General Supply & Construction Co. v. Goelet

148 N.E. 778, 241 N.Y. 28, 1925 N.Y. LEXIS 521
CourtNew York Court of Appeals
DecidedJuly 15, 1925
StatusPublished
Cited by49 cases

This text of 148 N.E. 778 (General Supply & Construction Co. v. Goelet) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Supply & Construction Co. v. Goelet, 148 N.E. 778, 241 N.Y. 28, 1925 N.Y. LEXIS 521 (N.Y. 1925).

Opinion

Lehman, J.

On or about the 22d day of August, 1906, the plaintiff entered into a written contract with the defendant Goelet whereby the plaintiff obligated itself to provide all the material and perform all the work for the erection of the “ mason work, structural iron and steel work and carpenter work ” in connection with a building, on premises owned by Goelet. The contract provided that the entire- building is to be completely *33 finished and shall be ready for occupancy on or before the 1st day of July, 1907, and in default thereof the Contractor shall pay to the Owner the sum of Two Hundred Dollars as liquidated damages for each and every day that the said building shall remain uncompleted and unfinished and not ready for occupancy, after the date above mentioned.”

The work was not completed on July 1st, 1907, and the plaintiff was permitted by the owner to continue performance of the work. The owner thereby waived time as an essential element of the contract (Taylor v. Goelet, 208 N. Y. 253); but none the less the failure to complete at the time fixed in the contract constitutes a breach and gives rise to a cause of action for damages caused by the delay. (Deeves & Son v. Manhattan Life Insurance Co., 195 N. Y. 324.) The work was still far from finished on March 23d, 1908, and on that date the owner, against the plaintiff’s protest and resistance, ejected the plaintiff from the premises and prevented it from proceeding with the work under the contract. The Appellate Division has made a finding that at that time the defendant Goelet was justified in concluding that the plaintiff would not, within any reasonable time, finish the work of erecting the building.

The continued delays of the contractor in the past might perhaps reasonably give rise to the inference that it would not proceed with reasonable speed in the future. We may assume that at the time the owner put the contractor off the work, he had, with reason, ceased to hope or expect that the contractor would mend his ways, yet the owner had no right to terminate the contract in the manner he did. He had provided in the contract protection for himself against unreasonable delays' on the part of the contractor, first, by stipulating that the work must be completed by a definite date; second, by provision for stipulated damages for each day’s delay in the completion of the work after that date; third, by provision *34 that the owner might terminate the contract at any time upon certificate of the architect that the work was being unreasonably delayed and that such delay was sufficient ground for termination of the contract. He terminated the contract and ejected the contractor, not for failure to complete the work in the contract time, but for unreasonable delay thereafter, and he failed to comply with the provision of the contract which made the architect’s certificate a condition precedent to the right to take such action. Though he may have been justified, as the Appellate Division has held, in his belief that the contractor would not thereafter mend his ways and finish the work within a reasonable time, yet where such delay did not amount to abandonment he could not rescind the contract for that reason, except according to its terms. (Brady v. Oliver, 125 Tenn. 595; McTague v. Sea Isle C. L. & Building Assn., 57 N. J. L. 427; Taylor v. Goelet, 208 N. Y. 253.) He was not left entirely at the mercy of a dilatory, contractor, even if the architect did not find and refused to certify that the contractor’s delays were sufficient ground for termination. Though time was waived as an essential element of the contract, it could be restored by notice to complete within a reasonable time stated in said notice. (Taylor v. Goelet, supra.) Having indicated purpose to keep the contract alive in spite of delays on the part of the contractor, the owner could not suddenly abandon the purpose and treat as essential an element in the contract which he had previously waived, as ground for termination. (Brede v. Rosedale Terrace Co., 216 N. Y. 246.) The termination of the contract in this case without the required previous notice and without a certificate from the architect in accordance with the terms of the contract was wrongful.

After the attempted termination of the contract the plaintiff brought this action to foreclose his hen for the reasonable value of the work done and the materials furnished. The courts below have found that the plaintiff *35 is entitled to recover such value. The defendant owner does not seriously dispute his obligation or claim that under the circumstances even a right to terminate the contract in the manner attempted would justify a refusal to pay for work performed or material furnished while the contractor was allowed to continue performance of the work. The substantial dispute between the parties upon this appeal concerns the question of whether the owner, in spite of his refusal, which we must hold was wrongful, is entitled to offset or counterclaim for damages suffered by the plaintiff’s failure to complete the work at the time fixed in the contract.

The Appellate Division has held that even if the attempted rescission was wrongful the plaintiff acquiesced in such rescission by bringing this action to foreclose a lien for the value of labor and materials furnished and, thereby, waived the owner’s breach. It seems to us that the form of action which the plaintiff has chosen for the vindication of the rights which he had after he was put off the work may not be given such effect. While the right to recover the value instead of the agreed price of the labor and materials furnished may be said to be based upon an implied contract, that contract was implied in law and not by intention of the parties when the owner wrongfully terminated the contract. The form of action may recognize that the express contract is terminated; it does not recognize that the termination was lawful or the result of agreement by the parties. If complete performance by the owner was a condition precedent to his right to recover for damages suffered by failure on the part of the contractor to finish the work in accordance with the contract, if performance by the contractor was thwarted by failure of performance on the part of the owner, it is clear that the owner’s breach of contract was not waived by the contractor. There was no intention to waive and no position assumed by the contractor inconsistent with its present claim that the termination was wrongful.

*36 Wrongful interference with the work could not, however, have thwarted the contractor in performance of his obligation to complete the work eight months before that interference, and by its nature it could not have constituted the breach of a condition precedent to the contractor’s obligation to complete at the time set. On July 1, 1907, the plaintiff was in default under his contract. That default gave rise to a claim for damages caused by the delay of the contractor and a right to terminate the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Empire Constr. Inc. v. Borough Constr. Group LLC
2021 NY Slip Op 05455 (Appellate Division of the Supreme Court of New York, 2021)
Black Riv. Plumbing, Heating & A.C., Inc. v. Board of Educ. Thousand Is. Cent. Sch. Dist.
2019 NY Slip Op 6321 (Appellate Division of the Supreme Court of New York, 2019)
McPherson Bldrs., Inc. v. Performance Premises, LLC
2019 NY Slip Op 2596 (Appellate Division of the Supreme Court of New York, 2019)
Kleinberg Electric, Inc. v. E-J Electric Installation Co.
111 A.D.3d 410 (Appellate Division of the Supreme Court of New York, 2013)
Mike Building & Contracting, Inc. v. Just Homes, LLC
27 Misc. 3d 833 (New York Supreme Court, 2010)
Lot 57 Acquisition Corp. v. Yat Yar Equities Corp.
63 A.D.3d 1109 (Appellate Division of the Supreme Court of New York, 2009)
Sweetser v. NETSMART TECHNOLOGIES, INC.
558 F. Supp. 2d 108 (D. Maine, 2008)
Allied-Lynn Associates, Inc. v. Alex Bro, LLC
34 A.D.3d 1247 (Appellate Division of the Supreme Court of New York, 2006)
J. Petrocelli Construction, Inc. v. Realm Electrical Contractors, Inc.
15 A.D.3d 444 (Appellate Division of the Supreme Court of New York, 2005)
R.W. Granger & Sons, Inc. v. City School District
296 A.D.2d 636 (Appellate Division of the Supreme Court of New York, 2002)
In Re Regional Building Systems, Inc.
273 B.R. 423 (D. Maryland, 2001)
Sauer v. Xerox Corp.
17 F. Supp. 2d 193 (W.D. New York, 1998)
International Fidelity Insurance v. County of Chautauqua
245 A.D.2d 1056 (Appellate Division of the Supreme Court of New York, 1997)
Bausch & Lomb Inc. v. Bressler
977 F.2d 720 (Second Circuit, 1992)
Bausch & Lomb Incorporated v. Bernard Bressler
977 F.2d 720 (Second Circuit, 1992)
In re Mercury Lamps, Inc.
109 B.R. 585 (E.D. New York, 1989)
US for Use of Cortolano & Barone v. Morano Const.
724 F. Supp. 88 (S.D. New York, 1989)
Greenspan v. Amsterdam
145 A.D.2d 535 (Appellate Division of the Supreme Court of New York, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
148 N.E. 778, 241 N.Y. 28, 1925 N.Y. LEXIS 521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-supply-construction-co-v-goelet-ny-1925.