Belmar Contracting Co. v. State

194 A.D. 69, 185 N.Y.S. 734, 1920 N.Y. App. Div. LEXIS 6601
Appellate Division of the Supreme Court of the State of New York·Decided November 18, 1920·Published·Cited by 1 cases

Opinions

H. T. Kellogg, J.:

On or about the 5th day of August, 1915, the State of New York, through its Commission of Highways, published a notice to contractors calling for bids for the improvement of one and seventeen one-hundredths miles of highway in the city of [71] Hudson, in the county of Columbia. The notice stated that maps, plans, specifications and estimates might be seen, and proposal forms might be obtained at the office of the Commission of Highways. It called “ the especial attention of bidders ” to the information for bidders,” the “ specifications ” and “ contract agreement” which were on file. The “ information for bidders ” to which attention was thus called in its first sentence provided that “ the specifications ’ and ‘ contract'agreement ’ adopted September 15, 1914, by the New York State Commission of Highways are to be considered as and shall form a part of the contract.” It also provided that “ Within ten days from the date of notice of award, the person or persons whose proposal is accepted will be required to execute the contract and furnish bonds for its faithful performance.” The claimant made a bid for the contract upon a printed form entitled itemized proposal " and therein made the following declaration: “ The undersigned also hereby declare that he had or they have carefully examined the plans, specifications, form of contract, and * * * understands that in signing this proposal he or they waive all right to plead any misunderstanding regarding the same.” The claimant also declared that it agreed “ to do and perform all the work necessary under the aforesaid conditions to complete the improvement of the aforementioned highways.” On the 25th day of August, 1915,' the claimant was notified in writing by the Highway Commission that it was low bidder and was directed to make arrangements to execute the contract agreement at once. On September 1, 1915, the claimant executed the formal contract for the highway improvement tendered to it by the Commission of Highways, which it must be assumed was the very contract which the information for bidders ” referred to, and which the claimant in its itemized proposal ” had asserted that it had carefully examined.” The claimant also submitted a bond for the performance of the contract which was satisfactory to the Commission of Highways. Thereupon Edward Duffy, Commissioner of Highways, wrote the letters O. K.” at the foot of the contract executed by the claimant, and beneath these letters subscribed his initials “ E. D.” Subsequently, on the 14th day of September, 1915, one W. I. Lee, Deputy Comptroller of the State of New York, approved the contract by the following words written there[72] upon: “ Approved Sept. 14, 1915, under the provisions of Chapter 342, Laws of 1913.”* Notwithstanding the execution of the contract by the claimant, the filing of a bond by it, the “ O. K.” of Commissioner Duffy, and the approval of the Comptroller, the contract was not thereafter formally signed by Commissioner Duffy until October 20, 1915. The reason for the delay given by officials of the Highway Commission was the fact that the city of Hudson had not until then made available its share of the moneys to be paid for the improvement. There was no provision of law requiring that the execution of the contract should be withheld until such a time. Moreover, the approval signed by the Comptroller on September 14, 1915, conclusively established that at this time all the necessary moneys were then on hand. After the contract had been executed by it the claimant repeatedly applied to the Commission of Highways requesting that it execute the contract, and was repeatedly told by its officials that they would get the same executed shortly, but that the city of Hudson was holding them up. The information for bidders ” provided that “ The work proposed under this contract must be completed on or before the eightieth working day.” The formal contract provided that time was of the essence of the contract, and that the contractor must pay ten dollars per day for each day’s delay in the performance of the work. Owing to the delay of the Highway Commission in appending its formal signature to the contract, or its delay in granting to the claimant permission promptly to begin work, the claimant was compelled to postpone operations until the spring of 1916, when it performed the contract at an increased cost as found by the Court of Claims of $10,716.05. It is undisputed, and was found by the Court of Claims, that if the contract had been promptly signed by the Highway Commission, and if claimant “ had been permitted to begin construction within a reasonable time after claimant’s contract agreement and bond had been delivered and accepted by the Highway Commission, and approved by the Comptroller ” it would have had time to complete the contract in the fall of 1915. The claimant having performed its contract in the [73] year 1916, thereafter filed this claim for damages on account of the delays in performance occasioned by the Highway Commission. The Court of Claims dismissed the claim, and from its judgment of dismissal this appeal was taken.

Free access — add to your briefcase to read the full text and ask questions with AI

Belmar Contracting Co. v. State, 194 A.D. 69, 185 N.Y.S. 734, 1920 N.Y. App. Div. LEXIS 6601 (N.Y. Ct. App. 1920).

194 A.D. 69 (Belmar Contracting Co. v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Coughlan & Co. v. Frankel
216 A.D. 565 (Appellate Division of the Supreme Court of New York, 1926)