City of Dallas v. Shortall

87 S.W.2d 844
CourtCourt of Appeals of Texas
DecidedOctober 5, 1935
DocketNo. 11751.
StatusPublished
Cited by10 cases

This text of 87 S.W.2d 844 (City of Dallas v. Shortall) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Dallas v. Shortall, 87 S.W.2d 844 (Tex. Ct. App. 1935).

Opinions

In a suit in a district court of Dallas county by appellee, Thomas H. Shortall, against appellant, city of Dallas, a municipal corporation, as defendant, appellee recovered damages in the sum of $29,803.96; $4,803.21 of this sum being accrued interest at the time the judgment was entered on October 14, 1933. The judgment represents the amount appellee claimed to be due him as damages over and above what appellant claims was due under the construction contract. Appellant has duly perfected an appeal to this court, and the following are the necessary facts:

On March 18, 1930, appellant entered into a contract with Henry C. Beck, contracting under his trade-name of Central Contracting Company, to construct a tunnel through a hill or ridge to divert the waters of Kidd Springs branch into Coombes creek. These two streams are approximately parallel with each other, and are separated by the hill or ridge through which the tunnel was to be excavated. The highest surface of the ridge is approximately 85 feet above the tunnel.

The engineering department of the city of Dallas prepared very elaborate plans and specifications and accompanied same by maps, profiles, and drawings upon which bidders were required to make their estimates of the costs of a finished construction; the bidders were required to furnish two bids, one on the basis of "gunite" construction, and the other on the basis of a concrete construction; the latter being a much heavier and more costly construction. The "gunite" or lighter construction could only be used, provided the tunnel was excavated through solid rock; otherwise, the only practical construction would be the heavier and more costly concrete construction.

Appellant's engineering department, after it had located the course of the tunnel, made what purported to be a survey of the formation to be encountered in excavating the tunnel. This survey determined the formation to be encountered by boring from the surface, making such borings at a distance from each other of from 50 to 100 feet throughout the length of the tunnel. These borings established the fact that rock formation would be encountered at a relatively short distance, from the surface from which the engineers concluded that the tunnel, throughout the greater portion of its length, would be excavated through a solid rock formation, and indicated such formation on the map, accompanying the plans and specifications, as a part of same, by a white line, that the construction would be through rock formation.

The bidders were requested to submit bids on both the "gunite" and the concrete construction. The bid of the Central Contracting Company was accepted by appellant as the lowest bid on each character of construction, and Henry C. Beck, trading as Central Contracting Company, was awarded the contract for the "gunite" construction; both parties accepting as true the fact that the tunnel would be excavated through solid rock formation, as shown by the survey made by appellant's engineers, and the contract in question was entered into. Before work was begun, and without notice to appellant, Beck, through his trade-name of Central Contracting Company, sublet or assigned the entire construction work called for by the contract to appellee, Thomas H. Shortall. By this agreement between appellee and Beck, appellee was to do the entire work and was to receive the entire consideration under the contract, but was to pay to Beck 10 per cent. of the amount received. No written notice was served on appellant of this agreement, and no formal permission was given by appellant to permit such an agreement to be entered into.

Appellee took charge of and completed the entire construction. The monthly estimates were made in the name of the Central Contracting Company, and vouchers issued to such company, as payee. Representatives of appellant's engineering department, to which department was committed supervision of the construction, were present at all times during the construction of this tunnel, and knew from the beginning that appellee was doing the entire work. At a meeting of the city commissioners, at which three of the five were present, appellee appeared before them as the person doing the work.

The contract is very lengthy, and a large portion of it is not necessary to be given for an understanding of the issues involved on this appeal. Those parts of the contract necessary to a disposition of the case will either be given in substance or copied in hæc verba. The contract declares that the contractor shall, "At its own cost and expense furnish all tools, labor, materials, machinery, appliances, equipment *Page 846 appurtenances and supplies necessary for the construction and performance of the work herein contracted to be done, and to do, and perform all the necessary work in the construction, installation and building in every detail of a branch tunnel in District No. 24 for the City of Dallas to be located and constructed in the County of Dallas, State of Texas, as follows: From Kidd Springs Branch to Coombes Creek Retention Basin and to do all the necessary excavation therefor in strict accordance and compliance with the plans, specifications, profiles and maps and drawings prepared by the city engineers, and to fully complete and construct said work in strict accordance with the true purpose and design of said profiles, plans and drawings, specifications and in accordance with the proposal of the said contractor."

Section 7, in effect, provides that the contractor shall not be entitled to any claim for damages for any hindrance or delay, for any cause whatever, in the progress of the work; but that such contractor may have an extension of time for completing the contract when the hindrance or delay resulted "from any cause entirely beyond the control of the contractor."

By section 12, the city engineer is given the power to make alterations in the line, grade, plan, form, or quantity of the work herein contemplated; and if such alterations diminished the quantity of work to be done, such alteration shall not constitute a claim for damages, or for anticipated profits on the work dispensed with. If, however, the alterations increased the amount of work, such increase shall be paid for according to the quantity actually done, and according to the price or prices stipulated for such work, or similar work, in this contract.

Section 14 forbids the contractor to transfer, sublet, or assign the contract, or to sublet any part of the work, except for delivery of material, or to in any way abridge the terms of the contract and the specifications, "without first obtaining the consent of the City of Dallas expressed by a resolution of the Board of Commissioners, and upon such conditions as may be prescribed by the said Commissioners." A like prohibition extends to the assignment of the moneys payable or arising under this contract, without first obtaining the consent of the board of commissioners.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gust K. Newberg, Inc. v. Illinois State Toll Highway Authority
506 N.E.2d 658 (Appellate Court of Illinois, 1987)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Franklin Contracting Co. v. State
338 A.2d 875 (New Jersey Superior Court App Division, 1975)
Grant Construction Co. v. Burns
443 P.2d 1005 (Idaho Supreme Court, 1968)
Ace Stone, Inc. v. Township of Wayne
221 A.2d 515 (Supreme Court of New Jersey, 1966)
Nix, Inc. v. City of Columbus
171 N.E.2d 197 (Ohio Court of Appeals, 1959)
Housing Authority of City of Dallas v. Hubbell
325 S.W.2d 880 (Court of Appeals of Texas, 1959)
City of Houston v. Scanlan
164 S.W.2d 760 (Court of Appeals of Texas, 1942)
Powell v. State
118 S.W.2d 960 (Court of Appeals of Texas, 1938)
City of Dallas v. Shortall
114 S.W.2d 536 (Texas Supreme Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
87 S.W.2d 844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-dallas-v-shortall-texapp-1935.