General Supply & Construction Co. v. Goelet

149 A.D. 80, 133 N.Y.S. 978, 1912 N.Y. App. Div. LEXIS 6354
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 9, 1912
StatusPublished
Cited by8 cases

This text of 149 A.D. 80 (General Supply & Construction Co. v. Goelet) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Supply & Construction Co. v. Goelet, 149 A.D. 80, 133 N.Y.S. 978, 1912 N.Y. App. Div. LEXIS 6354 (N.Y. Ct. App. 1912).

Opinion

Laughlin, J.:

On the 22d day of August, 1906, the plaintiff, a domestic corporation engaged in building construction, and the appellant made a contract in writing by which plaintiff undertook to erect on premises owned by appellant situate at the northeast corner of Sixty-fourth street and Broadway, borough of Manhattan, New York, a six-story reinforced concrete building in accordance with specifications and drawings theretofore prepared by one F. M. Andrews, an architect, under whose direction the work was to be done. The main floor of the building was to consist of stores and the remainder of the building was to be used as a garage. The contract provided that the building was to be completely finished and ready for occupancy on or before the 1st day of July, 1907, and in default thereof the respondent was to pay the appellant as liquidated damages the sum of $200 for each day thereafter until the building was completed and ready for occupancy. The respondent failed to complete the building within the time specified in the contract, and in fact had not completed the excavation work at one corner of the plot at that time, although the excavation work had been finished and some of the concrete work done on other parts of the plot. The contract contained the usual provision that should the contractor at any time refuse or neglect to supply a sufficient number of skilled workmen, or sufficient materials of proper quality, or fail in any other respect to prosecute the work promptly and diligently or to perform its agreement, the [83]*83owner should he at liberty, on such neglect, refusal or failure being certified by the architect, after three days’ notice in writing to the contractor, to provide the necessary labor or materials at the expense of the contractor; and it was further provided that the owner should be at liberty to terminate the employment of the contractor and to take possession of the work for the purpose of completing it for the account of the contractor as therein provided, should the architect certify that such refusal, neglect or failure on the part of the contractor constituted sufficient ground for such action. On the 2d day of July, 1907, Maynicke & Franke, architects, representing the owner, wrote respondent a letter setting out the status of the work on the day before, which was the day on which the work should have been completed, and demanding .that the contractor display greater energy to the extent of working nights, and drawing attention to the fact that the owner would suffer heavy financial loss on account of the delay, and that the contract spoke for itself on that point. The contractor remained in charge of the work, making slow progress, however, without interruption until the 10th day of March, 1908, when Maynicke & Franke in behalf of the owner demanded of Andrews that he issue a certificate authorizing the owner to terminate the contract. This was refused, but on the day following the architect issued a certificate authorizing the owner to supply certain broken stone and gravel with which to prosecute the work and to charge the same to the contractor. The next day, March 12, 1908, the appellant wrote respondent complaining that the work had not been completed within the time specified by the contract and that the contractor had not exercised proper diligence in prosecuting the work, and demanding that the respondent within three days supply a sufficient number of skilled workmen and sufficient material of proper quality to prosecute the work with promptness and diligence, and stating that on its failure so to do the appellant would furnish the labor and materials and terminate the respondent’s employment and enter upon the premises and take possession for the purpose of completing the work, and would take possession of the materials, tools and appliances of the contractor thereon for that purpose. The appellant having failed to [84]*84obtain the architect’s certificate, this notice was ineffectual for the purpose of affording a basis to enable the appellant to take charge of the work under the contract and complete it thereunder for the account of the respondent. On the twenty-first day of March thereafter, without further notice, the appellant forcibly ejected the respondent and took charge of the work, and on the same day the respondent wrote the appellant protesting against his action and claiming that it was not responsible for the delay and stating that it would insist upon its rights under the contract. On the third day of April thereafter appellant wrote respondent another letter in which he stated in substance that pursuant to his previous letter he had proceeded with the reinforced concrete work which respondent had abandoned; that other work had since been done by respondent’s sub-contractors who desired their pay, and complaining that respondent had not applied for an installment payment under the contract on March twenty-fifth, as provided in the contract, and had permitted liens to be filed, and giving notice that unless the respondent applied for the installment payment within three days which would enable appellant pursuant to authority contained in letters from the respondent under date of October 14 and 15, 1907, to pay the sub-contractors and unless respondent took action to satisfy the liens and proceeded “in an orderly and diligent manner,” appellant should consider that respondent had abandoned the entire work, and would complete the building and charge the expense to the respondent “ as provided for ha our contract. ” Respondent replied on the eighth of the same month claiming that appellant had previously ejected it and taken possession of the entibe work, and, in effect, that respondent would rest on appellant’s prior breach of the contract. There was no further correspondence or negotiations between the parties. The respondent subsequently filed a mechanic’s lien for the matei'ials furnished and woi'k perfonned less the amount i*eceived from the appellant, on the theory that it was entitled to a lien to recover for the value of the materials furnished and work done as upon a quantum meruit and it thereafter brought this action and has recovered upon that theory.

The learned counsel for the appellant concedes that the con[85]*85tract was not lawfully terminated pursuant to its provisions entitling his client to complete the work for the account of the contractor; and it could not he successfully contended that it was terminated under the contract. Counsel for both parties accept as applicable to this case the decision in Wyckoff v. Taylor (13 App. Div. 240), wherein it was held that if a building contractor does not complete the work within the time specified, the owner may then, or at any time thereafter, exclude the contractor and take possession of the work, on the theory that there is a continuing breach on the part of the contractor who cannot then recover damages for being deprived of completing the work. In that case the contractor after having been ejected from the work during its progress on account of not completing it within the time fixed by the contract, had recovered the contract price of the work as if he had fully performed, and the reversal was on that ground. The court, however, in the opinion discussed the contractor’s effort to sustain the recovery on the theory that it was had on a quantum meruit, and, without expressing an opinion as to whether he could recover on a quantum meruit, held that the evidence in the record would not sustain a recovery on that theory. On the appeal herein, and evidently upon the trial, counsel for both parties considered the Wyckoff

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Supply & Construction Co. v. Goelet
148 N.E. 778 (New York Court of Appeals, 1925)
General Supply & Construction Co. v. Goelet
207 A.D. 646 (Appellate Division of the Supreme Court of New York, 1924)
Hart v. American Concrete Steel Co.
278 F. 541 (E.D. New York, 1921)
Savannah Lighting Co. v. Fidelity & Deposit Co.
95 S.E. 113 (Court of Appeals of Georgia, 1918)
Frankfurt-Barnett Co. v. William Prym Co.
237 F. 21 (Second Circuit, 1916)
Mohn v. New York & Pennsylvania Smokeless Coal Co.
145 N.Y.S. 116 (Appellate Terms of the Supreme Court of New York, 1914)
Rice, Barton & Fales Machine & Iron Co. v. Hoffman-Youmans Paper Mills
158 A.D. 309 (Appellate Division of the Supreme Court of New York, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
149 A.D. 80, 133 N.Y.S. 978, 1912 N.Y. App. Div. LEXIS 6354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-supply-construction-co-v-goelet-nyappdiv-1912.