J. W. Brennan Construction Co. v. State

117 Misc. 816
CourtNew York Court of Claims
DecidedDecember 15, 1921
DocketClaim No. 15747
StatusPublished
Cited by5 cases

This text of 117 Misc. 816 (J. W. Brennan Construction Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. W. Brennan Construction Co. v. State, 117 Misc. 816 (N.Y. Super. Ct. 1921).

Opinion

Cunningham, J.

The claimant entered into a contract with the state of New York for the improvement of a state and county highway in Chemung county, known as the Erin-Van Etten-Spencer, part one, County Highway No. 1311,” six and eighty-seven one-hundredths miles long, and extending east and west. The contract was dated August 30, 1915, and was executed by the claimant September 1, 1915, and [817]*817by the state September 17, 1915. It required the contractor to begin work within ten days and to complete the work on or before the two hundredth working day, which would be on or about November 15, 1916.

About three and nine-tenths miles from the west end of the road a ravine crossed the highway. The plans, part of the contract, provided for a concrete culvert six feet by eight feet at this point, “to be built by the town,” over which culvert when built the claimant was required to deposit earth fill for a distance of about eighty feet and to a depth of twenty feet. On August 21, 1915, the town of Erin notified the state that the various bridges within its limits and in the route of the highway would be built, except the concrete culvert mentioned, the town contending it was unnecessary, and that an iron boiler three feet in diameter had sufficed previously under all flood conditions.

On September 17, 1915, the commissioner of highways, by letter, advised claimant that the right of way “ has been acquired, the contract has been executed by the Commissioner and work upon the same can be started at once by you.” On October 21, 1915, the state’s engineer wrote to the claimant, “ unless we find that you are prepared to start within the next week, I shall have to take up this matter with the department at Albany, * * * two-hundred working days are allowed you for the completion of this contract.” The claimant then was ignorant of the position the town of Erin had taken. The claimant began performance on October 20, 1915, and during that month' and November following delivered on the site of the contract the necessary plant and equipment. Much of the fill necessary was extensive and heavy and required the use of a steam shovel. This implement, weighing eighteen tons, began excavation, at the east end of the road and worked westerly toward the ravine.' There was ample time for the construction [818]*818of the culvert before the excavation so begun could progress to the ravine. The contract provided that the material to be deposited over the culvert must be taken from the highway on each side of it.

The orderly and proper method to progress the work required that the claimant obtain material to the east of the culvert to make a sufficient fill over it for the steam shovel to cross, and then to proceed with the work on the west side of the ravine. The claimant planned and prosecuted the work to that end, but when the shovel had progressed to the point east of the ravine from Avhich material should be taken to make the fill over it, the culvert had not yet been built. This was on December 21, 1915, and only four days’ excavation work for the shovel remained to be done between the point where it had arrived and the site of the culvert. Between September 17, 1915, and December 21, 1915, the claimant, at various times, had called the attention of the state’s engineers to the imperative necessity that the culvert be built promptly and that failure to do so would impede the claimant. The latter was assured each time that it soon would be built. On December 21, 1915, the claimant suspended all operations and did not resume work until the following spring. Its reasons for doing so were tAvo — unfavorable weather conditions because of which it preferred to suspend work, and the absence of the culvert which prevented further progress. Relying on the state’s assurances, the claimant retained the shovel until July 1, 1916, at the east of the culvert, so that it might continue the work from that point. In June, 1916, impelled by the necessity for the. completion of the culvert and the harassment resulting from its absence, the claimant itself attempted to build the culvert, being willing to assume the risk of obtaining compensation for it, but the state halted that work and prevented it being done. On July 1, 1916, the culvert not haAdng been constructed, the [819]*819claimant transferred the shovel to the west side of the ravine by means of a detour and considerable effort and expense. This could not have been done by any reasonable process in the winter months because of the physical conditions prevailing. The steam shovel excavation to the west of the ravine was continued during the season of 1916 and completed in the spring of 1917, at which time the culvert had not yet been built, and the claimant being unable yet to make the fill at that point, sent the shovel to work on another contract.

The culvert was completed in July, 1917. The claimant thereafter was required to return the shovel to that point and complete the fill there, in August, 1917. The road was completed and accepted August 27,1918.

Damages are sought in this proceeding,

(1) Because of the alleged delay and interference with claimant’s performance of the contract because of the failure to provide it with the site of its work, through the omission to build the culvert at the proper time; and also,

(2) Because of the following facts: Written information furnished the claimant at the time it bid provided:

“ REPORTS OP MATERIALS.

Sand

“ Sand, * * * taken from the property of Dwight Wolever, * * *. Reported plentiful. This sand is accepted for use in any class of concrete * * #

Gravel

Gravel, * * * from the property of Dr. Can-field, * * * is accepted for use in second and third class concrete * *

The plans also provided: ‘ ‘ Sand and gravel * * * shall be approved local materials from sources of supply located in the vicinity adjacent to the highway to be improved.”

[820]*820The contract, provided: “ Information will be furnished when available regarding location of accepted materials but the use of any materials will be permitted only so long as its quality remains equal to that of the accepted sample. In all cases the contractor will be required to satisfy himself as to the available supplies of materials and the relative location of the same.”

The contract further provided: “ The contractor further agrees, that he is fully informed regarding all of the conditions affecting the work to be done and labor and materials to be furnished for the completion of this contract, and that his information was secured by personal investigation and research and not from the estimates of the state commission of highways ; and that he will make no claim against the state by reason of estimates, tests or representations of any officer or agent of the state.”

Thereafter, the state rejected sand front Wolever property and claimant imported sand at an. additional expense of $522.52. The amount of gravel found on the Canfield property was negligible and the claimant was obliged to procure it elsewhere, at a cost of $649.56.

We will discuss the second phase of the claim first. There is a paucity of evidence of the circumstances under which the sand was rejected. There was no testimony that it was equal to the sample accepted. One of the claimhnt’s officers testified that the state ‘ ‘ again accepted the sand ’ ’ after the work was done. The meaning of this is not clear.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Village of Chestnut Ridge v. Howard
708 N.E.2d 988 (New York Court of Appeals, 1999)
Village of Chestnut Ridge v. Howard
172 Misc. 2d 745 (New York Supreme Court, 1997)
Johnson v. State
46 Misc. 2d 303 (New York State Court of Claims, 1963)
F. J. Lewis Mfg. Co v. Snyder
37 F.2d 299 (Sixth Circuit, 1930)
Hendrickson-McCabe Construction Co. v. State
120 Misc. 818 (New York State Court of Claims, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
117 Misc. 816, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-w-brennan-construction-co-v-state-nyclaimsct-1921.