Fehlhaber Corp. v. State

63 Misc. 2d 298, 312 N.Y.S.2d 123, 1970 N.Y. Misc. LEXIS 1745
CourtNew York Court of Claims
DecidedApril 2, 1970
DocketClaim No. 47387
StatusPublished
Cited by5 cases

This text of 63 Misc. 2d 298 (Fehlhaber Corp. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fehlhaber Corp. v. State, 63 Misc. 2d 298, 312 N.Y.S.2d 123, 1970 N.Y. Misc. LEXIS 1745 (N.Y. Super. Ct. 1970).

Opinion

Alexander Del Gtok.no, J.

Claimants, pursuant to a joint venture agreement, entered into a contract with the State of New York for the construction of Interstate Route Connection 512-Gowanus Expressway, 20th Street to 36th Street along 3rd Avenue, F. A. Project No. 1-278-1(47 0.82 mile of Interstate Highway (plus 0.82 mile street repairs on 3rd Avenue), Borough of Brooklyn, City of New York, Kings County, known as Contract FIGE 60-2, being the letting of March 17, 1960 and which [300]*300contract is dated April 8, 1960. Said contract was duly performed and the same accepted by the State of New York as completed on December 28, 1964.

The six remaining causes of action (the fifth cause of action having been withdrawn at trial) charge the State with various and sundry contract misinterpretations, interferences and delays which seem to be inherent, although needlessly so, in State construction contract work. As a result claimants now seek recompense for the added and excessive costs incurred. This memorandum, together with the several requests to find marked ‘1 Found ’ ’ submitted by the claimants and the State and initialled, constitutes the opinion of the court.

FIRST CAUSE OF ACTION.

The contract by its terms is controlling and provides in relevant portion as follows:

FOUNDATION REPORT (p. 64) .
It will be the Contractor’s obligation and responsibility to use methods and equipment which will insure the satisfactory completion of the required work with a minimum of delay, (p. 65). (Emphasis added.)
ITEM 85 TAS — TUBULAR CAST-IN-PLAOE CONCRETE PILES —16" DIA. X %" (P. 139)
The specifications for Item 85 T shall apply with the following additions and modifications: * * *
INSTALLATION OF PIPE PILE
The methods and equipment to be used in installing pipe at the location and to the depth shown on the Contract Plans, or in a satisfactory subsoil as approved by the Deputy Chief Engineer (Bridges), is the responsibility of the Contractor. (Emphasis added.)
(p. 140) The Contractor’s attention is directed to the close proximity of existing foundation and piles at the proposed pile locations. Special care shall be exercised not to distwb existing foundations while driving piles. Except as hereinafter specified, the number of hammer blows shall be kept between eight and ten blows per inch. When this limit of ten blows is reached, the Contractor shall use either or both of the following methods to reduce resistance:
(1) Water jetting. . . .
(2) Boil mucking. . . .
(3) [Chopping or drilling.] (Emphasis added.)
FINAL SEATING OF PILES
After water jetting, soil mucking or chopping, pile driving shall be resumed. Alternate driving and cleaning operations are anticipated for the installation of steel pipe pile. At final seating, the piles shall be driven to the tip elevation shown on the Contract Plans or to a deeper elevation to obtain a driving resistance of not less than (10) blows per inch of the specified hammer for the final inch driven, (pp. 140-41). (Emphasis added.) * * *
[301]*301MEASUREMENT AND PAYMENT
* * -t
The unit price bid per linear foot shall include the cost of furnishing all labor, materials and equipment necessary to establish a proper procedure of driving the pipes. The unit price bid shall also include * 11 * the cleaning and de-watering of the pipes * * * (p. 142). (Emphasis added.)

In addition, the Public Works Specifications of January 2, 1957, previously alluded to under Item 85 TAS, provide, in part, as follows:

ITEM 85T-TUBULAR OAST-IN-PLACE CONCRETE PILES
a. Work. Under this item the Contractor shall furnish and construct open ended tubular piles filled with concrete at locations indicated on the plans or as directed by the Engineer. The piles shall be constructed by filling with concrete steel tubes which are left in the ground, (p. 386). (Emphasis added.)
* * *
e. Placement of the Tube. The methods and equipment to be used in establishing the tube on rock or in satisfactory material is the responsibility of the Contractor, (p. 387). (Emphasis added.)
* * e
The Contractor may, if he so elects, after a study of the underlying material, use any or any combination of the following procedures:
(1) Previously drill the material at the location of the pile to a diameter not greater than 2" less than the outside diameter of the tube itself.
(2) Drive and not clean the tube until it is near its anticipated final position. In this instance, the sole responsibility for deformation of the pile shall rest with the Contractor. If any distortion of the pile occurs it shall be removed and a new pile or tube driven in its place.
(3) Drive the tube and remove obstructions which are found as the tube is driven below the surface to its final location. In all instances the tube in its final location shall be cleaned from its tip to its top. (p. 387). (Emphasis added.) * *
f. Measurement and Payment. * * 1i The unit price bid per linear foot shall include the cost of furnishing all labor, materials and equipment necessary to complete the work, including the furnishing and using of well driving equipment, or any other type of equipment necessary to establish a proper procedure under the Contractor’s selection of his method of driving the piles. The unit price bid shall also include the cutting off of surplus lengths of tubes, the removing of the material from the tube and the placing of concrete in the tube. (p. 388). (Emphasis added.)

Despite the clarity of these provisions, which merely reinforce the commonly accepted view that a contractor may choose his own method of performance, absent a clear direction to the contrary in the contract or the specifications, difficulty was immediately encountered regarding the manner in which the piles were to be driven.

It is clear and uncontradicted that claimants intended to use a removable end closure until the specified resistance of 10 blows per inch was reached at which time the temporary end [302]*302closure would be removed by shattering it with a steel ram. This is amply supported by the estimate sheet for Item 85 TAS prepared by Mr. Winterberg, chief engineer for the Fehlhaber Corporation, which provides for end closures (“End closures (Cl) 661 at 6.00 ea.”), for the removal of debris from the last few feet of the pile (“ Clean out last 5'0" — -3300 c.y. at 20.00") and for the disposal of this pile soil (“ Dispose of pile soil — from last 5' 0 feet 3305 c.y. = 150 c.y. at 15.00/c.y.").

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kalisch-Jarcho, Inc. v. City of New York
135 A.D.2d 262 (Appellate Division of the Supreme Court of New York, 1988)
Fehlhaber Corp. v. State
40 A.D.2d 881 (Appellate Division of the Supreme Court of New York, 1972)
Ingalls Iron Works Company v. Fehlhaber Corporation
327 F. Supp. 272 (S.D. New York, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
63 Misc. 2d 298, 312 N.Y.S.2d 123, 1970 N.Y. Misc. LEXIS 1745, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fehlhaber-corp-v-state-nyclaimsct-1970.