Deverho Construction Co. v. State

94 Misc. 2d 1053, 407 N.Y.S.2d 399, 1978 N.Y. Misc. LEXIS 2346
CourtNew York Court of Claims
DecidedJune 8, 1978
DocketClaim No. 59497
StatusPublished
Cited by7 cases

This text of 94 Misc. 2d 1053 (Deverho Construction Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Deverho Construction Co. v. State, 94 Misc. 2d 1053, 407 N.Y.S.2d 399, 1978 N.Y. Misc. LEXIS 2346 (N.Y. Super. Ct. 1978).

Opinion

OPINION OF THE COURT

Gerard M. Weisberg, J.

This claim seeks payment for work performed by Deverho Construction Company, Inc. (Deverho), under a contract with the State of New York (State), which provided for the reconstruction of a portion of the Newburgh-Campbell Hall State Highway. The contract was let on April 25, 1974, and was awarded to claimant on April 30, 1974. Pursuant to section 112 of the State Finance Law, the Comptroller’s approval was obtained on June 14, 1974.

Claimant’s first cause of action concerns item 619.01 of the contract entitled Basic Maintenance and Protection of Traffic, and relates to two distinct time periods, one at the beginning and one at the end of the contract’s duration.1 Basic Maintenance and Protection of Traffic is defined by the Standard Specifications of 1973 under paragraph 619-102 as follows: " '[t]raffic shall be maintained over a reasonably smooth traveled way which shall be so marked by signs, delineators, guiding devices and other methods that a person who has no knowledge of conditions may safely and with a minimum of discomfort and inconvenience ride, drive or walk, day or [1056]*1056night, over all or any portion of the highway under construction where traffic is to be maintained.’ ”

" '[M]aintain the drainage facilities and other highway elements, old or new, including detours’ ”. Also pertaining to this item, the following appears on page 26 of the contract documents under "Maintenance of Traffic”:

"The Contractor shall be required to maintain and protect two-way traffic and protect the public from damage to person and property, within the limits of and for the duration of the contract in accordance with all specifications for Basic Maintenance and Protection of Traffic, Item 619.01.”

"In order to maintain effective traffic control, the Contractor shall be responsible for continuous maintenance to make sure all signs, cones, flashing lights, etc. are in place and in good condition and that the traveled way is in a safe and reasonable condition. The Engineer will be the sole judge of the effectiveness of the Contractor’s efforts towards protection of traffic and personnel.”

"The Contractor shall maintain and protect traffic by so conducting his work operations that the public is subjected to a minimum of delay and hazard.”

The nature of this item was characterized by Nathaniel Gartman, a part owner and one of the managers of Deverho on this contract, as "payment for exposure”, representing the cost of procuring insurance for the protection of the public and to offset any potential liability, as well as for providing flagmen and other services as the need arose. Payment for Basic Maintenance and Protection of Traffic was on a per calendar day basis at the rate of $130 per day for the duration of the contract.

The dispute over this item concerns two periods — one from May 21 to June 19 and the other from October 16 to December 20 (1974). In regard to the former, claimant contends that payment is owed for Basic Maintenance and Protection of Traffic starting on May 21, by virtue of the contractor’s having performed work at the site on that date, pursuant to a request by the State. The facts are that on May 14 a preconstruction meeting was held at which a plan for performing the work was discussed. Subsequently, Mr. Gartman was instructed to provide certain assistance to the State’s surveyors. Deverho was informed by Mr. Lawrence Porvaznik, the State’s engineer-in-charge, that it was obligated to do so under the [1057]*1057contract.2 These instructions were given at a time when the contract had not yet been approved by the Comptroller. On May 21, the State surveyors commenced their work and claimant supplied the necessary assistance. Claimant had men on the job on May 21, 22, 23, 24 and 28 and June 12, 13 and 14, whose duties consisted of clearing brush, marking and removing trees and laying out stakes. Nothing of a positive nature was done by way of Basic Maintenance and Protection of Traffic on those dates, since the work was not near the highway. During this period, claimant was aware that if the Comptroller’s approval were not obtained, no payment for work performed would be forthcoming. Subsequently, however, on June 17, 1974, Deverho was notified that the contract had been approved by the Comptroller, and on June 19, it resumed work at the site.

The State contends that the contract officially began on June 19 and that claimant is not entitled to any payment for Basic Maintenance and Protection of Traffic prior to that date, even though some work was admittedly performed prior thereto. The basis for its contention is subdivision 2 of section 112 of the State Finance Law, which provides in relevant part as follows: “Before any contract made for or by any state department, board, officer, commission, or institution, shall be executed or become effective, when such contract exceeds one thousand dollars in amount * * * it shall first be approved by the comptroller and filed in his office.”

Claimant’s position is that the contract commenced when it first rendered performance (May 21). Claimant relies on the contract’s definition of “duration”, as set forth in the Standard Specifications of 1973 (p 394, par 619-1.10) as follows: "the duration of the Contract for the purpose of this work, shall be from the date any work is started on the Contract, including any preparatory work or moving in equipment, signs, offices, shops and the like, until the date the Contract is officially accepted.” (Emphasis added.)

The State maintains that the word "contract” in the definition of “duration” presupposes the existence of a valid, legally binding contract which, under subdivision 2 of section 112 of [1058]*1058the State Finance Law, did not occur until June 14. Notwithstanding this position, the State did in fact pay claimant for a number of items of work which were also performed prior to June 14. The State seeks to. distinguish these items from Basic Maintenance and Protection of Traffic on the theory that they were bid on a "lump sum” basis as opposed to per calendar day. Of these lump sum items, the State says in its brief at page 7: "They are paid for when the contract becomes effective, regardless of when performed.”3

The State’s argument raises two issues: (1) whether a contractor has a legal right to be paid for work performed after a contract has been awarded, but prior to its approval by the Comptroller, and (2) whether in this case, the word "contract” in the definition of "duration” presupposes the prior approval of the Comptroller.

Within the scope of its application, subdivision 2 of section 112 of the State Finance Law constitutes a complete bar to any payment for work performed on the State’s behalf pursuant to an incipient contract which is never approved by the Comptroller. (Blatt Bowling & Billiard Corp. v State of New York, 14 AD2d 144; Starling Realty Corp. v State of New York, 286 NY 272; Belmar Contr. Co. v State of New York, 233 NY 189.) In the present case, however, the contract was approved by the Comptroller; the question is whether the statute’s application should be extended to bar payment for work performed on the contract prior to the time when approval takes place. In interpreting this provision of law, it is the court’s duty to "give it a reasonable and sensible meaning in the light of the evil at which it was directed.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of New York v. State
665 N.E.2d 181 (New York Court of Appeals, 1996)
Professional Charter Services, Inc. v. State
166 Misc. 2d 306 (New York State Court of Claims, 1995)
230 Park Avenue Associates v. State
165 Misc. 2d 920 (New York State Court of Claims, 1995)
Bonelli v. Volkswagen of America, Inc
421 N.W.2d 213 (Michigan Court of Appeals, 1988)
Schenker v. State
126 Misc. 2d 1038 (New York State Court of Claims, 1984)
Kuczka v. Clark
110 Misc. 2d 273 (New York Supreme Court, 1981)
Edward C. Flaherty Corp. v. State
102 Misc. 2d 438 (New York State Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
94 Misc. 2d 1053, 407 N.Y.S.2d 399, 1978 N.Y. Misc. LEXIS 2346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/deverho-construction-co-v-state-nyclaimsct-1978.