Barnum v. Williams

115 A.D. 694, 102 N.Y.S. 874, 1906 N.Y. App. Div. LEXIS 3049
Appellate Division of the Supreme Court of the State of New York·Decided November 21, 1906·Published·Cited by 4 cases

Opinion

Hirschberg, P. J., Hooker, Gaynor, Rich and Miller, JJ., concurred.

The following is the opinion of Charles H. Otis, Esq., referee: Otis, Beferee:

On the 11th day of January, 1902, the plaintiff’s assignor, Hecla Iron Works, wrote a letter to the defendant,. John T. Williams, making a bid for the fabrication and erection of certain light and ornamental ironwork, offering, for the sum of $18,810, to furnish material and perform the labor to complete certain work, as shown by the drawings of the defendant on his premises in William street, known as the Lord’s Court Building.

On the . 21st day of January, 1902, Hecla Iron Works wrote a second letter to the. defendant, in which it stated that it would agree to complete its work in from five to six weeks’ time should it be awarded the contract; and would further agree to have all the material ready for the new stories to be put in place as fast as the steel frame was in place to receive it; and could proceed with the work of the lower stories at once, and could start the setting of the same in two weeks’ time and complete as above stated.

The propositions embodied in these two letters were accepted by the defendant by his letter of January twenty-third.

The work in question involved the ornamental work required for four additional stories which the .defendant was adding to Lord’s Court Building. There was also the iron work for three elevators extending from the ground floor to the new roof, and certain other smaller items which it is needless to mention.

Hecla Iron Works proceeded immediately upon the receipt of the letter of January twenty-third from the defendant with the fabrica[696] tiori'of the stairs for the additional five stories,which was the only part of the work upon which in could enter until it liad received plans from the defendant. The Hecla IronWorks was able to proceed with this portion of the work, for the reason that it had constructed the stairs for the original building and had in its possession the necessary data to enable it to proceed at once With the drawings and fabrication of these stairs. They were completed and put in storage on March 3, 1902.

On February twentieth a ■ formal contract was entered into between the parties, embodying these general features, and fixing April 1,1902, as the time within which the work to be performed by. Hecla Iron Works should be completed. As a matter of fact, beyond the construction of the stairs for the additional stories,Hecla Iron Works was not able to do anything whatever towards the performance of its contract until after the date fixed in the contract for its completion, April first, by reason, of delays occasioned by the defendant.

From time to time drawings were sent forward by the defendant to Hecla Iron Works for various parts of the construction.

On April eleventh, ten days after the time when the contract was by its terms to have.been completed, the defendant sent a revised plan for the.general layout of the elevator beams, framing and partitions. The final plans necessary for the construction called for by the contract were not sent to the Hecla Iron Works until June 24, 1902. It is in evidence and undisputed that Hecla Iron Works would. have been able to complete its contract by April first, the ■ time mentioned in the contract, had the necessary work, in the building and the reception of the plans by the Hecla Iron Works been ■ sufficiently prompt and sufficiently far advanced to enable Hecla Iron Works to proceed with its work, and it is certain that all such work could have been completed by Hecla Iron Works long prior to' July seventh, the date of the strike hereinafter referred to.

I am of opinion that all prior correspondence between Hecla Iron Works and the defendant was merged in the contract which was signed February twentieth, and regard the letters prior to the signing of the contract as material to this issue only as indicating the time within which Hecla Iron Works had the right to receive the necessary''information and to have the building sufficiently far [697] advanced to enable it to proceed without delay with its work in order to comply with the date fixed in the contract, which was undoubtedly framed in relation to the prior correspondence upon the subject.

The Hecla Iron Works, in every particular, had proceeded with its work with the utmost diligence, and for several months substantially all of the material required to complete the work had been in storage in the storehouse of Hecla Iron Works, and could have been set in a very short time, provided the building had been ready to receive it. This work, especially the elevator fronts, is of a character which cannot be set in the building until all the other contractors are practically out of it. In order to set it properly, the building must be what is termed “ broom clean,” although Hecla Iron Works had done a part of this work in advance of that condition and assumed the risk of the consequences. Substantially all the material required for the building had been fabricated, and practically all of such material had been actually delivered at the premises before July seventh, and on that day, when the building was first ready to receive them and when work could first be done in the matter of erecting the stairs, the stairs were sent to x the building, but not delivered, because prevented by a strike of the employees of the Hecla Iron Works, which was called at noon of that day.

At this point in the history of the transaction we find the Hecla Iron Works ready, willing and anxious to do all the work called for by the contract. We find that up to that date they had followed closely the other contractors, and sometimes anticipated them in the due order of their work, and there is no evidence that there was any moment during the period from January twenty-third until July seventh when there was any work on the building which could have been done by the Hecla Iron Works which was not done promptly.

On July seventh all of the employees of the Hecla Iron Works struck work on this building upon some alleged or pretended grievance that the defendant had failed to pay some other contractor some amount alleged to be due to him. Theoe employees were members of Local No. 2 Bridge and Structural Iron Workers of America.. All competent outside employees in the line of work of the Hecla Iron Works were members of this organization. Only [698] the building in question was struck, and doubtless the true reason for the strike was a means to enable one Sam Parks, a delegate 'of this organization, to extort sums either from the owner of,the building-or from the Hecla Iron Works. Certainly the strike was not called for any alleged or pretended grievance against Hecla Iron Works. No other work then in process by Hecla Iron Works was struck by the members of this organization. During the period of the strike it was-impossible for the Hecla Iron Works to proctire any competent men with whom to complete the building, as is evidenced by the later efforts on the part of the defendant to complete the building himself. ■

Free access — add to your briefcase to read the full text and ask questions with AI

Barnum v. Williams, 115 A.D. 694, 102 N.Y.S. 874, 1906 N.Y. App. Div. LEXIS 3049 (N.Y. Ct. App. 1906).

115 A.D. 694 (Barnum v. Williams) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Philip Zweig & Sons, Inc. v. Tuscarora Construction Co.
50 A.D.2d 1069 (Appellate Division of the Supreme Court of New York, 1975)
O'Rourke Engineering Construction Co. & Duit, Inc. v. City of New York
229 A.D. 261 (Appellate Division of the Supreme Court of New York, 1930)
Beskin v. State
119 Misc. 209 (New York State Court of Claims, 1922)
Belmar Contracting Co. v. State
194 A.D. 69 (Appellate Division of the Supreme Court of New York, 1920)