Shute v. Hamilton

3 Daly 462
New York Court of Common Pleas·Decided March 15, 1871·Published·Cited by 9 cases

Opinion

By the Court.*

Daly, Chief Justice.

As the contract was originally drawn, the plaintiffs were to take down the old walls to the foundation, remove all the rubbish, and do all the excavating necessary to the laying of the foundation for the new structure. By an addenda, however, to the instrument before it was executed, it was declared that this was not to be included in the contract. A person named Richardson was employed by the defendant to do it; but the day after the signing of the contract the plaintiffs agreed with the defendant to do it, and Richardson was dismissed.

The referee has found, as a conclusion of law, that the doing of this preparatory work was necessarily contemplated by both parties when the plaintiffs stipulated to erect and finish the new structure by the 1st of November, 1866, or pay to the defendant, as liquidated damages, fifty dollars per day for every day’s delay thereafter, and the finding of the referee in this respect was clearly correct.

When the plaintiffs contracted to erect and finish the new [465] building by the time agreed upon, they necessarily knew that this preparatory work would have to bé done before they could begin theirs, and it is therefore to be assumed that they made allowance for the time it would take to pull down the old walls, remove the debris, and make the excavations, when they fixed upon the 1st of November, 1866, as the period within which they stipulated to erect and complete the new building.

They had a right to assume that the defendant would have this work done as soon thereafter as it could he done in the ordinary course, and after they agreed to do it themselves, their position in respect to the time for the commencement and completion of the new structure, was in no respect changed for the worse. This work had to be done by some one before they could commence their labors, and, whether it was done by them or by others, it had no bearing upon the time within which they agreed that they would erect and complete the new building. They had provided in their contract against any delay in the performance of this work by a provision that they should be entitled to excuse and justify any default on their part on account of any omission or neglect of other contractors, by giving written notice of it to the defendant or to the architect; a provision which became inapplicable in respect to this particular work, when they undertook to do it, as they owed it alike to themselves and to the defendant, in the faithful fulfillment of their contract, to execute it with all reasonable dispatch.

The plaintiffs commenced clearing out the ruins'on the 28th of Hay, 1866, and they were engaged in this work until the 28th of June, following. If the time which then remained for the erection and completion of the new building was too limited, the plaintiffs are alone answerable for it. The defendant certainly is not. If too much time was occupied in taking down the old walls, removing the ruins, and making the excavations, it must have arisen from the plaintiffs’ inability or delay in doing it, or, if that time was no more than was necessary, then it was incumbent upon the plaintiffs, when they undertook to do this, to have the period extended for the completion of the new building. No material delay was occasioned by the change, for they made the agreement to do this preparatory work the [466] very day after they signed the contract for the erection of the new building. Where the performance of a contract within the time stipulated for, becomes impossible by reason of some act of the other party, the party contracting with him is excused. (Russell v. Da Bandeira, 13 Com. B. N. S. 204; Comyn’s Digest, Condition L. 6.)

Thus, where one who contracts to have work done for him, omits to do something on his part, which is essential before the work can be begun or carried on and by which the other party is delayed (Holme v. Guppy, 3 Mees. & Welsb. 386; Allamon v. The Mayor, &c. of Albany, 43 Barb. 33); or where an agreement is afterwards made for extra work, or for a change in the plan, which produces delay (Van Buskirk v. Stow, 42 Barb. 9; Russell v. Da Bandeira, 13 Com. B. N. S. 148); or where the one for whom the work is to be done is prevented from doing what was essential on his part through the happening of a casualty (Niblo v. Binsse, 1 Keyes, 476), the strict condition in respect to time is waved, and the party who is to do the work is allowed a reasonable time thereafter within which to complete it (Green v. Haines, 1 Hilt. 254; Meehan v. Williams, 2 Daly, 367).

. Nothing of this kind existed in this case, for if the plaintiffs were prevented from putting up the new structure within the time agreed upon, in consequence of the length of time occupied in clearing away the ruins of the old one, it was not through any act of the defendant but through a cause for which the plaintiffs are answerable, or against which they should have provided.

The stipulation for the payment by the defendant of $50 a day for every day’s delay after the 1st of November, 1866, was not a penalty, but damages liquidated and agreed upon between the parties.

The language of the stipulation is: Shóuld the contractor fail to complete the work by the time specified the sum of fifty dollars for each and every day the said contractor shall be in default is hereby mulMoIly fixed a/nd determined as the Hgmdar ted damages of the owner by reason thereofP

In the first place, the intention of the parties to liquidate and fix the amount of the damages in the event of the plaintiffs’ [467] failure to complete the building by the specified time, is here plainly expressed.

In the next place, it is applied only in the event of the breach of a single covenant, and lastly the damages, from their very nature, were conjectural and uncertain, all of which show incontrovertibly that this is not a penalty, but an agreement to fix beforehand, by this provision, the actual amount of the damages in the event of a breach (Mundy v. Culver, 18 Barb. 336; Cotheal v. Talmadge, 1 E. D. Smith, 573; Id. 9 N. Y. 551; Dakin v. Williams, 11 Wend. 67; Bagley v. Peddie, 16 N. Y. 469; Lampman v. Cochran, Id. 275; Hosmer v. Fine, 19 Barb. 106; Jackson v. Baker, 2 Edw. Ch. 471; Beale v. Hays, 5 Sandf. 640; Academy of Music v. Hackett, 2 Hilt. 217; Crisdel v. Bolton, 3 Car. & P. 240).

The building was not completed until the 1st of February, 1867, or two months after the time agreed upon; but the referee, upon the assumption that some delay before the 1st of February might be excusable in the plaintiffs, allowed the $50 only up to the 15th of January, charging the plaintiffs with two months and a half for delay, or $3,750. This he might properly •do, as the parties had arranged between themselves what should be the damage per day, and if the referee was of opinion, upon the facts, that two weeks of the delay had been occasioned by the defendant, he could disallow the $50 a day for that period of time.

Free access — add to your briefcase to read the full text and ask questions with AI

Shute v. Hamilton, 3 Daly 462 (N.Y. Super. Ct. 1871).

3 Daly 462 (Shute v. Hamilton) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

General Supply & Construction Co. v. Goelet
148 N.E. 778 (New York Court of Appeals, 1925)
General Supply & Construction Co. v. Goelet
207 A.D. 646 (Appellate Division of the Supreme Court of New York, 1924)
Kleinfelter v. Granger
136 N.Y.S. 485 (New York Supreme Court, 1911)
Mikolajewski v. Pugell
62 Misc. 449 (New York Supreme Court, 1909)
Charleston Lumber Co. v. Friedman
61 S.E. 815 (West Virginia Supreme Court, 1908)
Morgan v. Stevens
6 Abb. N. Cas. 356 (New York Court of Common Pleas, 1878)
Rathbun v. Waters
1 N.Y. City Ct. Rep. 36 (New York Marine Court, 1876)
Kemp v. Knickerbocker Ice Co.
51 How. Pr. 31 (New York Court of Common Pleas, 1876)
Berrinkott v. Traphagen
39 Wis. 219 (Wisconsin Supreme Court, 1875)