In re the Arbitration Between Board of Education & Heckler Electric Co.

26 Misc. 2d 876, 204 N.Y.S.2d 396, 1960 N.Y. Misc. LEXIS 2714
CourtNew York Supreme Court
DecidedJuly 8, 1960
StatusPublished

This text of 26 Misc. 2d 876 (In re the Arbitration Between Board of Education & Heckler Electric Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Arbitration Between Board of Education & Heckler Electric Co., 26 Misc. 2d 876, 204 N.Y.S.2d 396, 1960 N.Y. Misc. LEXIS 2714 (N.Y. Super. Ct. 1960).

Opinion

Bernard S. Meyer, J.

In the Daedalian ■ labyrinth of “ contract documents ” that constitutes the agreement between petitioner and respondent lurks a contractual monstrosity equally as fabulous as the mythological Minotaur — the arbitration provisions of that agreement. Petitioner school board entered into an agreement with respondent, an electrical contractor, for the electrical work on 17 buildings constituting new junior and senior high schools. The contract documents include Drawings and Specifications, Notice to Contractors, Instructions to Bidders, Proposal, Contract, General Conditions Governing All Contracts and the Standard Form of the American Institute of Architects which the General Conditions amend and supplement. A number of the provisions of those documents concern the procedure for the determination of claims. The contract of January 3, 1956 between the parties contains the following provision:

[877]*877article 11. Arbitration

In the event that any disagreement shall arise between the parties hereto and in the event that either of the parties is not satisfied with the decision of the Architect, then the dispute shall be settled by arbitration. Each party shall, upon five (5) days written notice from the other, select one arbitrator and the two arbitrators so selected shall select a third arbitrator and the decision of a majority of the arbitrators shall be binding upon both of the parties hereto when submitted to them in writing by the arbitrators. Each of the parties shall .pay for one-half of the cost of the arbitrators. Arbitration shall be had in accordance with the terms of the General Conditions. The place of arbitration, however, shall be the City of New York.

The General Conditions Governing All Contracts include: — Article 38, defining the Architect’s Status, which provides in part as follows:

As the Architect is, in the first instance, the interpreter of the conditions of the Contract and the judge of its performance, he shall side neither with the Owner nor with the Contractor, but shall use his powers under the contract to enforce its faithful performance by both;

Article 39, entitled “Architect’s Decisions”, reading as follows:

The Architect shall, within a reasonable time, make decisions on all claims of the Owner or Contractor and on all other matters relating to the execution and progress of the work or the interpretation of the Contract Documents.

The Architect’s decisions, in matters relating to artistic effect, shall be final, if within the terms of the Contract Documents.

Except as above or as otherwise expressly provided in the Contract Documents, all the Architect’s decisions are subject to arbitration.

If, however, the Architect fails to render a decision within ten days after the parties have presented their evidence, either party may then demand arbitration. If the Architect renders a decision after arbitration proceedings have been initiated, such decision may be entered as evidence but shall not disturb or interrupt such proceedings except where such decision is acceptable to the parties concerned.

Article 40, entitled ‘ ‘ Arbitration ’ ’, reading as follows:

All disputes, claims or questions subject to arbitration under this contract shall be submitted to arbitration in accordance with the provisions, then obtaining, of the Standard Form of Arbitration Procedures of The American Institute of Architects, and this Agreement shall be specifically enforceable under the prevailing arbitration law, and judgment upon the award rendered may be entered in the court of the forum, state or federal, having jurisdiction. It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right of legal action that either party may have against the other.

The Contractor shall not cause a delay of the work during any arbitration proceedings, except by agreement with the Owner.

Notice of the demand for arbitration of a dispute shall be filed in writing with the Architect and the other party to the contract. If the arbitration is an appeal from the Architect’s decision, the demand therefor shall be made within ten days of its receipt; in any other case the demand for arbitration shall be made within a reasonable time after the dispute has arisen; in no ease, however, shall the demand be made later than the time of final payment, except as otherwise expressly stipulated in the contract.

[878]*878The arbitrators, if they deem that the ease requires it, are authorized to award to the party whose contention is sustained, such sums as they or a majority of them shall deem proper to compensate him for the time and expense incident to the proceeding and, if the arbitration was demanded without reasonable cause, they may also award damages for delay. The arbitrators shall fix their own compensation, unless otherwise provided by agreement, and shall assess the costs and charges of the proceedings upon either or both parties.

(a) Notwithstanding requirements of Article 40 to contrary, arbitration shall be had only during course of construction work of each Contract, until substantial completion of work, in City of New York, be governed by pertinent provisions of American Arbitration Association, State of New York, by 3 arbitrators : Contractor, Architect, and an Engineer.

(b) No traveling fees and expenses of witnesses shall be charged to either party to dispute nor shall arbitrator fix his own compensation.

Article 45, entitled Cooperation- ”, subparagraph (c) of which reads as follows:

It is agreed that in event of any dispute arising as to possible or alleged interference among various Contractors which may retard progress of work, same shall be adjusted by Architects whose decision as to parties at fault and as to manner in which matter may be adjusted shall be binding and conclusive on all parties.

On September 3, 1958 respondent demanded arbitration of (1) its claim for damages of $312,477.28 sustained by delays and interferences by reason of acts of the respondent board, failure of the board to co-ordinate work of contractors and acts of other contractors, and (2) specified extras totaling $11,979.67. The Appellate Division reversed the denial of a stay of that arbitration (8 A D 2d 940) in a memorandum decision stating (1) that section 3813 of the Education Law “ must be deemed to be part of the terms of the contract ” and (2) that the contract did not provide for arbitration of “ acts of the other contractors.” The Court of Appeals affirmed (7 N Y 2d 476) the ruling that section 3813 applied. Its decision contained the following analysis: “ Under the statute, the contractor must present his claim to the Board of Education within three months after its accrual, and the board is given 30 days in which to arrive at a decision. Under the contract, if the decision of the board is adverse to the contractor, he may submit the dispute to the architect (art. 39). And, if he is dissatisfied with the architect’s decision, he is privileged to seek arbitration, but the demand therefor shall be made within ten days ’ of the receipt of the decision (art. 40). As is manifest, neither the provision of the contract for the architect’s decision of disputes nor the provision for an ‘ appeal ’ therefrom to arbitration, comes into effect until the contractor first presents his basic claim to the board pursuant to section 3813.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gold Plastering Co., Inc. v. 200 E. End Ave. Corp.
120 N.E.2d 846 (New York Court of Appeals, 1954)
Matter of Delmar Box Co.(ætna Ins. Co.)
127 N.E.2d 808 (New York Court of Appeals, 1955)
Todd v. Board of Education of the City of Syracuse
79 N.E.2d 274 (New York Court of Appeals, 1948)
McMahon v. . the New York and Erie Railroad Company
20 N.Y. 463 (New York Court of Appeals, 1859)
Thomann v. City of Rochester
176 N.E. 129 (New York Court of Appeals, 1931)
Farrell v. Levy
139 A.D. 790 (Appellate Division of the Supreme Court of New York, 1910)
Gioia v. Gioia
257 A.D. 920 (Appellate Division of the Supreme Court of New York, 1939)
Gold Plastering Co. v. 200 East End Avenue Corp.
282 A.D. 1073 (Appellate Division of the Supreme Court of New York, 1953)
Gioia v. Gioia
171 Misc. 683 (New York Supreme Court, 1939)
Garr v. Gomez
9 Wend. 649 (Court for the Trial of Impeachments and Correction of Errors, 1832)

Cite This Page — Counsel Stack

Bluebook (online)
26 Misc. 2d 876, 204 N.Y.S.2d 396, 1960 N.Y. Misc. LEXIS 2714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-board-of-education-heckler-electric-co-nysupct-1960.