Shore Bridge Corp. v. State

186 Misc. 1005, 61 N.Y.S.2d 32, 1946 N.Y. Misc. LEXIS 1966
CourtNew York Court of Claims
DecidedMarch 20, 1946
DocketClaim No. 27112
StatusPublished
Cited by12 cases

This text of 186 Misc. 1005 (Shore Bridge Corp. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shore Bridge Corp. v. State, 186 Misc. 1005, 61 N.Y.S.2d 32, 1946 N.Y. Misc. LEXIS 1966 (N.Y. Super. Ct. 1946).

Opinion

Lambíase, J.

On or about the 19th day of October, 1938, claimant and the defendant, State of New York, duly entered into a written contract whereby claimant agreed to furnish all the materials, appliances, tools and labor of every kind required for the reconstruction of the Hornell-Big Creek Bridge No. 1-A and North Approaches, constituting reconstruction contract No. 3998, and for the construction of the Hornell City, Seneca Street-South Approach to the Bridge, constituting contract No. C-38-9, in the county of Steuben, New York, work under the contract to be completed in the most substantial and workmanlike manner.

Work under the contract was commenced by the claimant on or about October 30,1938, and, pursuant to its terms, was to be completed and wholly performed on or before September 1, 1939. Claimant completed its contract on or about August 26, 1939, and all work thereunder was accepted by the defendant. A receipt for payment under the final estimate was signed by claimant on or about January 19,1940. This receipt contained a provision to the effect that it was signed without prejudice to claimant’s right to have recourse to the Court of Claims for damages alleged to have been sustained by it" during the course of its performance of the work under said contract.

Thereafter and on or about June 14, 1940, claimant filed a notice of intention to file a claim herein, and on or about February 21,1942, it filed a claim for $24,048.18 with interest thereon from February 24, 1940. This claim alleges various breaches of contract on the part of the State of New York, and recovery is sought therein in the amount above stated, as and for increased costs to the claimant in the performance of its work, and damages sustained by claimant occasioned by reason of the afore-mentioned breaches of contract.

Upon the trial of this claim, the claimant, by its proof, reduced its demand for damages to the sum of $4,100, which sum is composed of two items: The first, in the amount of $2,000, for damages alleged to have been sustained by claimant by reason of the fact that claimant’s plant, machinery and equipment, which had been brought to the contract site for the purpose of performing the work under the contract, were compelled to remain idle on the job for a period of one month due to the unnecessary and unreasonable delays caused by the State: and [1008]*1008the second, in the amount of $2,100, for extra work performed by claimant under protest and at the direction of the defendant’s engineer in charge of the job.

The State rested its case at the close of claimant’s case; the length and the alleged cause or causes of the delays involved in claimant’s first item of damage, and the amount and value of the alleged extra work constituting the basis of claimant’s second item of damage are not contested by the State. In fact, it is conceded that the length of time that claimant was delayéd in the performance of its work under the contract herein is one month; and that the claimant’s plant, machinery and equipment were held idle at the site and could not be put to gainful use by claimant for said period of time. ' It is also admitted by the defendant that the fair rental value of said plant, machinery and equipment for said period of one month that it was held idle is $2,000 (State’s proposed Findings of Fact Nos. 5, 6 and 7). The defendant also admits that the fair and reasonable value of the extra work item is the sum of $2,100; but in this connection,' it argues and submits that said amount covers all extra work and increased costs to claimant by reason of errors, changes and requirements of every name and'nature (State’s proposed Findings of Fact No. 2, in part)'.

At the conclusion of claimant’s case, the State moved for the dismissal of all of that part of claimant’s claim which, for the purpose of' convenience, we have designated herein as the first item thereof. It also moved at various times during, the trial and at the end of claimant’s case to strike out all the. testimony of the claimant and its witnesses with reference to said item upon the ground that the claim attempted to be proved thereby was not actionable. Decision was reserved by the court on said motions,, and they are disposed of hereinafter.

It seems to us, therefore, that the question for us to determine herein with reference to the first item of claimant’s claim may be briefly stated as follows: Is claimant precluded from recovering its damages sustained by reason of the enforced idleness of its plant, machinery and equipment occasioned by delays caused by the State, notwithstanding the fact that claimant completed its contract within the time specified under the contract, the period of such enforced idleness of such plant, machinery and equipment being wholly within the contract period? Under the circumstances of this case, the question is one of law, and we shall now consider it.

It is the contention of the claimant that although the contract was completed within the time-specified therein, it was, [1009]*1009nevertheless, because of the delay caused through the State’s fault, prevented from completing its contract according to its work progress schedule, which would have seen the work completed and performed one month before the date of actual completion and termination of the work. It contends that thereby the State breached its contract.

On the other hand, the State argues that, since the claimant completed its work under the contract within the time set forth therein, the claimant cannot and does not have a cause of action for damages for the enforced idleness of its plant, machinery and equipment because of the delay hereinbefore mentioned. The State concludes that there has been no breach of contract under the circumstances, and it submits further that all extra work and increased costs to the claimant by reason of errors, changes and requirements of every name and natiixe have either been paid in full or are already included in the item of $2,100 which claimant is seeking for extra work herein. And it contends that any acts or circumstances which resulted in consuming the entire period of the contract for its performance are not unreasonable and are clearly contemplated by the contract, and that no recovery can be had by reason thereof.

Although the State concedes that the total length of time that the claimant was delayed by the State in the performance of its work is the period of one month, we deem it necessary to refer to, and to discuss briefly, the salient evidence relating to said delay or delays as it bears upon the question of whether or not the State did commit a breach of contract herein.

Some of the acts complained of by the claimant are as follows: (a) It appears that soon after the commencement of the work, the State’s engineer set out the temporary line for the location of the temporary bridge; and this line, as thus established, was, through his error, laid out too close to the old bridge structure, thereby necessitating a relocation of the line. A new site, therefore, had to be cleared for the new location despite the fact that one had already been prepared where previously designated by the State. Errors were also made by the engineer for the State in laying out the pile bents on both the north and south sides of the site of the temporary bridge.

(b) The plans prepared and furnished by the State had indicated at certain points thereon, the location of water lines. Upon excavation being made at the indicated points, it was discovered that the indicated location was erroneous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A & B Enterprises, Inc. v. Hartford Insurance
198 A.D.2d 389 (Appellate Division of the Supreme Court of New York, 1993)
Acme Builders, Inc. v. Facilities Development Corp.
69 A.D.2d 937 (Appellate Division of the Supreme Court of New York, 1979)
Fehlhaber Corp. & Horn Construction Co. v. State
65 A.D.2d 119 (Appellate Division of the Supreme Court of New York, 1978)
Deverho Construction Co. v. State
94 Misc. 2d 1053 (New York State Court of Claims, 1978)
Mount Vernon Contracting Corp. v. State
56 A.D.2d 952 (Appellate Division of the Supreme Court of New York, 1977)
Dynamics Corp. of America v. International Harvester Co.
429 F. Supp. 341 (S.D. New York, 1977)
New Again Construction Co. v. City of New York
76 Misc. 2d 943 (New York Supreme Court, 1974)
Fehlhaber Corp. v. State
63 Misc. 2d 298 (New York State Court of Claims, 1970)
Norman Co. v. County of Nassau
27 A.D.2d 936 (Appellate Division of the Supreme Court of New York, 1967)
Polley v. Plainsun Corp.
7 Misc. 2d 605 (New York Supreme Court, 1957)
A. E. Ottaviano, Inc. v. State
202 Misc. 532 (New York State Court of Claims, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
186 Misc. 1005, 61 N.Y.S.2d 32, 1946 N.Y. Misc. LEXIS 1966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shore-bridge-corp-v-state-nyclaimsct-1946.