McMahon v. . the New York and Erie Railroad Company

20 N.Y. 463
CourtNew York Court of Appeals
DecidedDecember 5, 1859
StatusPublished
Cited by61 cases

This text of 20 N.Y. 463 (McMahon v. . the New York and Erie Railroad Company) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McMahon v. . the New York and Erie Railroad Company, 20 N.Y. 463 (N.Y. 1859).

Opinion

Selden, J.

The decision filed by the referee in this case, consists of a series of mingled conclusions of fact and of law; and the printed Case contains no such statement of the facts found by him as will of itself enable this court to judge as to the accuracy of those conclusions. I find, however, appended to the Case, a printed paper, entitled in the cause and headed: “ Statement of facts.” It is not signed, nor in any way specially authenticated; but from its position, I shall assume, especially as against the appellant, by whom the papers are presented, that it is authentic, and shall follow it so far as practicable, and refer to the other parts of the case for the purpose of explanation only.

The first conclusion arrived at by the referee,, as stated in his written decision is,, “ that there was no such measurement or classification of the work as to conclude the plaintiff,” and *465 that “ the amount and quality of the work, is, therefore, an open question, to be determined upon the evidence in the case.”

To this part of the decision of the referee, the defendants have excepted; and to understand the ground of this exception, it is necessary to refer to the contracts under which the work was done. Each of the contracts, of which there were two, contained the following provision, viz.: “ The work shall be executed under the direction and constant supervision of the engineer of the-company, by whose measurements and calculations the quantities and amounts of the several kinds of work performed under this contract shall be determined, and who shall haye full power to reject or condemn all work or materials which in his opinion do not fully conform to the spirit of this agreement; and shall decide every question which can or may arise between the parties, relative to the execution thereof, and his decision shall be final and binding upon both parties.”

Provisions analogous to this are very common in contracts of this description, and are inserted to prevent disputes in regard to the amount and character of the work performed; and to secure the accuracy of all measurements and calculations, by having competent persons to make them. They aie free from any legal objection, and have frequently been held to be obligatory upon parties according to their terms. In principle, they do not differ materially from the provisions in question in the cases of Smith v. Briggs (3 Denio, 73), and The United States v. Robeson (9 Peters, 319). In the latter of those cases, in which the transportation of certain troops and stores for the government was to" be paid for upon the certificate of the commanding officer of the troops as to the amount of the service, it was held that the certificate of the officer was a condition precedent to any right of recovery, and that the party must either procure the certificate, or show sufficient reason why it could not be obtained.

So here, where the amount of the work was “ to be determined" by the engineer of the company, whose decision was to be final and binding upon the parties, it was incumbent upon the plaintiff to prove such a determination made, or else *466 to show something which would legally exempt him from the obligation. The proposition, therefore, contained in the decision of the referee, that “ there was no such measurement or classification of the work as to conclude the plaintiff”—and therefore the amount and quality of the work was an open question, to be determined upon the evidence—requires some further explanation or qualification in order to be sustained. It states, taken by itself, a complete bar to any right of recovery by the plaintiff; because it negatives a condition precedent, the performance of which it was incumbent upon the plaintiff to prove, and suggests no excuse for its non-performance. We cannot look into the evidence, to ascertain the grounds upon which this proposition was based. Were it not, therefore, lor a clause in the statement of facts appended to the Case, this exception would be fatal to the judgment. It is however there stated: “That such estimates, measurements, calculations and classifications as were made, were erroneous in fact, and were made ex parte without notice to Patrick McMahon, or the plaintiff and without giving either of them an opportunity to be present; and that the defendants were requested to have estimates, measurements, calculations, and classifications of the work made by the engineer, or to have those that had been made reviewed by him, which the defendants refused.”

The first proposition of the referee, so far as its review by this court is concerned, rests exclusively upon this statement. The question presented, therefore, is, whether under such a provision on the subject of a final estimate as that contained in these contracts, the contractor or party doing the work has a right to be present when the measurements are made; or whether the engineer may proceed ex parte, and without giving any notice to the contractor, and make such estimate. I am not aware that this question has ever been decided. It is open, therefore, to the application of such principles as are best calculated to secure the rights of the parties. When it is considered, then, that the engineer who makes the estimate is the agent and employee of the defendants, selected by and receiving his compensation from them, and that his estimate, if legally *467 made, is absolutely conclusive upon the rights of the plaintiff, it is too plain to be denied, that he ought in justice to have at least the opportunity of being present, when that in which he is so deeply interested is done. An arbitrator, although supposed to be entirely indifferent, can never proceed a single step without notice to the parties. The position of the engineer here, is not unlike that of an arbitrator; with this difference, that he is the selected and paid servant of one of the parties. Ought he then to be permitted to go on without notice to the other party ? There can be but one answer to the question. As the con. tractor in such cases is dependent entirely upon the skill and integrity of the company’s agent, he ought at least to have such protection as a right to notice may afford. I have no hesitation, therefore, in holding, that the ex parte estimate and measurement made in this case was not such a final estimate as would bind the plaintiff.

This conclusion alone, without some excuse on the part of the plaintiff for not having procured a proper final estimate to be made, would not support the decision of the referee. But such an excuse is afforded by the latter part of the paragraph in the statement of facts, already cited, which states that the defendants “ were requested” to have estimates, measurements, &c., made, and that they “ refused.” It is to be inferred, undoubtedly, from this statement, that the request was made by the plaintiff or his assignor, the original contractor. This was all, I think, that it was incumbent upon the contractor to do. The engineer was entirely under the control of the company, subject to its order and moved by its will; and after the company had absolutely refused to direct him to make an estimate, or to review what he had already made, it would have been useless for the contractor to apply to him; and I think he was under no obligation to do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BOARD OF WATER & SEWER COM'RS v. Bill Harbert Const. Co.
870 So. 2d 699 (Supreme Court of Alabama, 2003)
Taylor v. State Farm Fire & Casualty Co.
1999 OK 44 (Supreme Court of Oklahoma, 1999)
Thomas Crimmins Contracting Co. v. City of New York
138 A.D.2d 138 (Appellate Division of the Supreme Court of New York, 1988)
Demms v. Blanchard
150 Misc. 867 (New York Supreme Court, 1934)
Clayburgh v. Clayburgh
218 A.D. 411 (Appellate Division of the Supreme Court of New York, 1926)
Croker v. New York Trust Co.
123 Misc. 460 (New York Supreme Court, 1924)
Cleave v. Reeder
204 A.D. 826 (Appellate Division of the Supreme Court of New York, 1923)
Second Nat. Bank v. Columbia Trust Co.
288 F. 17 (Third Circuit, 1923)
Breymann v. Morris & Cummings Dredging Co.
202 A.D. 464 (Appellate Division of the Supreme Court of New York, 1922)
Demotte v. Whybrow
263 F. 366 (Second Circuit, 1920)
Faber v. . City of New York
118 N.E. 609 (New York Court of Appeals, 1918)
City of Chickasha v. Hollingsworth
1916 OK 223 (Supreme Court of Oklahoma, 1916)
Bradley v. McDonald
157 A.D. 572 (Appellate Division of the Supreme Court of New York, 1913)
Norcross v. Wyman
72 N.E. 347 (Massachusetts Supreme Judicial Court, 1904)
General Electric Co. v. National Contracting Co.
70 N.E. 928 (New York Court of Appeals, 1904)
Cornwall v. J. J. Moore & Co.
125 F. 646 (N.D. California, 1903)
Sweeny v. . City of New York
66 N.E. 101 (New York Court of Appeals, 1903)
National Contracting Co. v. Hudson River Water Power Co.
63 N.E. 460 (New York Court of Appeals, 1902)
Fuller v. Cole
58 N.Y.S. 741 (Appellate Division of the Supreme Court of New York, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
20 N.Y. 463, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcmahon-v-the-new-york-and-erie-railroad-company-ny-1859.