Lenart Constructors, Inc. v. State

6 Misc. 2d 473, 165 N.Y.S.2d 407, 1957 N.Y. Misc. LEXIS 2820
CourtNew York Court of Claims
DecidedJune 24, 1957
DocketClaim No. 32384
StatusPublished
Cited by2 cases

This text of 6 Misc. 2d 473 (Lenart Constructors, Inc. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lenart Constructors, Inc. v. State, 6 Misc. 2d 473, 165 N.Y.S.2d 407, 1957 N.Y. Misc. LEXIS 2820 (N.Y. Super. Ct. 1957).

Opinion

Richard S. Heller, J.

About December 22,1950, the claimant and the State entered into a written contract known as contract No. FA BQE 50-4. Under this contract the claimant agreed to construct for the State of New York a section of the Brooklyn-Queens Expressway, including the Williamsburg Bridge connection viaduct and the Meeker Avenue viaduct on an itemized proposal totaling $2,290,468. The principal construction features consisted of foundations, substructures, steel superstructures and concrete structural slabs, walls and abutments, grading, paving, and utilities for the Expressway.

The work was completed and accepted by the State on March 9, 1953. Thereafter the State forwarded to the claimant a final estimate dated June 8, 1953. This final estimate was returned to the State together with a letter from the claimant verified by claimant’s vice-president setting forth that the final estimate was incorrect in that it failed to include payment for about 40,000 pounds of reinforcing rods installed in cast-in-place piles for which the unit bid price was 15 cents per pound, making a total not included for payment of $6,000 and further that the State had “ wrongfully and arbitrarily” refused to permit the claimant to subcontract the work of paving the road, construction of curbs and sidewalks and other incidentals included in 15 separate items of the contract, which refusal resulted in damage to the claimant in the amount of $84,843. Subsequently, the State forwarded to the claimant on December 17, 1953 a check in the amount of $77,008.13, which was the amount admittedly due from the State to the claimant under this contract. This check was returned by the claimant in order to avoid the provision contained in the contract that acceptance of a final payment constituted a release of any further claims.

[475]*475On January 7, 1954 the claimant filed this claim seeking recovery of the sum of $84,771.70 based upon ah alleged arbitrary and wrongful refusal to permit subcontracting of certain work, the sum of $6,000 for the failure of the State to pay for 40,000 pounds of reinforcing rods and for the sum of $77,008.13 which represented the balance due under the contract aside from the disputed items together with interest on each of these sums. Subsequently the claim for $77,008.13 was severed from the other items and recovery of that amount was granted but the question of the claimant’s right to interest thereon was specifically reserved for determination with the other two items contained in the claim.

The issues before this court for determination on this trial are:

1. Is the claimant entitled to recover for damages alleged to have resulted from the State’s refusal to permit subcontracting of certain items of the contract?

2. Is the claimant entitled to recover for reinforcement used in cast-in-place piles?

3. "What amount of interest is claimant entitled to recover?

In entering into this contract the claimant agreed to ‘ ‘ furnish all of the materials, appliances, tools and labor of every kind required, and construct and complete in the most substantial and workmanlike manner ” the designated work in accordance with the contract and to “do everything required by the Contract (Contract Documents) as defined herein ”.

One of the provisions of the contract was an agreement by the contractor that in accordance with section 138 of the State Finance Law, the contractor was prohibited by law “ from assigning, transferring, conveying, sub-letting or otherwise disposing of the same [contract], or of his right, title or interest therein, or his power to execute such contract to any other person, company or corporation, without the previous consent in writing of the department or official awarding the same.” The contract also contained certain provisions required in all contracts involving Federal aid funds. The contract itself bears a notation of concurrence by the Bureau of Public Works of the United States Department of Commerce dated November 29,1950 and in article 1 thereof specifically refers to Federal aid. Among these provisions required for contracts involving Federal aid funds was article 7 which provides:

“ The contractor shall perform with his own organization work amounting to not less than fifty percent of the remainder obtained by subtracting from the total original contract value [476]*476the sum of any items designated in the contract as “ Specialty Items ”.

“ Any items that have been selected as “ Specialty Items ” for the contract are listed as such in the Special Provisions found elsewhere in the contract.

“No portion of the contract shall be sublet, assigned or otherwise disposed of except with the written consent of the contracting officer or his authorized representative.

“ Request for permission to sublet, assign, or otherwise dispose of any portion of the contract shall be in writing and accompanied by a showing that the organization which will perform the work is particularly experienced and equipped for such work. * * * Consent to sublet, assign or otherwise dispose of any portion of the contract shall not be construed to relieve the contractor of any responsibility for the fulfillment of the contract.”

It is undisputed that no section of the contract contained any listing of “ Specialty Items ”.

The dispute which has arisen here is limited to the right of the claimant to delegate the performance of a contractual duty by subcontracting for a portion of the work with another contractor. At the time of entering into this contract the claimant had no right to delegate performance of the contract or any portion thereof. He could acquire such right only by the express consent of the Superintendent of Public Works and the contract clearly provided that this consent would not be granted for more than 50% of the total original contract value. This prohibition against the delegation of performance is a valid provision of the contract. (2 Williston on Contracts [rev. ed.], p. 1217; Restatement, Contracts, § 160.) It does not involve any question of an invalid restraint upon the right of alienation and it was not repugnant to public policy since the contractual provisions were a reflection of statutes and Federal regulations. Unless there was some implied obligation on the part of the Superintendent of Public Works to consent to a delegation of the duty of performance in whole or in part, a refusal to so consent could not constitute a breach of contract by the State. Such refusal could not be either a failure to perform an act promised or a prevention or hindrance of the performance which the claimant had agreed to deliver. Thus there could be no breach by the State. (Restatement, Contracts, § 312 )

Claimant urges that there was an on part of the State to consent to delegation of performance since the nature of the construction industry required subcontracting. [477]*477No such requirement may be implied as a provision of this contract on the evidence presented. The restrictions on delegation of performance were clear and unambiguous and voluntarily entered into by the claimant.

The claimant further urges that there was an obligation on the part of the State to consent to this specific request to delegate performance by reason of the State’s prior conduct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deverho Construction Co. v. State
94 Misc. 2d 1053 (New York State Court of Claims, 1978)
Merritt-Chapman & Scott Corp. v. State
25 A.D.2d 455 (Appellate Division of the Supreme Court of New York, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
6 Misc. 2d 473, 165 N.Y.S.2d 407, 1957 N.Y. Misc. LEXIS 2820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lenart-constructors-inc-v-state-nyclaimsct-1957.