Pitt Const. Co. v. City of Dayton

237 F. 305, 151 C.C.A. 11, 1916 U.S. App. LEXIS 1960
CourtCourt of Appeals for the Sixth Circuit
DecidedNovember 16, 1916
DocketNo. 2798
StatusPublished
Cited by11 cases

This text of 237 F. 305 (Pitt Const. Co. v. City of Dayton) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pitt Const. Co. v. City of Dayton, 237 F. 305, 151 C.C.A. 11, 1916 U.S. App. LEXIS 1960 (6th Cir. 1916).

Opinion

WARRINGTON, Circuit Judge.

The Pitt Construction Company, a Pennsylvania corporation, and the city of Dayton, state of Ohio, entered into a written contract, September 16, 1912, for an extension and improvement of the waterworks system of Dayton. The Construction Company was to furnish the material and perform the labor in constructing a line of cast-iron water pipe, with proper connections, along a particular course between the pumping station and the reservoir of the city, including standpipe foundations, according to specifications, plans, and drawings, and for prices attached to the several items as stated in the accepted proposal. In consideration of this the city undertook to furnish the right of way for the improvement, and also to pay the prices named for such material and labor. The improvement was completed to the satisfaction of the city, and was paid for according to prices named, and provided for in the contract; and those features of the contract are not involved in the present controversy.

In the suit below it was sought to recover damages for alleged delay and neglect of the city in furnishing a right of way for a substantial portion of the improvement. The items of damage so alleged are as follows:

(1) Increase in cost of excavation from 72 cents to $1.12 per lineal foot, amounting to $2,168.

(2) Increase in cost of laying pipes from 15 cents to 25 cents per lineal foot, amounting to $542.

(3) Cost of pumping water from the trenches, which would not have been required if such delay and neglect had not occurred, amounting to $2,072.48; cost of supplies required for such pumping, $1,404.17; cost of new pumping equipment, $358.97.

(4) Increase in cost of labor in the sum of $1,396.99.

(5) Cost and expense incurred in management of the business and in keeping the equipment and organization at Dayton instead of elsewhere, in the sum of $4,050.

(6) Cost of moving machinery and appliances from one portion of the improvement to another portion, which but for such delay and neglect would have been unnecessary, $138.60.

(7) A profit of 10 per cent, upon the item of labor and that of pumping, amounting to $346.30.

The alleged consequences of such delay and neglect, as respects the items of damage so claimed, will be better understood through further statement of the terms of the contract and the extent of the delay complained "of. The contract required the contractor to commence the work within 30 days after its date, September 16, 1912, and to complete the [307]*307improvement by June 1, 1913; and failure in this behalf in terms rendered the contractor liable for wages of inspectors at the rate of $3 a day for each, and for the further sum of $25 a day, not as a penalty, but as liquidated damages, and such sums were to be deducted from moneys accruing to the contractor. The contractor, under direction of the city, placed its equipment in position to commence work Sep-, tember 30, 1912, upon what was known as “Station 53” in the proposed line of improvement, but was on that day prevented from proceeding with the work by an order of injunction issued against the city and the contractor alike, in a suit commenced by Joseph E. Bimm in the Montgomery common pleas court.- It developed that the city did not own a right of way for such an improvement as this along the line of Station 53. This resulted in an order on the part of the city, directing the contractor to remove its equipment to another portion of the line, and along which the city owned the right of way. The contractor carried out this order, and there commenced the work. December 19, 1912, the city instituted a proceeding in the Montgomery county probate court to appropriate the right of way through the land in which Bimm claimed an interest; on February 19, 1913, the value of the interest taken and the damage to the residue were assessed at $9,841; and on May 19th final judgment was entered. The judgment, however, was not paid until the following July 2d, a month succeeding the expiration of the period within which the contractor was to complete the improvement. The city’s delay in so acquiring the right of way is alleged to have prevented completion of the improvement until December 22, 1913.

The. city met these allegations by answer' containing ten separate defenses. In its first defense the city set up the written contract above pointed out, admitting, however, prevention from doing the portion of the work which was embraced in the injunction suit of Bimm, that on December 19, 1912, it commenced proceedings to appropriate that portion of the right of way, and that on July 2, 1913, it paid the money assessed therefor, but denying generally all other allegations of the petition. The first defense was pleaded by reference thereto in each of the succeeding defenses; but those defenses each contain additional matter. The second defense alleges that the cost of removing the contractor’s equipment from Station 53 to another portion of the work was agreed by the parties to have been the only effect of the injunction, and that such expense was paid in full settlement of all claims arising in that behalf. The third defense alleges that when plaintiff resumed work on the portion of the improvement east of Station 53, it complained of an excess of water in the trench, of losses on account of the delay caused by the city, extra work, high prices of labor, etc., and that these claims were thereupon settled and discharged by an arrangement for changing to the advantage of the contractor the grade along which the pipes were to be laid, and that this arrangement was carried out. The fourth, fifth, sixth, and seventh defenses set up, respectively and in the following order, certain provisions of sections 21, 34, 33, and 31 of the contract, and so present questions of law rather than of fact. These questions will, so far as necessary, be con[308]*308sidered later. The eighth defense denies certain allegations contained in the petition, to the effect that the city, through its officers, had falsely represented to the plaintiff that it had secured the right of way for the improvement, and had so induced plaintiff to enter into the contract, and thereupon avers that the city had, for a consideration, secured the right of way in dispute from a railroad company, and that the. city solicitor had advised the city that Bimm (plaintiff in the injunction suit mentioned) had no valid claim against it in respect of such right of way. The ninth defense, in effect, alleges as a bar to recovery the total payment made and received under and according to the contract, and, further, that plaintiff’s losses were due “to natural conditions attending the work, the incompetency of plaintiff’s employés and the flood of March 25, 1913,” and for which defendant denies responsibility. The tenth defense, in substance, recites the city’s right in terms reserved in the contract to recover of plaintiff the wages paid to inspectors, and also the penalty of $25 a day during the contractor’s delay in completing the improvement, amounting in all to $5,000, and alleges that it was agreed between the parties that the city’s waiver of this sum, together with its payment of the other sums mentioned in the answer, should be and were accepted in full discharge of all claims of every kind and character. The issues were closed by plaintiff’s reply.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Ace Stone, Inc. v. Township of Wayne
221 A.2d 515 (Supreme Court of New Jersey, 1966)
Nix, Inc. v. City of Columbus
171 N.E.2d 197 (Ohio Court of Appeals, 1959)
Housing Authority of City of Dallas v. Hubbell
325 S.W.2d 880 (Court of Appeals of Texas, 1959)
Grand Trunk Western R. Co. v. HW Nelson Co.
116 F.2d 823 (Sixth Circuit, 1941)
City of Dallas v. Shortall
87 S.W.2d 844 (Court of Appeals of Texas, 1935)
Henry Shenk Co. v. Erie County
178 A. 662 (Supreme Court of Pennsylvania, 1935)
E. De Voe Tompkins, Inc. v. City of Bridgeport
123 A. 135 (Supreme Court of Connecticut, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
237 F. 305, 151 C.C.A. 11, 1916 U.S. App. LEXIS 1960, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pitt-const-co-v-city-of-dayton-ca6-1916.