Barash v. State

2 Misc. 2d 680, 154 N.Y.S.2d 317, 1956 N.Y. Misc. LEXIS 1689
CourtNew York Court of Claims
DecidedJuly 24, 1956
DocketClaim No. 32533
StatusPublished
Cited by1 cases

This text of 2 Misc. 2d 680 (Barash v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barash v. State, 2 Misc. 2d 680, 154 N.Y.S.2d 317, 1956 N.Y. Misc. LEXIS 1689 (N.Y. Super. Ct. 1956).

Opinion

Russell G. Hunt, J.

The claimant herein entered into a contract dated October 2, 1952, with the State, through the Department of Public Works, for the work of rehabilitation of the Governor’s hearing room on the second floor of the State Capitol at Albany. The completion date was stated to be December 15, 1952, but there is evidence that the claimant was not to be held to this date, and in fact the completion date was extended to March 23, 1954; the claimant testified that his work was completed before the end of December, 1952, except for the work on the doors, referred to below. The claimant commenced the work of the contract on October 8, 1952, and thereafter there arose differences between the parties over the interpretation of the contract as to certain work which the State called on the claimant to perform. The claimant refused to comply, whereupon the State ordered him to do the work, and the claimant alleges he then complied, but under protest. He now submits a claim wherein he seeks to recover $1,100 for the work of refinishing the entire wood ceiling of the hearing room which he alleges he was required to do, in violation of the contract and over his protest that this was not included in the work of the contract. In addition, claimant seeks to recover [682]*682$1,651.17 for being compelled to perform again the work of rehabilitating and hanging the hearing room doors after he alleges such work had been done, ápproved and accepted; and, also the sum of $2,796.20, being the final payment due claimant and which he refused to accept because, he alleges, the acceptance thereof, under the agreement, constituted a release of the claims above. The State concedes that claimant is entitled to this last amount.

The agreement sets forth that the claimant was “ to furnish the material and perform the labor required and necessary for construction work for rehabilitation of existing room No. 202, for the executive department, as shown on the drawings or specified, at the Capitol, Albany, New York, in accordance with specification No. 17469, addendum No. 1 dated August 20, 1952, and addendum No. 2 dated August 29, 1952 ”.

The agreement is on a printed form with the blanks filled in on the typewriter; the general conditions are printed; the specifications are printed in part and mimeographed as to other parts which particularly apply to the work of this contract; and the addenda are mimeographed. The printed forms are in general use by the State for its construction contracts and the typewritten and mimeographed parts contain the matter particularly applicable to this contract.

As a part of the specifications there is included a mimeographed section 19A entitled “ Mill & Cabinetwork ” (it is not captioned Standard Specifications ”). It calls for the rehabilitation of the entire wood ceiling in room No. 202 and it sets forth the particulars as to inspections and repair of beams, moldings and panels, amongst others. Immediately following the foregoing is a mimeographed page dated August 20, 1952, entitled addendum No. 1, referring to an unrelated matter, and, then follow three mimeographed pages, dated August 29, 1952, entitled Addendum No. 2 to Specification No. 17469, construction work for rehabilitation of existing room No. 202 ”, and a note thereon states: ‘‘ this addendum shall be attached to and form a part of specification No. 17469. Addendum No. 1 shall remain in force ”; it then states it is section 19A ’’ and to ‘‘ Disregard the entire section 19A as contained in the specification and use the following in lieu thereof ”, and, it then omits completely that part of the original mimeographed specification numbered ‘section 19A ’’, referred to above, specifying the work on the wood ceiling. Furthermore, and immediately following the front cover of the contract, attention was again directed to the same addendum No. 1 and the same addendum No. 2 and there set forth in full. The contract drawings show [683]*683the detail of the wood ceiling as to beams, moldings and panels, amongst others, referred to in the original specification numbered section 19A.

The conflict between the parties was generated when the State called on the claimant to do the ceiling work and contended such work was not omitted from the new section 19A as set forth in addendum No. 2 and that it was a part of the work of the contract and embraced by the “ cabinet work ” and it pointed .to the drawings for the ceiling work as showing the intention that the work should be done; further, the State Architect asserted that pursuant to article 12, paragraph 50, of the general conditions, he had the power to decide the true meaning of the drawings or specifications on any point concerning the character, acceptability or nature of the several kinds of work or materials or construction thereof ”, whereupon he decided that the “ cabinet work on the ceiling ” had to be done and so informed the claimant.

The claimant, on the other hand, points out that while the ‘ ‘ wood ceiling ’ ’ work had been included in the original specifications, it had been removed by addendum No. 2, dated August 29,1952, which was also the date of the notice to bidders ,and was prior to the receipt by the State of bids on September 11,1952, and to the signing of the contract on October 2,1952; he disputes the assertion that cabinet work ” included the ceiling work; and he also refers to section 37 of article 68 of the printed general conditions which provides that where there is a discrepancy between the drawings and the specifications then the addenda are to be preferred in interpretation. A ‘‘ discrepancy ” exists ‘‘ where different parts of the same instrument or different instruments are in conflict with one another ” (Matter of Barrett, 209 App. Div. 217, 222).

When the specifications were made available to bidders, the original section 19A remained as a physical part thereof but the ‘‘ wood ceiling ’’ work had been eliminated by addendum No. 2 because all bidders were told to disregard “ the entire section 19A ’’; and, other changes were made which are not now material. Both the original section 19A and new section 19A referred to cabinet work ” (which was not defined), but, the “ cabinet work ” referred to in original section 19A excluded the ‘‘ wood ceiling ’’ because the latter was there treated separately and apart from the “ cabinet work ” and particular specifications were therein set up for the inspection, repair and refinishing of the ceiling. “ Cabinet work ” in new section 19A had no greater meaning than it had in the original; it did not refer to and did not embrace the “ wood ceiling ”.

[684]*684Where there is an uncertainty, conflict or ambiguity in an instrument, it is to be construed most strongly against the party who drew it ” and most favorably to the claimant and so as not “ to put one party at the mercy of the other ”, (Wilson & English Constr. Co. v. New York Central R. R. Co., 240 App. Div. 479, 483; Bintz v. City of Hornell, 268 App. Div. 742, 747, affd. 295 N. Y. 628.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

I. S. Joseph Co. v. Golde
185 F. Supp. 521 (D. Minnesota, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
2 Misc. 2d 680, 154 N.Y.S.2d 317, 1956 N.Y. Misc. LEXIS 1689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barash-v-state-nyclaimsct-1956.