J. F. O'Connor & Co. v. Smith & Gething

19 S.W. 168, 84 Tex. 232
CourtTexas Supreme Court
DecidedMarch 11, 1892
DocketNo. 3149.
StatusPublished
Cited by12 cases

This text of 19 S.W. 168 (J. F. O'Connor & Co. v. Smith & Gething) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. F. O'Connor & Co. v. Smith & Gething, 19 S.W. 168, 84 Tex. 232 (Tex. 1892).

Opinion

HENRY, Associate Justice.

— This suit was brought to recover damages by the appellees.

Plaintiffs’ petition charged, that J. F. O’Connor & Co. had, prior to the 1st day of September, 1886, contracted with the Dallas & Green-ville Eailway Company to grade and repair its roadbed for laying its track between the cities of Greenville and Dallas, and that on said date said defendants contracted to sublet to plaintiffs the forty-second, forty-fifth, forty-sixth, and forty-seventh miles of said work, for which defendants agreed to pay plaintiffs 115 cents per cubic yard; that defendants contracted and undertook that plaintiffs should be allowed to do said work in accordance with the usage and custom prevailing in railway construction, and that defendants would cause to them no unnecessary delay or hindrance in the performance of said work; that the usage and custom then prevailing in said business was, that such work as plaintiffs had contracted to do was required to be done ac *235 cording to certain measurements and directions made and given by the railway company’s engineer, which were known in such business as “cross-sectioning;” that it was by custom and usage the duty of the chief contractor to have this engineering work done in such time as not unreasonably to delay the subcontractor; that the contract between plaintiffs and defendants was made with reference to said custom, which thereby became a part of it; and also that defendants specially and expressly undertook and agreed to have said cross-sectioning done as aforesaid, but that they failed to perform their said contract, and did not procure said cross-sectioning to be done promptly, so that plaintiffs were unreasonably and unnecessarily delayed during the periods named in plaintiffs’ petition, aggregating twenty-five days, by which delays plaintiffs were damaged as follows: By hire of teams and wages of men paid by them during said period of delay, $2110.50; reasonable value of gains lost during periods of delay aforesaid, $2000. Plaintiffs likewise allege, that defendants further broke their said contract by refusing to allow them to perform the work agreed to be done on the forty-second mile, and let the same to another; that they could have performed said work for 10 cents per cubic yard; that there were 20,000 cubic yards in said mile, on which they would have made a profit of 15 cents per cubic yard; that by reason of this breach of the contract they were damaged $300.

Defendants answered said petition with a general denial, plea of settlement and receipt in full, and set up the construction contract between defendants and the railway company; and averred, that under said contract defendants had agreed to construct said railway in accordance with the plans and directions of the company’s engineer; that it was the universal custom in railway construction that the railway should be constructed under the supervision and in accordance with the directions of the railway company’s engineer, who was the agent of the company, paid and controlled by it; and wholly beyond the control of the contractor; that there was no custom allowing the subcontractor to look to the chief contractor for any damage done him by delays arising out of the conduct or directions of the engineer, and that plaintiffs were fully advised of the terms of aforesaid contract and said custom at and before the time they entered into said subcontract. Defendants further pleaded, that if plaintiffs had been delayed and thereby damaged as alleged, that the same was through no fault of theirs and was the breach of no contract by them made with plaintiffs, but was the fault of the Dallas & Greenville Bailway Company, and asked that said company be made a party and required to answer, and that defendants have judgment over against said company for any damages that plaintiffs might recover against them by reason of aforesaid delays.

*236 Plaintiffs replied to defendants’ answer by supplemental petition, and alleged that the receipt given by them to defendants was not intended to cover their demand for damages asserted in this case, and as to said demand was without consideration.

The railway company appeared and pleaded a general denial of all the allegations of both plaintiffs and defendants, a release of and bond of indemnity against defendants’ claim over against it, statute of limitation, certain provisions of the construction contract between defendants and the railway' company, which it was alleged precluded defendants from recovering over against said company; and further, that plaintiffs could have obtained ample work outside of their contract during the periods of alleged delay, and thereby prevented the damages, if any, occasioned by said delays.

Defendants replied to aforesaid pleading of the railway company, alleging that said company had waived the requirement of the construction contract that no work should be sublet without the consent, in writing, of the railway company’s engineer, and that said company was estopped from setting up the same; and in the third clause of said reply defendants pleaded, that the bond of indemnity set up by said railway company did not in terms cover the cause of action sued upon; and that if its language did cover said cause of action it was not intended so to do, and was not one of the claims or causes of action intended to be released or indemnified against; and that said company so understood it, and recognized, up to June, 1890, when it filed its amended pleading herein, its liability to defendants for any damage plaintiffs might recover against them on account of the delays complained of by plaintiffs. Defendants also pleaded a general denial.

The case was tried November 22, 1890, and resulted in a verdict in favor of the railway company against defendants, and in favor of plaintiffs against defendants O’Connor & Co. for $1000, whereon the court entered judgment in favor of plaintiffs against J. F. O’Connor So Co. for $1000 and costs, and that said railway company go hence without day and recover of said O’Connor So Co. its costs.

Plaintiffs’ damage, as itemized in their pleading, consisted of the hire of teams and men which they were obliged to keep and pay during the several periods of delay, aggregating $2110.60; reasonable value of earnings lost during said periods, $2000; and profits lost on the forty-second mile by refusal of defendants to allow plaintiffs to do the work, $300. Total damage claimed, $4410.

E. E.- Smith, one of the plaintiffs, testified to the various delays and the number of men that plaintiffs had on hand during each period of delay and the wages paid them; to the number of teams plaintiffs had on hand during said periods of delay, which teams he stated they owned, but could have hired for $3 per day. He also testified to the value of his own services, which he put at $100 per month, and the *237 profits lost by not being allowed to grade the forty-second mile, which profits he put at $225. Plaintiffs did all the work contracted for except the forty-second mile, and that was sublet when plaintiffs got upon the ground.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
19 S.W. 168, 84 Tex. 232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-f-oconnor-co-v-smith-gething-tex-1892.