Del Genovese v. Third Avenue Railroad

13 A.D. 412, 43 N.Y.S. 8
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 15, 1897
StatusPublished
Cited by32 cases

This text of 13 A.D. 412 (Del Genovese v. Third Avenue Railroad) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Del Genovese v. Third Avenue Railroad, 13 A.D. 412, 43 N.Y.S. 8 (N.Y. Ct. App. 1897).

Opinion

Ingraham, J.:

The complaint alleges two causes of action. The first cause of action was for the balance due under a certain contract for excavating the cellars and foundation for a building to be erected upon the-property of the defendant, it being alleged that there was due and unpaid under the contract the sum of $10,792.50.

The second cause of action was to recover damages sustained by the plaintiffs in consequence of the defendant having “ hindered,, delayed, embarrassed and interfered with them (the plaintiffs) and with the work being carried, on by them; prevented the plaintiffs, from going on and finishing the same in a reasonable and proper-manner ; suspended the entire work under said contract from time to time; forced them to keep. their working forces, teams and [414]*414machinery idle for a long period of time; filled, or caused to be filled, the area of excavation with timbers and braces, so that access to the said work with teams was prevented; forced the plaintiffs to take out the material excavated by derricks and buckets instead of by teams; caused the plaintiffs to lose the sale of the material excavated by inability to deliver at time agreed upon; forced the plaintiffs to handle and rehandle many times the excavated material before removing the same; increased the time and necessity of pumping beyond that called for in the ■ contract, and in many other ways increased the expense of the plaintiffs’ work,” whereby it is alleged that the plaintiffs sustained damages in the sum o.f $73,800. The referee found that there was unpaid and due to the plaintiffs on .account of the contract price which the defendant agreed to pay for such excavation the sum of $7,500,' and for extra work done by the plaintiffs in the sum of $485.

Upon the second cause of action the referee found that, for various periods of time, during the year 1892, the plaintiffs’ work of excavation was entirely suspended, either by order of the architect, or .in consequence of the said premises being so occupied by other contractors acting under the architect’s supervision and direction, that the plaintiffs were unable to have access to the premises for the purposes of their contract; that the whole number of days that the plaintiffs were prevented from prosecuting their work was forty-seven ; that the said interruptions to the plaintiffs’ work were unreasonable and the fault of the defendant, and in disregard • and violation of the duty which the defendant owed to the plaintiffs to give them fair access to the said premises, in order that they might perform their contract, and not to hinder or obstruct them in their work. The referee also found that, in consequence of the said premises being largely filled with obstructions, such as timbers and earthworks, and interior walls placed there by the defendant, or under the personal supervision and direction of the defendant’s said architect, the plaintiffs, during a large part of 1892, were unable to carry on the work of excavating in the ordinary way, which greatly increased the costs to the plaintiffs of removing such material. The referee further finds that such interference with the plaintiffs was unreasonable and the fault of the defendant, and in disregard and violation of its .said duty to the plaintiffs; that the delay of the [415]*415plaintiffs in performing their said contract within the stipulated time was caused by the interruptions and interferences and suspensions above referred to ; that, except for such interruptions and interferences, the plaintiffs would have fully performed the said contract in about 100 days. The referee, therefore, orders judgment for the plaintiffs for $25,805.40, with interest and costs.

It is quite evident, I think, that the correctness of the referee’s decision depends upon the question as to whether the finding that the interruptions to the plaintiffs’ work were caused by the defendant and were a violation of the duty under which, or of an implied contract whereby, the defendant was to furnish access to the said premises in order that they should perform their contract, and not to hinder and obstruct them in their work, was sustained by the evidence. In considering this question it' is quite important to consider how far the action of the architect under the contract between the plaintiffs and. the defendant was as agent of the defendant; and how far the architect, in giving directions to the plaintiffs as to the manner of doing the work, and in directing and controlling the other contractors in the performance of their contract as to so unreasonably and unnecessarily obstruct the work of the plaintiffs as to materially increase the cost of performing their contract, can be said to he acting for the defendant. There can he no question but that, under this contract, there was an “ implied understanding by all parties that they (the plaintiffs) were to he unrestricted in the employment of means to perform it (the contract), and that nothing which it was the duty of the owner to do to enable the contractors to perform should be left undone” (see Mansfield v. N. Y. C. & H. R. R. R. Co., 102 N. Y. 213); and the question is whether there has been a breach by the defendant of this implied understanding or contract.

It is not claimed by the plaintiffs that the defendant in any way directed or interfered with the operation of the work, or with the performance by the plaintiffs of their contract, except by the directions given by the architect to the plaintiffs and to the other contractors. And we must look to the contract to determine just what relation this architect bore to the parties t.o the contract, and to the evidence to see just how far either party was responsible for an unreasonable or negligent performance of the duties imposed upon him.

[416]*416-In the case of Mansfield v. N. Y. C. & H. R. R. R. Co. (supra) attention is expressly called to the absence of any provision in the contract for the submission of the question there at issue to the decision either of the owners or their engineer. In that case the court says: “ It was made the duty of the owner not only to prepare the foundations for the reception of the work of the contractors, but also to notify them (the contractors), through their agent, of the fact of such-readiness. The terms of the contract plainly imply that the notice was to be of an actually existing condition, and not the expression of an opinion on the part of the engineer that the foundations were sufficiently advanced, to enable the contractors to prosecute their work advantageously. ’The contractors have not submitted any such question to the decision either of the owners or their engineer, and in view of the heavy obligations assumed by them it would have been unwise and hazardous to have done so.”

We have here to ascertain just what questions were left to the decision of the architect by the contract, and how far the architect, in determining the questions submitted to him, was acting as the chosen arbitrator between the parties, independently of either party, but upon his own responsibility. By this contract both parties agree that the architect shall have a certain limited control over, the work ; that the contract itself shall he performed in a good, workmanlike and substantial manner, to the satisfaction and under the direction of the said architect, to be testified to by the writing of a certificate under the hand of the said architect; and his certificate is as binding upon the defendant as upon the plaintiffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman Co. v. County of Nassau
27 A.D.2d 936 (Appellate Division of the Supreme Court of New York, 1967)
Johnson v. State
46 Misc. 2d 303 (New York State Court of Claims, 1963)
Dorsey v. Oregon Motor Stages
194 P.2d 967 (Oregon Supreme Court, 1947)
Shore Bridge Corp. v. State
186 Misc. 1005 (New York State Court of Claims, 1946)
R. H. Baker Co. v. State
267 A.D. 712 (Appellate Division of the Supreme Court of New York, 1944)
Haley v. Brady
137 P.2d 505 (Washington Supreme Court, 1943)
Seglin Construction Co. v. State
249 A.D. 476 (Appellate Division of the Supreme Court of New York, 1937)
Mason Tire & Rubber Co. v. Cummins-Blair Co.
157 N.E. 367 (Ohio Supreme Court, 1927)
John Johnson Construction Co. v. State
211 A.D. 512 (Appellate Division of the Supreme Court of New York, 1925)
Mack v. State
122 Misc. 86 (New York State Court of Claims, 1923)
Worthington v. Davis
94 So. 806 (Supreme Court of Alabama, 1922)
American Concrete Steel Co. v. Hart
285 F. 322 (Second Circuit, 1922)
J. W. Brennan Construction Co. v. State
117 Misc. 816 (New York State Court of Claims, 1921)
Schunnemunk Construction Co. v. State
116 Misc. 770 (New York State Court of Claims, 1921)
Hart v. American Concrete Steel Co.
278 F. 541 (E.D. New York, 1921)
S. Pearson & Son, Inc. v. State
112 Misc. 29 (New York State Court of Claims, 1920)
M. L. Ryder Building Co. v. City of Albany
187 A.D. 868 (Appellate Division of the Supreme Court of New York, 1919)
W. G. Cornell Co. v. Schuylkill County
222 F. 876 (Third Circuit, 1915)
Hayden v. Astoria
145 P. 1072 (Oregon Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
13 A.D. 412, 43 N.Y.S. 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/del-genovese-v-third-avenue-railroad-nyappdiv-1897.