East Empire Constr. Inc. v. Borough Constr. Group LLC

2021 NY Slip Op 05455
CourtAppellate Division of the Supreme Court of the State of New York
DecidedOctober 12, 2021
DocketIndex No. 655963/16 Appeal No. 14220 Case No. 2020-04836
StatusPublished
Cited by1 cases

This text of 2021 NY Slip Op 05455 (East Empire Constr. Inc. v. Borough Constr. Group LLC) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Empire Constr. Inc. v. Borough Constr. Group LLC, 2021 NY Slip Op 05455 (N.Y. Ct. App. 2021).

Opinion

East Empire Constr. Inc. v Borough Constr. Group LLC (2021 NY Slip Op 05455)
East Empire Constr. Inc. v Borough Constr. Group LLC
2021 NY Slip Op 05455
Decided on October 12, 2021
Appellate Division, First Department
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This opinion is uncorrected and subject to revision before publication in the Official Reports.


Decided and Entered: October 12, 2021 SUPREME COURT, APPELLATE DIVISION First Judicial Department
Rolando T. Acosta
Anil C. Singh Tanya R. Kennedy Manuel Mendez John R. Higgitt

Index No. 655963/16 Appeal No. 14220 Case No. 2020-04836

[*1]East Empire Construction Inc., Plaintiff-Respondent,

v

Borough Construction Group LLC, et al., Defendants-Appellants, CPR Money LLC, et al., Defendants.


Defendants appeal from an order of the Supreme Court, New York County (Barbara Jaffe, J.), entered on or about November 1, 2019, which, insofar as appealed from, granted plaintiff's motion for summary judgment as to liability on its breach of contract claim against defendant Borough Construction Group LLC and dismissing defendants' eleventh affirmative defense.



Tuttle Yick LLP, New York (David G. Skillman of counsel), for appellants.

Ingram Yuzek Gainen Carroll & Bertolotti, LLP, New York (Maurizio Anglani of counsel), for respondent.



ACOSTA, P. J.

This breach of contract case, in which plaintiff alleges that defendant failed to comply with the notice-to-cure provision before terminating the contract, gives us the opportunity to address the strict nature of these types of provisions and the very rare instances when they can be ignored. Defendant general contractor terminated the steel work subcontract it had entered into with plaintiff based on what was essentially a claim that plaintiff provided faulty work. As discussed in more detail below, defendant was obligated to give plaintiff the 10-day notice to cure provided in the contract, as faulty work does not fall within the very limited and rare circumstances when the provision can be dispensed with, namely, where the other party expressly repudiates the contract or abandons performance or where the breach is impossible to cure.

In 2015, defendant Borough Construction Group LLC (Borough), as general contractor for defendant property owner 952 Columbus LLC (Owner), subcontracted with plaintiff to perform steel work at the residential development project located at 952 Columbus Avenue. As relevant here, the subcontract required plaintiff to supply and install all steel needed for "Support of Excavation" and for construction of the structural steel frame of the new building, and to secure and pay for the crane permits for installation. In addition, the subcontract required plaintiff to provide a full-time, on-site safety manager, take reasonable safety precautions, and comply with applicable ordinances, codes, and safety measures.

Section 3.4 of the subcontract provides,

"If the Subcontractor [plaintiff] defaults or neglects to carry out the Work . . . fails within five working days after receipt of written notice from the Contractor to commence and continue correction of such default or neglect with diligence and promptness, the Contractor may . . . make good such deficiencies and may deduct the reasonable cost thereof from the payments then or thereafter due the Subcontractor."

Section 7.2.1 provides,

"If the Subcontractor repeatedly fails or neglects to carry out the Work in accordance with the Subcontract Documents or otherwise fails to perform in accordance with this Subcontract and fails within a ten-day period after receipt of written notice to commence and continue correction of such default or neglect with diligence and promptness, the Contractor [Borough] may by written notice[*2][,] . . . terminate the Subcontract and finish the Subcontractor's Work by whatever method the Contractor may deem expedient."

The subcontract rider, schedule A, provided the owner (as opposed to Borough) with a shorter notice period. The rider provides,

"If for any reason the Subcontractor fails to perform to the degree and standards set forth by the Owner, he will be issued [a 72-hour] Notice to Cure. Should the Subcontractor fail to rectify and remedy the situation within that timeframe, the Owner will remove Subcontractor from the Project and any and all costs and all fees associated with the Subcontractor's failure to perform will be back-charged and deducted from any monies owed to the Subcontractor."

On May 9, 2016, Borough sent plaintiff a written "notice of termination" stating that the subcontract would be terminated in three days from the date of the letter and that plaintiff was in default by "failing to provide sufficient manpower [] [and] failing to meet the schedule, safety regulations and qualified workmanship for the Project." The letter further stated that plaintiff "failed to respond or delayed response to requests for crane usage" and "has delayed the performance and completion of the work." The letter instructed plaintiff to cease work immediately. After negotiations, Borough cancelled the termination notice, and plaintiff returned to the job. However, on May 16, 2016, Borough sent plaintiff an identical notice of termination and directed plaintiff to cease operations. Borough subsequently retained a new steel subcontractor.

In November 2016, plaintiff brought this action, asserting a breach of contract claim against Borough and quasi contract claims against Owner. The complaint alleges that Borough breached the subcontract by improperly terminating plaintiff from the project on May 16, 2016 without good cause and without providing plaintiff with the appropriate notice and opportunity to cure the alleged default, and it asserts that plaintiff is owed over $225,000 for outstanding invoices for construction services performed on the project.

In March 2019, plaintiff moved, as relevant here, for summary judgment as to liability on its breach of contract claim against Borough and dismissing defendants' eleventh affirmative defense, which seeks setoffs for costs incurred in curing plaintiff's allegedly defective work, on the grounds that Borough did not give plaintiff the chance to "commence and continue correction" of its alleged breach, as required by the subcontract. Plaintiff argued that nothing in the record showed that the alleged defects were impossible to cure or amounted to a repudiation of the subcontract so as to render futile a notice-to-cure, and that this failure by Borough to follow the notice-to-cure requirements precluded Borough from attempting to recover or offset its costs associated with the alleged deficiencies in plaintiff's performance.

In opposition, defendants alleged persistent, incurable acts [*3]of negligence and numerous safety violations and delays by plaintiff from the outset that resulted in defendants' engineering consultant's total shutdown of the work site as of May 16. They argued that, at the very least, triable issues of fact existed as to whether plaintiff had created a situation so deficient and dangerous that it could not be remedied within the cure period and that plaintiff, which had been directed to cease operations due to safety concerns, could not be trusted to attempt to cure the deficient performance.

Supreme Court granted plaintiff's motion. We now affirm.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Empire Constr. Inc. v. Borough Constr. Group LLC
2021 NY Slip Op 05455 (Appellate Division of the Supreme Court of New York, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2021 NY Slip Op 05455, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-empire-constr-inc-v-borough-constr-group-llc-nyappdiv-2021.