Powell v. State

118 S.W.2d 960, 1938 Tex. App. LEXIS 68
CourtCourt of Appeals of Texas
DecidedApril 6, 1938
DocketNo. 8271.
StatusPublished
Cited by8 cases

This text of 118 S.W.2d 960 (Powell v. State) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Powell v. State, 118 S.W.2d 960, 1938 Tex. App. LEXIS 68 (Tex. Ct. App. 1938).

Opinion

BAUGH, Justice.

Appeal is from a judgment based upon an instructed verdict in favor of the State in a suit brought by Powell against the State under permission to do so granted by the Legislature. The suit was for extra compensation by way of damages growing out of a contract between Powell and the Highway Commission for construction of 12.8S5 miles of highway in Gillespie County. The contract provided for several undertakings, but the only one here involved relates to the excavation work done on said project. The following material facts are not controverted:

The project was originally advertised by the Highway Commission as what is termed a “classified” project, on which bids were to be opened at 10 a. m., December 1, 1930. In the notice sent to bidders the “approximate quantities” of materials to be removed were stated to be -53,585 cubic yards of common roadway excavation and 17,412 cubic yards of solid rock, with the further information to bidders that “Detailed plans and specifications of the work may be seen for examination, and information may be obtained at the office of E. B. Calvin, Resident Engineer, Fredericksburg, Texas, and at the office of the State Highway Dept.”

Subsequent to such advertisement for bids, the Highway Commission changed the project from a “classified” to an “unclassified” job, and appellant was so notified only a few days before the bids were to be opened, and not in time for him to make a full investigation himself of the terrain over which the contract was to be let and ascertain for himself the quantity of rock beneath the surface which might be encountered. He did, however, send his foreman to the site of the project who made a hurried examination of it, discussed the matter with Calvin at Fredericksburg, who told him that the Highway Department had made soundings and borings on the route; that he thought the quantities of materials as shown in the notices were approximately correct and that they could be relied upon as a basis for a bid on an “unclassified” project.

Upon completion of the project it was found that these estimates were incorrect; and that appellant had to remove 36,474 cubic yards of rock instead of the 17,412 stated in. the notices for bids; and only 33,930 cubic yards of common earth instead of 53,585 as indicated in such notices. All the plans, specifications, maps, profile sheets, etc., on which bids were asked were attached to and made a part of the contract executed by Powell, as well as the “blank proposal sheet” on which Powell was awarded such contract,. and on which he made his bid to remove the entire 70,997 cubic yards of “unclassified roadway excavation” at 35 cents per cubic yard.

It is the contention of appellant that in view of all these facts and circumstances, and of the fact the notices showing the separate quantities of rock and common soil to be excavated, same being first advertised as a “classified” project, were attached to and made a part of the contract subsequently let as an “unclassified” proj ect, there was a representation and a warranty by the State upon which he relied that the materials in the quantities indicated only would be encountered. That such was what he contracted for and that the additional rock encountered was extra work, beyond the provisions of his contract for which he was entitled to be paid. In support of this contention appellant relies in large measure on the case of Maney v. Oklahoma City, 150 Okl. 77, 300 P. 642, 76 A.L.R. 258, and annotated cases thereunder on pages 268-278. The rule announced in that case was followed in a majority opinion by the Dallas Court of Civil Appeals in City of Dallas v. Shortall, 87 S.W.2d 844. That rule as summarized *962 by the annotator under the Maney Case is “The general rule may be deduced from the decisions that where plans or specifications lead a public contractor reasonably to believe that conditions indicated therein exist, and "may be relied upon in making his bid, he will be entitled to compensation for extra work or expense made necessary by conditions being other than as so represented.” This rule was deduced from the decisions of the Supreme Court of the United States in contracts made with the United States. Hollerbach v. United States, 233 U.S. 165, 34 S.Ct. 553, 58 L.Ed. 898; Christie v. United States, 237 U.S. 234, 35 S.Ct. 565, 59 L.Ed. 933; United States v. Atlantic Dredging Company, 253 U.S. 1, 40 S.Ct. 423, 64 L.Ed. 735; United States v. L. P. & J. A. Smith, 256 U.S. 11, 12, 41 S.Ct. 413, 414, 65 L.Ed. 808.

The Supreme Court having granted a writ of error in the Shortall Case, supra, we have withheld disposition of the instant case until the Supreme Court decided that case. That court on March 23, 1938, reversed the judgment of the Court of Civil Appeals in the Shortall Case and rendered judgment for the City of Dallas. See 114 S.W.2d 536.

While no such distinction ' is drawn in the Shortall Case, it is not amiss to observe that in the case of Maney v. Oklahoma City, 150 Okl. 77, 300 P. 642, 76 A.L.R. 258, relied upon by appellant herein, the court held that in that instance the city was acting in a proprietary, and not in a governmental, capacity; whereas in the instant case the State, in the construction of its public highways acts in a governmental capacity. Brooks v. State, Tex.Civ.App., 68 S.W.2d 534, writ refused, and cases therein cited. That being true the State would not be liable for any tortious acts of its officers, agents or employees. And the mere permission to sue the State in no wise alters this well settled rule nor imposes any such liability upon the State. Brooks v. State, supra. While appellant in the instant case alleged fraudulent misrepresentations by the Highway Department as to the quantities of rock and earthen material to be excavated, and that no tests were made upon which to base such estimates, no proof was offered as to this allegation, no bad faith charged against the engineers of the Highway -Department, and on this appeal appellant relies upon the contention that the quantities of materials stated in the notices for bids upon the project amounted to warranties by the State upon which he had a right to rely, and did rely, in entering into his contract with the State, and that consequently he was entitled under the cases cited to compensation accordingly.

The notices for bids sent to appellant and others on the project here involved, and on which the contract made with the State was predicated, after specifying the units of work involved, contained the following:

“Item 2. Proposal Requirements and Conditions.
“2.3. Examination of Plans, Specifications, Special Provisions, and Site of Work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Contracting Corp. v. City of Dallas
407 F.3d 708 (Fifth Circuit, 2005)
Keith A. Nelson Co. v. R. L. Jones, Inc.
604 S.W.2d 351 (Court of Appeals of Texas, 1980)
Austin Bridge Co. v. State
550 S.W.2d 135 (Court of Appeals of Texas, 1977)
Erickson v. Rocco
433 S.W.2d 746 (Court of Appeals of Texas, 1968)
In Re Nueces County, Texas, Road District No. 4
174 F. Supp. 846 (S.D. Texas, 1959)
Gogo v. Los Angeles County Flood Control District
114 P.2d 65 (California Court of Appeal, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
118 S.W.2d 960, 1938 Tex. App. LEXIS 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/powell-v-state-texapp-1938.