; would supply all track material (by a later modification of the contract the ties were excepted); and would furnish plans for a bridge which plaintiff was to build; that defendant did not have the right of way, and did not obtain it until October 5, 1929; did not furnish the track material in accordance with the schedule agreed upon, or within a reasonable time; did not furnish the plans for the erection of the bridge until September 1, 1929; and that, due to defendant’s failures in these respects, plaintiff could not complete the construction by November 7, 1929, and the work was thrown into wintry weather, with the ground frozen and covered with snow.

Plaintiff’s time to finish the work was extended to December 31, 1929.

The answer denies the delays and sets up, as separate defenses, [481]*481that the plaintiff waived any claim by not protesting while the work was in progress, and, itself, was responsible for the delays.

The answer made no point of the provision appearing in the printed part of the contract upon which, on the trial, the motion was made to dismiss the complaint and upon which it was granted. That provision reads as follows: " It is expressly understood and agreed that the Contractor shall not be entitled to claim or receive from the Company any sum whatever in excess of the contract price for the work provided for herein, by reason or on account of, any delay caused in such work by the Company.”

The contract is a printed form used by the defendant for construction work, with typewritten pages added. It contains a fifty dollars per day liquidated damage clause for failure to complete. It was executed early in July, but by letter of June 12, 1929, plaintiff was notified that the contract had been awarded to it, and started work about June 17, 1929.

The contract provided that detailed plans for the substructure and superstructure of the bridge were to be furnished later.

After repeated demands for the bridge plans, they were received August eighth; and about August fifteenth the plaintiff was notified that as to the superstructure they had been approved. Plaintiff immediately ordered the structural steel in accordance with the plans. ,

It appears that the reasonable time for fabricating the steel after placing such an order is two months. It was received on the job October 10, 1929, and the bridge was far enough advanced to permit the passage of trains by October 17, 1929.

This bridge was located about two miles from the point where the spur track in question makes connection with the railroad. The evidence is to the effect that the contractor had planned to erect the bridge and use it in carrying materials needed in the work south of‘that point; and by reason of the delay in the receipt of the plans it had to truck a good part of the materials, which otherwise could have been carried by rail over the bridge.

The contract contains a provision that the contractor shall prepare a schedule stating when track material will be required, and shall give the engineer at least thirty days’ ádvance notice of the time when any shipment may be desired.

The evidence is that plaintiff gave the defendant its schedule for track material on July fifteenth, that the material was not furnished in accordance with the schedule, though repeatedly demanded, and that the last of the track material was received the middle of December, 1929.

There was evidence to the effect that the plaintiff was delayed [482]*482because of defendant’s failure to secure a certain right of way, which was not obtained by defendant until October 5, 1929.

Plaintiff continued on the job, working in frozen ground under deep snow, with the thermometer reaching at one time forty degrees below zero, all of which increased the cost of the work.

The work was finished December 31, 1929. When the engineers took up the question of the added cost to the plaintiff by reason of the delays, it appears that the assistant engineer of the defendant agreed that there was merit in plaintiff’s claim.

On April 9, and again on November 17, 1930, plaintiff wrote to the defendant, making the claims upon which this action is founded. The defendant then agreed to arbitrate the claim, but later refused to do so.

So far as the record shows, at no time until the close of the plaintiff’s case was the point raised with respect to the third paragraph in article 26 of the contract, which I have quoted, and upon which, at the close of plaintiff’s case, the complaint was dismissed.

Two questions are raised on this appeal:

1. Does the quoted clause in the contract preclude the plaintiff from recovering the damage suffered by reason of the delays caused by the defendant in failing to perform its side of the contract?
2. Did the defendant waive this clause in the contract by taking up for consideration the claims presented, acknowledging that there was merit to them, asking for revised bills of the claims and agreeing to arbitrate the same, without raising this question?

The defendant undertook to provide the right of way; to furnish all track material, excepting ties, in accordance with a schedule; to furnish plans for the bridge which the plaintiff was to erect.

It is in proof that the defendant did not have the right of way at the time the contract was made (a fact not disclosed to plaintiff); defendant acquired it some months thereafter; defendant did not furnish the track material in accordance with the 'schedule, and the delays from these several causes prevented the plaintiff from finishing the work by November seventh.

It does not seem to me that the parties contemplated by their agreement to throw the loss on plaintiff by reason of the above-quoted clause of the contract.

The agreement is on a printed form, which I think we can assume is used by the defendant for its construction contracts. It is supplemented by typewritten provisions applicable to the particular work to be done.

To ascertain the intention of parties entering into a contract, we have well-recognized elementary rules of construction to guide us. The following seem applicable here:

[483]*483Where contracts are partially written and partially printed, and there is a conflict between the two parts, the written portion prevails.
In case of conflict or ambiguity in the agreement, it is to be construed most strongly against the party who drew it, and any promise is to be construed in the way that the promisee had good reason to understand it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eldor Contracting Corp. v. County of Nassau
6 A.D.3d 654 (Appellate Division of the Supreme Court of New York, 2004)
Forward Industries, Inc. v. Rolm of New York Corp.
123 A.D.2d 374 (Appellate Division of the Supreme Court of New York, 1986)
Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Kalisch-Jarcho, Inc. v. City of New York
448 N.E.2d 413 (New York Court of Appeals, 1983)
Deverho Construction Co. v. State
94 Misc. 2d 1053 (New York State Court of Claims, 1978)
Vanderlinde Electric Corp. v. City of Rochester
54 A.D.2d 155 (Appellate Division of the Supreme Court of New York, 1976)
Franklin Contracting Co. v. State
338 A.2d 875 (New Jersey Superior Court App Division, 1975)
Peckham Road Co. v. State
32 A.D.2d 139 (Appellate Division of the Supreme Court of New York, 1969)
Norman Co. v. County of Nassau
27 A.D.2d 936 (Appellate Division of the Supreme Court of New York, 1967)
Rein v. Wagner
49 Misc. 2d 683 (New York Supreme Court, 1965)
Tibbetts Contracting Corp. v. O & E Contracting Co.
206 N.E.2d 340 (New York Court of Appeals, 1965)
Ippolito-Lutz, Inc. v. Cohoes Housing Authority
22 A.D.2d 990 (Appellate Division of the Supreme Court of New York, 1964)
Hawley v. Orange County Flood Control District
211 Cal. App. 2d 708 (California Court of Appeal, 1963)
Nix, Inc. v. City of Columbus
171 N.E.2d 197 (Ohio Court of Appeals, 1959)
Polley v. Plainsun Corp.
7 Misc. 2d 605 (New York Supreme Court, 1957)
Barash v. State
2 Misc. 2d 680 (New York State Court of Claims, 1956)
Psaty & Fuhrman, Inc. v. Housing Authority
68 A.2d 32 (Supreme Court of Rhode Island, 1949)
Sanka Classics, Inc. v. Atlantic Terra Cotta Co.
274 A.D. 103 (Appellate Division of the Supreme Court of New York, 1948)
Shore Bridge Corp. v. State
186 Misc. 1005 (New York State Court of Claims, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
240 A.D. 479, 269 N.Y.S. 874, 1934 N.Y. App. Div. LEXIS 10679, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-english-construction-co-v-new-york-central-railroad-nyappdiv-1934.