B.I. Chipping Company v. R.F. Scurlock Co, Unpublished Decision (12-20-2005)

2005 Ohio 6748
CourtOhio Court of Appeals
DecidedDecember 20, 2005
DocketNo. 04AP-1219.
StatusUnpublished
Cited by1 cases

This text of 2005 Ohio 6748 (B.I. Chipping Company v. R.F. Scurlock Co, Unpublished Decision (12-20-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B.I. Chipping Company v. R.F. Scurlock Co, Unpublished Decision (12-20-2005), 2005 Ohio 6748 (Ohio Ct. App. 2005).

Opinion

OPINION
{¶ 1} Plaintiff-appellant, B.I. Chipping Co. ("appellant"), appeals from a judgment of the Franklin County Court of Common Pleas in which that court granted summary judgment in favor of defendant-appellee, R.F. Scurlock Co. ("appellee") on appellant's claims.

{¶ 2} This matter arises out of an April 2, 2001 contract between the two parties ("the contract"), which provided that appellant would perform the clearing and grubbing of trees and underbrush along a portion of U.S. Route 50 in Vinton County, Ohio. The contract was part of a larger undertaking to realign that particular section of the highway, which appellee was obligated to accomplish pursuant to a separate contract with the Ohio Department of Transportation ("ODOT"). The stated contract price for appellant's portion of the work was $86,000.

{¶ 3} The specifications for purposes of bidding represented that aerial utility lines owned by American Electric Power and Verizon would be relocated by March 14, 2001, before work was to begin. The contract contained several other pertinent provisions. Section 3 provides:

The Subcontractor shall be bound to the Contractor by the terms and conditions of all documents forming a part of the Principal Contract, and to assume toward the Contractor all the obligations and responsibilities that the Contractor assumes in and by the Principal Contract toward the Owner, insofar as they are applicable to this particular Subcontract * * *.

{¶ 4} Section 8 provides:

The Contractor shall not be responsible to the Subcontractor for any loss, damage or delay of any nature caused by the Owner or Contractor or any other subcontractor or materialman other than for such amounts as the Owner or such other subcontractor or materialman shall be liable to and shall pay to the Contractor, including any amounts found due under any disputes clause of the Principal Contract. In any case of any dispute between the Subcontractor and the Contractor involving the Owner, Subcontractor agrees to be bound to the Contractor to the same extent that the Contractor is bound to the Owner by the terms of the Principal Contract and by any and all decisions or determinations made thereunder by the party or board so authorized in the Principal Contract or by any court of competent jurisdiction whether or not the Subcontractor is a party to such proceeding. The Contractor agrees to the Owner all Subcontractor's claims (submitted in writing by the Subcontractor to the Contractor) involving the Owner whenever the Contractor is permitted to do so by the terms of the Principal Contract and to further invoke, on behalf of the Subcontractor, those provisions in the Principal contract for determining disputes.

{¶ 5} Section 14 provides:

The Subcontractor agrees to perform and coordinate his work with that of the Contractor and other subcontractors to the best interests of the work as a whole, as determined by Contractor, and shall have no claim for extra compensation on account of delays, interference or hindrance caused by the Contractor or other subcontractors in the performance of their respective items of work.

{¶ 6} It is undisputed that when appellant arrived on site to begin work, Verizon's aerial utility lines had not been removed or relocated. It is also undisputed that Verizon was obligated, through an agreement with ODOT, to remove or relocate the lines during construction. Appellant began work nonetheless, but incurred expenses beyond those originally forecast for cost items such as extra labor and equipment rental. According to appellant, its anticipated costs for the project had doubled by the time the project was complete. Appellant claims that appellee directed its work, including directing appellant to demobilize and remobilize at various points along the work route because of interference from the utility lines. Appellee claims that appellant knew, prior to commencing work, that the utility lines had not been relocated, and simply made a business decision to complete the work anyway.

{¶ 7} After completion of the project, in February 2002, appellee sent a claim package to ODOT, in which it requested additional compensation for the increased costs incurred by both appellant and appellee due to Verizon's failure to relocate its utility lines. ODOT indicated that it viewed the claim as meritless, but ultimately agreed to settle the claim for $25,000. Shortly thereafter, appellant wrote a letter to appellee in which appellant advised that appellee possessed no authority to settle appellant's claims on appellant's behalf, and insisted that, "we will not be bound by any settlement that Scurlock agrees upon with ODOT."

{¶ 8} Upon its receipt of the $25,000 settlement from ODOT, appellee forwarded $10,000 of the funds to appellant, but appellant refused to accept the check. Appellee requested that ODOT reopen the claim for cost increases, whereupon appellant presented its claim directly to ODOT. ODOT determined that appellant was not entitled to any additional compensation.

{¶ 9} On October 22, 2002, appellant commenced this action against appellee, asserting claims for breach of contract, unjust enrichment, and breach of an implied warranty to provide a site free from obstructive utility lines. Appellant sought total damages in the amount of $88,876.22. Both parties moved for summary judgment. The trial court denied appellant's motion and granted appellee's motion.

{¶ 10} The court found that Sections 8 and 14 of the contract precluded appellant's claim for its delay-related damages. The court rejected appellant's arguments that these provisions were unenforceable pursuant to R.C. 4113.62(C), which provides:

(1) Any provision of a construction contract, agreement, or understanding, or specification or other documentation that is made a part of a construction contract, agreement, or understanding, that waives or precludes liability for delay during the course of a construction contract when the cause of the delay is a proximate result of the owner's act or failure to act, or that waives any other remedy for a construction contract when the cause of the delay is a proximate result of the owner's act or failure to act, is void and unenforceable as against public policy.

(2) Any provision of a construction subcontract, agreement, or understanding, or specification or other documentation that is made part of a construction subcontract, agreement, or understanding, that waives or precludes liability for delay during the course of a construction subcontract when the cause of the delay is a proximate result of the owner's or contractor's act or failure to act, or that waives any other remedy for a construction subcontract when the cause of the delay is a proximate result of the owner's or contractor's act or failure to act, is void and unenforceable as against public policy.

{¶ 11} The trial court found that because the contract allows appellant to recover for delays in the amount that appellee receives through the ODOT claims process, and thus does not preclude all liability for delays, R.C. 4113.62(C) does not apply and does not render any provision of the contract unenforceable.

{¶ 12} The trial court also rejected appellant's argument that, even if the delay-related clauses are enforceable, they cannot be enforced in this particular instance because the parties did not contemplate the cause of the delay at the time of contracting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kahler v. Eytcheson
2012 Ohio 208 (Ohio Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 6748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bi-chipping-company-v-rf-scurlock-co-unpublished-decision-ohioctapp-2005.