Nix, Inc. v. City of Columbus

171 N.E.2d 197, 111 Ohio App. 133, 14 Ohio Op. 2d 44, 1959 Ohio App. LEXIS 682
CourtOhio Court of Appeals
DecidedDecember 1, 1959
Docket6243
StatusPublished
Cited by12 cases

This text of 171 N.E.2d 197 (Nix, Inc. v. City of Columbus) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nix, Inc. v. City of Columbus, 171 N.E.2d 197, 111 Ohio App. 133, 14 Ohio Op. 2d 44, 1959 Ohio App. LEXIS 682 (Ohio Ct. App. 1959).

Opinion

Wiseman, P. J.

This is an appeal on questions of law from a judgment of the Common Pleas Court of Franklin County sustaining a general demurrer to plaintiff’s petition and, the plaintiff electing not to plead further, dismissing the action.

*134 The plaintiff, appellant herein, Nix, Inc., hereinafter will be referred to as plaintiff, and the defendant, appellee herein, the city of Columbus, hereinafter will be referred to as the defendant.

The amended petition of the plaintiff consists of two causes of action. In the first cause of action plaintiff sued to recover $10,374.59 which it alleged was the balance due under a written contract, and in the second cause of action plaintiff sued to recover $94,068.80 for breach of contract. The defendant demurred to both causes of action on the ground that the facts alleged do not show a cause of action. The demurrer was sustained to both causes of action.

In the first cause of action plaintiff alleges that it entered into a written contract whereby plaintiff agreed to construct a bridge across Sunbury Road; that plaintiff completed the work under the contract and the engineers of the defendant certified that plaintiff had completed all the work in accordance with the terms of the contract; that under the contract the defendant was authorized to retain two per cent of the contract price for a period of one year subsequent to the date of the final acceptance of the work; that the defendant has paid 98 per cent of the contract price; that at the expiration of one year all the work was in good order; that defendant admits that it owes the 2 per cent reserved, to wit, $10,374.59 plus interest, but refuses to pay the same to the plaintiff, except on condition that the acceptance thereof shall operate as a full release of all claims which plaintiff may have against the defendant, including plaintiff’s claim for damages as set forth in the second cause of action; and that plaintiff is entitled to recover $10,374.59 plus interest.

In its second cause of action plaintiff alleges that the written contract, which is incorporated in the amended petition, made it the obligation of the defendant to acquire the land, referred to as the right of way, for the location of the bridge and road and the construction thereof; that the contract contained the certificate of the Director of the Department of Public Service of the defendant, certifying as follows: “I hereby certify that the additional right of way required for the relocation of this road has been provided by the city of Columbus, Ohio ’ ’; that defendant established December 31,1953, as the date when *135 the plaintiff was to begin work under the contract; that plaintiff was at all times ready and able to proceed with the work and to complete the contract within the 470 days provided by the terms of the contract; and that the defendant failed and neglected to make available the required right of way for the construction of said bridge and road on the date the defendant established as the beginning of said contract, or within a reasonable time thereafter. Plaintiff alleges that it notified the defendant at numerous times that the failure of the defendant to acquire the right of way was interfering with the progress of the work and would prevent the plaintiff from completing its work in the time specified in said contract; that by reason of the failure of the defendant to acquire the right of way the plaintiff was not only delayed for a period of over four months, but was caused to do certain work off-season, during the rainy season and resulting high water in the stream and required to do other work during severe winter weather, instead of during the summer months as contemplated by the plaintiff; and that as a consequence the plaintiff was put to extra expense in the performance and completion of the contract. Plaintiff alleges that the contract completion date was April 6, 1955; that on April 7, 1955, the defendant granted the plaintiff a time extension of 156 days, and on January 20, 1956, the defendant extended the completion date 218 days, to April 15, 1956; and that but for the failure of the defendant to acquire the right of way the work would have been completed within the 470 days as agreed to in the contract, but, because of .such failure and neglect of the defendant, the plaintiff was prevented from completing the contract before February 29,1956. Plaintiff alleges it has presented to the defendant a detailed written statement of its claim, and requested payment, but defendant has not responded. Plaintiff alleges further that:

“Sections D-1.07, 1.15 and 1.21 of the specifications incorporated herein by reference are not applicable to the claims set forth in this cause of action for the reason that such damages were not in the minds or contemplation of the parties when the agreement was executed since the agreement itself was based on the. assumption by both parties that the complete right-of-way had been secured; that the language of said sections does not *136 cover the factual situation herein set forth; and that the defendant cannot rely on said sections, after breaching a fundamental obligation of the contract. ’ ’

Plaintiff sets forth an itemization of its claim for damages in the sum of $94,068.80, for which amount it prays judgment.

The errors assigned by plaintiff are: Error in sustaining the demurrer to the first and second causes of action, and error in dismissing the action.

In the first cause of action plaintiff alleges that it has completed the work according to the terms of the contract; that the \fork has been accepted by the defendant; and that the 2 per cent of the contract price which was retained by the defendant for a period of one year after the completion of work is now due the plaintiff, but that the defendant refuses to pay said amount except on condition that the acceptance thereof by the plaintiff operate as a complete release from all liability of the defendant to the plaintiff, including the claim for damages set up in the second cause of action.

We are required to examine the contract to determine their rights. Section D-1.37, in addition to the provision for payment of the 2 per cent after the expiration of one year, provides as follows:

“The acceptance by the contractor of such final payment shall operate as and shall be a release to the city, and all officers or agents thereof, from all claim and liability to the contractor for any reason whatsoever.”

The rationale of the ruling of the trial court is that, since the'plaintiff was suing on the contract, it was legally bound by the provisions of the contract; that, by reason of the above-quoted provision in the contract, the acceptance of the final payment operates as a release of all claims for damages; and that by the terms of the contract the plaintiff is not entitled to receive final payment without thereby releasing the defendant from all claims of the plaintiff “for any reason whatsoever.” The court held that, since plaintiff did not allege that the defendant refused to make the final payment pursuant to the terms of the contract, no cause of action is alleged, citing Raudebaugh v. Hart, 61 Ohio St., 73, 55 N. E., 214, the third paragraph of the syllabus reading as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Highway Administration v. Greiner Engineering Sciences, Inc.
577 A.2d 363 (Court of Special Appeals of Maryland, 1990)
Earthbank Co. v. City of New York
145 Misc. 2d 937 (New York Supreme Court, 1989)
Carrabine Construction Co. v. Chrysler Realty Corp.
495 N.E.2d 952 (Ohio Supreme Court, 1986)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Ace Stone, Inc. v. Township of Wayne
221 A.2d 515 (Supreme Court of New Jersey, 1966)
Hawley v. Orange County Flood Control District
211 Cal. App. 2d 708 (California Court of Appeal, 1963)
Mills v. Larrance
120 Ill. App. 83 (Appellate Court of Illinois, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
171 N.E.2d 197, 111 Ohio App. 133, 14 Ohio Op. 2d 44, 1959 Ohio App. LEXIS 682, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nix-inc-v-city-of-columbus-ohioctapp-1959.