Pitt Const. Co. v. City of Dayton

237 F. 305, 151 C.C.A. 11, 1916 U.S. App. LEXIS 1960
Court of Appeals for the Sixth Circuit·Decided November 16, 1916·No. No. 2798·Published·Cited by 11 cases

Opinion

WARRINGTON, Circuit Judge.

The Pitt Construction Company, a Pennsylvania corporation, and the city of Dayton, state of Ohio, entered into a written contract, September 16, 1912, for an extension and improvement of the waterworks system of Dayton. The Construction Company was to furnish the material and perform the labor in constructing a line of cast-iron water pipe, with proper connections, along a particular course between the pumping station and the reservoir of the city, including standpipe foundations, according to specifications, plans, and drawings, and for prices attached to the several items as stated in the accepted proposal. In consideration of this the city undertook to furnish the right of way for the improvement, and also to pay the prices named for such material and labor. The improvement was completed to the satisfaction of the city, and was paid for according to prices named, and provided for in the contract; and those features of the contract are not involved in the present controversy.

In the suit below it was sought to recover damages for alleged delay and neglect of the city in furnishing a right of way for a substantial portion of the improvement. The items of damage so alleged are as follows:

(1) Increase in cost of excavation from 72 cents to $1.12 per lineal foot, amounting to $2,168.

(2) Increase in cost of laying pipes from 15 cents to 25 cents per lineal foot, amounting to $542.

(3) Cost of pumping water from the trenches, which would not have been required if such delay and neglect had not occurred, amounting to $2,072.48; cost of supplies required for such pumping, $1,404.17; cost of new pumping equipment, $358.97.

(4) Increase in cost of labor in the sum of $1,396.99.

(5) Cost and expense incurred in management of the business and in keeping the equipment and organization at Dayton instead of elsewhere, in the sum of $4,050.

(6) Cost of moving machinery and appliances from one portion of the improvement to another portion, which but for such delay and neglect would have been unnecessary, $138.60.

(7) A profit of 10 per cent, upon the item of labor and that of pumping, amounting to $346.30.

The alleged consequences of such delay and neglect, as respects the items of damage so claimed, will be better understood through further statement of the terms of the contract and the extent of the delay complained "of. The contract required the contractor to commence the work within 30 days after its date, September 16, 1912, and to complete the [307] improvement by June 1, 1913; and failure in this behalf in terms rendered the contractor liable for wages of inspectors at the rate of $3 a day for each, and for the further sum of $25 a day, not as a penalty, but as liquidated damages, and such sums were to be deducted from moneys accruing to the contractor. The contractor, under direction of the city, placed its equipment in position to commence work Sep-, tember 30, 1912, upon what was known as “Station 53” in the proposed line of improvement, but was on that day prevented from proceeding with the work by an order of injunction issued against the city and the contractor alike, in a suit commenced by Joseph E. Bimm in the Montgomery common pleas court.- It developed that the city did not own a right of way for such an improvement as this along the line of Station 53. This resulted in an order on the part of the city, directing the contractor to remove its equipment to another portion of the line, and along which the city owned the right of way. The contractor carried out this order, and there commenced the work. December 19, 1912, the city instituted a proceeding in the Montgomery county probate court to appropriate the right of way through the land in which Bimm claimed an interest; on February 19, 1913, the value of the interest taken and the damage to the residue were assessed at $9,841; and on May 19th final judgment was entered. The judgment, however, was not paid until the following July 2d, a month succeeding the expiration of the period within which the contractor was to complete the improvement. The city’s delay in so acquiring the right of way is alleged to have prevented completion of the improvement until December 22, 1913.

Free access — add to your briefcase to read the full text and ask questions with AI

Pitt Const. Co. v. City of Dayton, 237 F. 305, 151 C.C.A. 11, 1916 U.S. App. LEXIS 1960 (6th Cir. 1916).

237 F. 305 (Pitt Const. Co. v. City of Dayton) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Ace Stone, Inc. v. Township of Wayne
221 A.2d 515 (Supreme Court of New Jersey, 1966)
Nix, Inc. v. City of Columbus
171 N.E.2d 197 (Ohio Court of Appeals, 1959)
Housing Authority of City of Dallas v. Hubbell
325 S.W.2d 880 (Court of Appeals of Texas, 1959)
Grand Trunk Western R. Co. v. HW Nelson Co.
116 F.2d 823 (Sixth Circuit, 1941)
City of Dallas v. Shortall
87 S.W.2d 844 (Court of Appeals of Texas, 1935)
Henry Shenk Co. v. Erie County
178 A. 662 (Supreme Court of Pennsylvania, 1935)
E. De Voe Tompkins, Inc. v. City of Bridgeport
123 A. 135 (Supreme Court of Connecticut, 1923)