Allamon v. Mayor of Albany

43 Barb. 33, 1864 N.Y. App. Div. LEXIS 141
CourtNew York Supreme Court
DecidedMarch 7, 1864
StatusPublished
Cited by19 cases

This text of 43 Barb. 33 (Allamon v. Mayor of Albany) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allamon v. Mayor of Albany, 43 Barb. 33, 1864 N.Y. App. Div. LEXIS 141 (N.Y. Super. Ct. 1864).

Opinion

By the Court,

Miller, J.

By the terms of the contract between the plaintiff and the defendants, for a breach of which a recovery was had in this action, no definite time was fixed for the completion of the plaintiff’s work under it, but it contained a covenant by which the plaintiff was bound “to commence said work and proceed therewith without delay, and in such manner as not to delay the contractor for the mason work.” It will be observed that here was a positive engagement on the part of the plaintiff as to the manner in which he was to proceed with the performance of the work he had agreed to do, and a direct promise and obligation on his part that he should commence at once and proceed without delay to its conqiletion. If the plaintiff had failed to proceed with the work and fulfill this provision of the contract without delay, he would most certainly have been liable for any damages which may have accrued to the defendants, unless the delay was caused by the default of the defendants. This covenant in the contract was, to a considerable extent, for the advantage and benefit of the defendants, and contemplated a prompt and speedy performance of the work contracted for. The plaintiff, being thus bound by his agreement, commenced and proceeded with the job without delay, and was liable in damages for a non-performance of the covenant, which obligated him to do so. The question arises whether there was not a corresponding obligation on the part of the defendants, implied from the contract itself, [36]*36that they were to have the building upon which the work was to be executed, in readiness for the plaintiff, so as to enable him to commence and fulfill this provision of the contract. Was it a provision which bound the plaintiff alone, with no agreement whatever on the part of the defendants that they were to have the building in such a condition as to enable him to fulfill the contract? If it was thus confined in its character, it would be a contract merely on one side, with no corresponding obligation, no duty to be performed on the part of the other contracting party. There would be no mutuality in such a covenant, if thus limited in its operation and effect. While on the one hand the plaintiff would be bound to incur liabilities, expend money and make arrangements to complete the contract and perform its conditions, and thereby subject himself to large expenses and losses; on the other, the defendants would be free from all liability, entirely exonerated from all obligations, and permitted to remain quiet, without doing a single thing to enable the plaintiff to perform his contract. .

Suppose the plaintiff had proceeded, as he had a right to do, and provided the materials necessary to perform the work, and the defendants failed to provide the building so that he could use them until they became depreciated in value, and caused serious loss to the plaintiff ; can there be a doubt that the defendants would be liable ? Again: suppose they had not provided any building whatsoever, so that the plaintiff was utterly unable to perform this condition, and was damaged greatly thereby; could they then be exonerated ? If they had a right to delay three months, then they were equally authorized to delay for a year, or forever, and the plaintiff was without any redress whatever. In such a view of the question, the contract was utterly void as to the defendants, while the plaintiff was bound to perform it, and was liable for any failure to do so.

I think the covenant on the part of the plaintiff, to commence the work and proceed therewith without delay, raised [37]*37an implied obligation, on the part of the defendants, to have the building in readiness for the plaintiff to fulfill this condition. By entering into such a contract the defendants agreed that they would be prepared for its performance, and it is to be assumed that the very thing essential for that purpose constituted an element of the agreement. It was a mutual covenant, binding upon both the parties; on the part of the plaintiff, that he would commence and proceed at once; and on the part of the defendants, that they would be ready to allow him to do so. Without such a mutual contract neither party could be bound; the plaintiff might take his own time, and proceed at any time he deemed best, and the defendants were not bound to juovide the building for the purpose of having the work done.

The principle decided in Holmes v. Groff, (3 M. (& W. 38,) appears to be applicable to the case at bar. There the defendants were not allowed a deduction under the contract from the contract price, for the non-completion of the building within the specified time, because they were unable to give possession of the building to the plaintiff for some weeks. There was no express provision in that contract, that the defendants should give possession, in so many words, but it was essential for its performance; such is precisely the case here. Until the building was in readiness, it was utterly out of the power of the plaintiff to perform.

It is said that there was no breach of the contract, and that it only imposed upon the defendants a single duty, and that was to pay the plaintiff for his work. I think otherwise. It would certainly he remarkable if, with a positive duty imposed upon the plaintiff, no corresponding obligations rested upon the defendants. Bor is it adding any thing to the written contract, to infer an implied obligation to do what was actually intended, and what was absolutely essential to give force, effect and vitality to it. Without this, it would be entirely useless and ineffective for any purpose. The case stands thus: The defendants desired that the plaintiff [38]*38should do the work in question; it could not'he performed without the building was in readiness for that purpose; the plaintiff agreed to commence the work, and proceed with it without delay. It necessarily follows that the defendants were to furnish an opportunity to carry out the contract, and impliedly agreed to do so. There being an obligation on the part of the defendants which was not performed by them, and the plaintiff having sustained damages by reason of such nonperformance, it follows that the action was properly brought.

It is said that the plaintiff waived the alleged breach of the contract, by going on without complaint or objection and completing the work, some three months after the execution of the contract. I think there was no waiver by proceeding with the contract, the failure of the defendants to have the building ready for him preventing his going on with it at an earlier day. He had a right to proceed with it afterwards, and compel the defendants to pay the increased expenses incurred by reason of the delay. Where a party was prevented from the performance of a contract within the stipulated time by the omission of the other, and subsequently performed the work agreed upon at a higher price, it was held, that he was not obliged to bring his action on the contract, but might resort to the quantum meruit to obtain his indemnity. (Dubois v. The Delaware and Hudson Canal Co., 4 Wend. 285.) The court also held in that case, that if the work was more expensive, the additional expense thus incurred should be added to the contract price. The loss may have been far greater to abandon the contract entirely, than to proceed with its execution so far as practicable; and under the authority cited, the actual damages would not be confined to his actual loss at that time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Rourke Engineering Construction Co. & Duit, Inc. v. City of New York
229 A.D. 261 (Appellate Division of the Supreme Court of New York, 1930)
John Johnson Construction Co. v. State
211 A.D. 512 (Appellate Division of the Supreme Court of New York, 1925)
Mack v. State
122 Misc. 86 (New York State Court of Claims, 1923)
Keechi Oil & Gas Co. v. Smith
1921 OK 168 (Supreme Court of Oklahoma, 1921)
Belmar Contracting Co. v. State
194 A.D. 69 (Appellate Division of the Supreme Court of New York, 1920)
Kleinfelter v. Granger
136 N.Y.S. 485 (New York Supreme Court, 1911)
Norcross v. . Wills
91 N.E. 803 (New York Court of Appeals, 1910)
Mikolajewski v. Pugell
62 Misc. 449 (New York Supreme Court, 1909)
Barnum v. Williams
115 A.D. 694 (Appellate Division of the Supreme Court of New York, 1906)
Security Trust & Life Insurance v. Ellsworth
109 N.W. 125 (Wisconsin Supreme Court, 1906)
Sanitary District of Chicago v. McMahon & Montgomery Co.
110 Ill. App. 510 (Appellate Court of Illinois, 1903)
Weeks v. Rector
67 N.Y.S. 670 (Appellate Division of the Supreme Court of New York, 1900)
Weeks v. Rector, Churchwardens & Vestrymen
56 A.D. 195 (Appellate Division of the Supreme Court of New York, 1900)
Mairs v. Mayor of New York
30 Misc. 384 (New York Supreme Court, 1900)
French v. City of Syracuse
18 Misc. 278 (New York Supreme Court, 1896)
Morier v. Moran
58 Ill. App. 235 (Appellate Court of Illinois, 1895)
Shute v. Hamilton
3 Daly 462 (New York Court of Common Pleas, 1871)
Currie v. White
6 Abb. Pr. 352 (The Superior Court of New York City, 1869)

Cite This Page — Counsel Stack

Bluebook (online)
43 Barb. 33, 1864 N.Y. App. Div. LEXIS 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allamon-v-mayor-of-albany-nysupct-1864.