Mikolajewski v. Pugell

62 Misc. 449, 114 N.Y.S. 1084
CourtNew York Supreme Court
DecidedFebruary 15, 1909
StatusPublished
Cited by4 cases

This text of 62 Misc. 449 (Mikolajewski v. Pugell) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mikolajewski v. Pugell, 62 Misc. 449, 114 N.Y.S. 1084 (N.Y. Super. Ct. 1909).

Opinion

Wheeler, J.

This action was brought by the plaintiffs to recover damages against the contractor in a building contract for a failure to complete the building to be erected for the plaintiffs within the stipulated time.

The defendant agreed in his contract with the plaintiffs to complete the building in question on or before the 30th of October, 1906. As a matter of fact, the building was not [450]*450completed until March, 1907. The contract price was $3,250. Payments had been made from time to time, but a balance on the contract price remained unpaid. The defendant demanded the balance and threatened to file a mechanic’s lien against the property unless paid. In the conversation had between the parties, the defendant was requested to make an allowance for loss of rent owing to the delay in completing the building within the agreed time. The defendant absolutely refused to allow anything, whereupon the plaintiffs paid the defendant the balance on the contract. The evidence discloses no agreement on the part of the plaintiffs to relinquish or abandon their claim for loss of rent. All that was done or said consisted of a request for such an allowance for lent lost, a refusal by the defendant to make any such allowance and a payment by the plaintiffs of the balance of the contract price.

The trial court dismissed the plaintiffs’ complaint on the following grounds: First, because time was not of the essence of the contract between the parties. Second, if time was of the essence of the contract, the plaintiffs took possession of the house before it was completed, and remained in possession until all work was done; and, Third, the plaintiffs having paid the defendant the balance of the contract price, and at the time having asked for some allowance for delay in finishing the house, which was refused by defendant, the transaction amounted to an accord and satisfaction of all claims between the parties.

This court is of the opinion the court below erred in the conclusions reached.

We think time was of the essence of the contract. The agreement to complete by October thirtieth was inserted in the contract for the express benefit of the plaintiffs. If this agreement had been carried out, the plaintiffs would have had the use of the building from that date on. The clause was inserted to accomplish that very purpose, and we cannot understand on what principle of law or equity the defendant should be permitted to say that the clause fixing the date of completion meant nothing, and might be disregarded with im" punity.

[451]*451Delay meant loss o£ rents, and it has been held that in such contract time is of its essence. Wyekoff v. Taylor, 13 App. Div. 240; Schlachter v. Hopkins, 84 Hun, 402; Hexter v. Knox, 63 N. Y. 561; Oberlies v. Bullinger, 75 Hun, 248; Ansonia Brass & C. Co. v. Gerlach, 8 Misc. Rep. 256.

As to the proposition that the plaintiffs took possession before completion and so- suffered no damage, it is sufficient to say that the undisputed evidence is that the house was not ready for occupation until the 1st of March, 1907, and then uncompleted, and that, notwithstanding, the defendant went on and finished the work. We are unable to understand how talcing’ partial or even complete possession on March first in any way prejudiced either the plaintiffs or the defendant. There is nothing in the testimony given on the trial tending to show any such thing, and by taking possession the plaintiffs cannot be said to have waived any claim for damages for a failure to complete the building sooner.

As to the proposition of an accord and satisfaction, we find nothing in the case to sustain that view. The evidence simply discloses that the plaintiffs made a demand for an allowance for delay in the completion of the building, and that the defendant flatly refused to recognize any such claim. The defendant was then paid the balance of the contract price for the erection of the building, under the threat that, unless the money was paid, a mechanic’s lien would be filed against the property. Nothing was said by the plaintiffs to the effect that they relinquished their demand. There was no compromise of their differences. The defendant threw nothing off his demand. He demanded payment in full and he received it.

The defendant had a cause of action for the balance due on the contract price of the building. The plaintiffs had a cause of action for a breach by the defendant to complete in time. The defendant’s cause of action was paid in full; the cause of action of the plaintiffs was refused recognition, and nothing was paid or allowed by the defendant to settle it. The defendant, having been paid in full, and having neither paid nor nllowéd the plaintiffs anything, cannot, we think, assert that be has thereby satisfied their claim. Nor did the payment [452]*452of the defendant’s claim in full constitute a legal waiver by the plaintiffs of their claim against the defendant.

The covenant on the part of one party to the contract to perform within a certain time, and the covenant on the part of the other to pay, are independent and distinct. A right of action may grow out of either.

The owners could allow the contractor to go on and complete without waiving or forfeiting their right to damages for a breach of the contract as to time. Ruff v. Rinaldo, 55 N. Y. 664; Granniss & Hurd Lumber Co. v. Deeves, 72 Hun, 171; affd., 147 N. Y. 718; Beyer v. Henry Huber Co., 115 App. Div. 344; Crocker-Wheeler Co. v. Varick R. Co., 104 id. 570; Sinclair v. Talmadge, 35 Barb. 602-606; Rogers v. Beard, 36 id. 31.

We are also of the opinion that, by paying the defendant the amount of the contract price of the building, the plaintiffs did not thereby foreclose themselves from asserting and enforcing their demand for damages by reason of a failure on the contractor’s part to complete the building within the stipulated time.

The case of Ruff v. Rinaldo, 5 5 N. Y. 664, was an action to foreclose a mechanic’s lien. Defendant, Rinaldo, contracted with one Fincke to do the mason work on three buildings being erected by him, which was to be completed April 1, 1872. Fincke did not complete it until the first of July. Defendant after the expiration of the time permitted Fincke and his subcontractors (of whom plaintiff was one), to proceed with the work, and make payments on the contract. Held: “ That this was not a release or discharge of the stipulation as to time, but that Fincke was liable for the damages resulting therefrom; which damages were the value of the use of the buildings, while defendants were deprived in consequence of the delay.”

This question is fully discussed in the case of Shute v. Hamilton, 3 Daly, 470, which was an action by a contractor to recover an unpaid balance due upon a building contract. The opinion is as follows:

“ It is insisted that the defendant waived the condition in respect to time, by making payments as the work pro[453]*453gressed, after the first of November. By the contract certain payments were to be made at certain stages in the progress of the work, and the defendant continued to make these payments from the 1st of November to the 12th of January, as he had done before, leaving only to be paid on the last payment $300.

“ The referee has found, that by these payments the defendant merely treated the contract as still in force, and that they constituted no waiver of the defendant’s claim for damages, by reason of the delay. The finding was correct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Empire Heating Corp. v. James Stewart & Co.
140 Misc. 303 (New York Supreme Court, 1931)
National Pencil Co. v. Pinkerton's National Detective Agency
91 S.E. 432 (Court of Appeals of Georgia, 1917)
Rice, Barton & Fales Machine & Iron Co. v. Hoffman-Youmans Paper Mills
158 A.D. 309 (Appellate Division of the Supreme Court of New York, 1913)
Kleinfelter v. Granger
136 N.Y.S. 485 (New York Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
62 Misc. 449, 114 N.Y.S. 1084, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mikolajewski-v-pugell-nysupct-1909.